UNIT 2: ENERGY AUDIT & MANAGEMENT - SHORT NOTES
I. Fundamentals of Energy Audit and Management
Definition and Objectives
-
Energy Audit: A systematic process to evaluate energy consumption, identify inefficiencies, and recommend conservation measures. It is the "first step" towards energy management.
-
Objectives:
-
Quantify energy use and costs.
-
Identify energy wastage and inefficiencies.
-
Recommend Energy Conservation Measures (ECMs).
-
Establish baseline for future monitoring.
-
Ensure compliance with regulations (e.g., BEE).
-
Types of Energy Audits
| Feature | Preliminary Energy Audit | Detailed Energy Audit |
|---|---|---|
| Scope | Walk-through survey, quick assessment. | In-depth, data-intensive study. |
| Data | Limited, based on visual inspection & utility bills. | Extensive, includes measurements, sub-metering, load profiling. |
| Output | List of obvious ECMs, rough cost/savings estimates. | Detailed report with precise calculations, technical specifications, implementation plan, ROI analysis. |
| Duration | 1-2 days. | Several weeks/months. |
| Depth | Low/Medium. | High. |
Steps for Energy Audit (Institutional Organization)
-
Planning & Organizing: Form audit team, define scope, secure management commitment.
-
Data Collection: Gather utility bills (electricity, fuel, water) for 1-3 years, building plans, equipment inventory.
-
Walk-through Survey: Visual inspection to identify major areas of consumption/wastage.
-
Detailed Measurement & Verification (M&V): Use instruments to measure actual energy use of key systems (lighting, HVAC, motors).
-
Data Analysis: Calculate specific energy consumption (SEC), benchmark against standards, identify deviations.
-
Identify ECMs & Technical Feasibility: List potential measures (e.g., LED retrofit, VFD installation, boiler tuning).
-
Economic Analysis: Calculate Simple Payback Period (SPP), Net Present Value (NPV), Internal Rate of Return (IRR) for each ECM.
-
Report Preparation & Presentation: Compile findings, recommendations, action plan, and management summary.
Roles and Responsibilities
-
Energy Manager:
-
Duties: Implement energy policy, coordinate audits, monitor consumption, promote awareness, track ECM implementation, report to top management.
-
Key Role: In-house champion for continuous energy management.
-
-
Energy Auditor:
-
Duties: Conduct independent/third-party audit, verify data, apply standards/formulas, prepare objective audit report, certify compliance (if designated by BEE).
-
Key Role: External expert providing impartial assessment.
-
Bureau of Energy Efficiency (BEE) Regulations
-
Manners & Intervals (for Designated Consumers - large industries/commercial buildings):
-
Frequency: Every 3 years.
-
Compliance: Must be conducted by a BEE-certified energy auditor.
-
Submission: Audit report (Form 1) must be submitted to BEE and State Designated Agency (SDA) within the stipulated time.
-
Verification: BEE may conduct random verification audits.
-
Equipment and Instruments for Energy Auditing
| Instrument | Primary Use | Working Principle / Key Parameter Measured |
|---|---|---|
| Clamp-on Power Meter | Electrical load analysis | Measures voltage, current, power (kW), power factor (PF), harmonics without breaking circuit. |
| Thermal Imager (Infrared Camera) | Heat loss detection, insulation gaps | Detects infrared radiation to create thermal map showing temperature differentials. |
| Flue Gas Analyzer | Boiler/furnace combustion efficiency | Measures O₂, CO, CO₂, stack temperature to calculate excess air and heat loss. |
| Lux Meter | Lighting level assessment | Measures illuminance (lux) at work planes. |
| Ultrasonic Flow Meter | Liquid/ gas flow measurement | Uses sound waves to measure flow rate in pipes without insertion. |
| Tachometer | Motor/fan speed measurement | Measures RPM (Rotations Per Minute) optically or mechanically. |
Barriers in Energy Auditing & Elimination Strategies
| Barrier | Elimination Strategy |
|---|---|
| Lack of Top Management Commitment | Demonstrate financial benefits (NPV, IRR), align with corporate sustainability goals. |
| Insufficient/Inaccurate Data | Implement sub-metering, use data loggers, maintain proper records. |
| High Initial Investment Perception | Use Life Cycle Costing (LCC) to show long-term savings, explore ESCO financing models. |
| Lack of Technical Expertise | Train in-house energy manager, hire BEE-certified auditors. |
| Operational Disruption | Plan audits during off-peaks/shutdowns, use non-intrusive instruments. |
| Fear of Job Loss | Emphasize efficiency improvement, involve operators in process optimization. |
General Principles of Energy Management
-
Management Commitment & Policy: Top-down mandate.
