Operation Research & Supply Chain (ME-703 (A)) - Important Questions
-
Unit 17 Marks High Priority
Solve the following LPP by simplex method: Maximize Z = 20x1 + 25x2 subject to 12x1 + 16x2 <= 100, 16x1 + 8x2 <= 80, x1, x2 >= 0.
Predicted for DEC-2026
-
Unit 17 Marks High Priority
Determine an initial basic feasible solution to a transportation problem using Vogel's approximation method.
Predicted for DEC-2026
-
Unit 17 Marks High Priority
A small manufacturer employs 15 skilled men and 30 semi-skilled men and makes an article in two qualities, a deluxe model and an ordinary model. Formulate the LPP to maximize profit subject to skilled and semi-skilled labour hour constraints.
Predicted for DEC-2026
-
Unit 17 Marks High Priority
Explain degeneracy in a transportation problem, why it occurs, and how to resolve it.
Predicted for DEC-2026
-
Unit 17 Marks High Priority
Give the mathematical formulation of the assignment problem and explain how it differs from the transportation problem.
Predicted for DEC-2026
-
Unit 27 Marks High Priority
Explain the flow of materials, money, and information in a typical supply chain with an example.
Predicted for DEC-2026
-
Unit 27 Marks High Priority
Explain the Bull-Whip effect in supply chain management.
Predicted for DEC-2026
-
Unit 27 Marks High Priority
Explain the importance of outbound logistics in supply chain management.
Predicted for DEC-2026
-
Unit 37 Marks High Priority
Find the EOQ / optimum lot size and associated minimum cost, number of orders and cycle time for the classical no-shortage inventory model with deterministic demand.
Predicted for DEC-2026
-
Unit 37 Marks High Priority
What is ABC analysis in inventory control? Describe it in detail with the help of graph.
Predicted for DEC-2026
-
Unit 37 Marks High Priority
What is Just-In-Time (JIT) manufacturing? Explain its relationship with Lean Manufacturing principles.
Predicted for DEC-2026
-
Unit 47 Marks High Priority
The service time at a counter has exponential distribution with mean service rate of 20 customers per hour. Find the probability that service time exceeds 15 minutes / is within a given number of minutes.
Predicted for DEC-2026
-
Unit 47 Marks High Priority
Solve the following game graphically.
Predicted for DEC-2026
-
Unit 57 Marks High Priority
Draw the project network diagram from given activities/durations and identify the critical path and project duration.
Predicted for DEC-2026
-
Unit 514 Marks High Priority
Write short notes on any two: (i) CPM vs PERT (ii) Fulkerson's rule for numbering events (iii) Phases of project management.
Predicted for DEC-2026