-
Baseline Establishment: Measure and document current energy performance.
-
Monitoring & Targeting (M&T): Regular tracking against benchmarks.
-
Energy Conservation Opportunities (ECOs) Identification: Systematic review of all energy-using systems.
-
Implementation & Verification: Execute ECMs and Measure & Verify (M&V) savings.
-
Continuous Improvement (PDCA Cycle): Plan-Do-Check-Act cycle for ongoing optimization.
-
Awareness & Training: Engage all personnel.
II. Environmental Aspects of Energy
Environmental Impact of Energy Consumption
| Energy Source | Key Environmental Impacts |
|---|---|
| Non-Renewable (Coal, Oil, Gas) | • Air Pollution: SOₓ, NOₓ, PM (particulate matter), CO₂ (greenhouse gas).<br>• Water Pollution: Ash slurry, thermal pollution.<br>• Land Degradation: Mining, drilling waste.<br>• Major Contributor to climate change (CO₂). |
| Renewable (Solar, Wind, Hydro, Biomass) | • Solar/Wind: Low operational emissions; impacts from manufacturing (silicon, rare earths) and land use.<br>• Hydro: Alters river ecosystems, affects fish migration, methane from reservoirs.<br>• Biomass: Can be carbon-neutral if sustainably sourced; air pollution from combustion (PM). |
Elements of Systematic Environmental Assessment
-
Goal & Scope Definition: Define purpose, system boundaries (cradle-to-gate, cradle-to-grave).
-
Inventory Analysis (LCI): Quantify all material/energy inputs and environmental releases (emissions, effluents, solid waste) across the life cycle.
-
Impact Assessment (LCIA): Evaluate potential environmental impacts (global warming, acidification, eutrophication) using inventory data.
-
Interpretation: Summarize results, identify significant issues, draw conclusions, and recommend improvements.
III. Electrical Systems and Power Quality
Power Factor (PF)
-
Definition: PF = $$\displaystyle \frac{\text{Real Power (kW)}}{\text{Apparent Power (kVA)}} = \cos\phi $$. It measures effectiveness of power utilization.
-
Importance & Benefits of PF Improvement:
-
Reduces kVA demand → lowers electricity bill (if billed on kVA or has PF penalty).
-
Decreases system current → reduces I²R losses in cables/transformers.
-
Improves voltage regulation.
-
Increases system capacity (existing infrastructure can serve more load).
-
-
Causes of Low PF:
-
Inductive loads: Induction motors, transformers, fluorescent ballasts, welding sets.
-
Lightly loaded motors (operate at very low PF).
-
-
Disadvantages of Low PF:
-
Higher current for same kW → larger cable sizes, higher losses.
-
Penalty charges from utility.
-
Poor voltage regulation, overheating of equipment.
-
PF Improvement using Capacitor Banks
-
Principle: Capacitors supply leading kVAr to cancel lagging kVAr from inductive loads.
-
Optimal Location:
-
Individual Motor Compensation: Capacitor bank at motor terminals (best for large, constant-speed motors).
-
Bus Bar/Common Compensation: At distribution board (good for multiple small loads).
-
Central/Utility Point Compensation: At main incoming (improves overall PF, but doesn't reduce distribution losses).
!TIP: For energy & cost saving, locate capacitors as close as possible to the inductive load.
-
-
Sizing Considerations:
-
Calculate existing kVAr demand from kVA, kW, PF.
-
Required capacitor kVAr = kVAr_initial - kVAr_target.
-
Consider harmonics (detuning reactors may be needed).
-
Avoid over-correction (leading PF).
-
PF Improvement & Penalty Calculation (Example from Past Paper)
Given: Max Demand = 800 kVA, Avg PF = 0.80 lag, Min Required PF = 0.90 lag, Penalty = Rs 20,000 per 1% dip. Capacitor Installed: 100 kVAr.
Step 1: Calculate Initial kVAr & kW
$$ \text{kW} = \text{kVA} \times \text{PF} = 800 \times 0.80 = 640 \text{ kW} $$
$$ \text{Initial kVAr} = \text{kVA} \times \sin\phi = 800 \times \sqrt{1 - 0.80^2} = 800 \times 0.6 = 480 \text{ kVAr} $$
Step 2: Calculate New kVAr after 100 kVAr capacitor
$$ \text{New kVAr} = 480 - 100 = 380 \text{ kVAr} $$
Step 3: Calculate New kVA & PF
$$ \text{New kVA} = \sqrt{\text{kW}^2 + \text{New kVAr}^2} = \sqrt{640^2 + 380^2} = \sqrt{409600 + 144400} = \sqrt{554000} \approx 744.3 \text{ kVA} $$
$$ \text{New PF} = \frac{\text{kW}}{\text{New kVA}} = \frac{640}{744.3} \approx 0.86 \text{ lag} $$
Step 4: Check Penalty
Min Required PF = 0.90. New PF = 0.86 < 0.90. Dip from 0.90 = 0.90 - 0.86 = 0.04 = 4%.
$$ \text{Penalty} = 4 \times 20,000 = \boxed{\text{Rs. 80,000}} $$
!TIP: PF penalty is usually calculated on the dip from the specified minimum PF, not from the original PF.
Harmonics
-
Sources/Equipment:
-
Non-linear loads: VFDs (Variable Frequency Drives), UPS systems, computers, LED drivers, SMPS, arc furnaces, rectifiers.
-
Cause: These devices draw non-sinusoidal current (rich in multiples of fundamental frequency, e.g., 5th, 7th, 11th harmonics).
-
-
Effects:
-
Heating: In motors, transformers, cables (core/copper losses increase).
-
Nuisance Tripping: Of circuit breakers, protective relays.
-
Capacitor Failure: Resonance amplification, overheating.
-
Neutral Overload: In 3-phase 4-wire systems (triplen harmonics add in neutral).
-
Metering Inaccuracies.
-
Communication Interference.
-
-
Harmonic Distortion Evaluation:
-
Measure voltage/current waveforms with power quality analyzer.
-
Perform FFT (Fast Fourier Transform) to decompose into harmonic components.
-
Calculate Total Harmonic Distortion (THD):
-
$$ \text{THD}_V (\%) = \frac{\sqrt{V_2^2 + V_3^2 + ... + V_n^2}}{V_1} \times 100 $$
$$ \text{THD}_I (\%) = \frac{\sqrt{I_2^2 + I_3^2 + ... + I_n^2}}{I_1} \times 100 $$
(Where subscript 1 = fundamental, 2,3...n = harmonic orders).
4. Compare with **IEEE 519 standards** for limits.
HT vs. LT Systems
| Feature | HT (High Tension) | LT (Low Tension) |
|---|---|---|
| Voltage Level | > 1000 V (Typically 11kV, 33kV) | ≤ 1000 V (Typically 415V, 230V) |
| Application | Power transmission, large industrial loads. | Distribution, small industries, commercial, residential. |
| Current | Lower for same power (P = √3 V I cosφ). | Higher. |
| Insulation Cost | Higher (per unit length). | Lower. |
| Safety | Requires more safety measures. | Relatively safer. |
| Transformer Losses | Lower percentage losses (due to higher voltage). | Higher percentage losses. |
Transformer Losses & Minimization
| Loss Type | Cause | Minimization Technique |
|---|---|---|
| Core (Iron) Loss | Magnetizing current, hysteresis & eddy currents in core. | Use high-grade silicon steel (CRGO), thin laminations, amorphous core. Constant (independent of load). |
| Copper (Load) Loss | I²R heating in windings. | Use larger cross-section conductors (aluminum or copper), improve jointing. Varies with square of load. |
| Stray Loss | Leakage flux causing eddy currents in tank, structures. | Proper design, shielding, use of low-loss materials. |
| Dielectric Loss | Insulation (oil) leakage current. | Use high-quality insulating oil, maintain oil quality (dry, clean). |
!TIP: For lightly loaded transformers, core loss dominates. For heavily loaded, copper loss dominates. Select transformer with lowest total loss at typical load factor (often 50-70%).
IV. Thermal Systems and Steam Management
Boiler Efficiency
- On GCV (Gross Calorific Value) Basis:
$$ \eta_{\text{GCV}} = \frac{\text{Steam Output (kg/hr)} \times (h_s - h_w)}{\text{Fuel Input (kg/hr)} \times \text{GCV}} \times 100\% $$
(Where $$\displaystyle h_s $$ = enthalpy of steam, $$\displaystyle h_w $$ = enthalpy of feed water).
- On NCV (Net Calorific Value) Basis:
$$ \eta_{\text{NCV}} = \frac{\text{Steam Output} \times (h_s - h_w)}{\text{Fuel Input} \times \text{NCV}} \times 100\% $$
> **Relationship**: $$\displaystyle \eta_{\text{NCV}} > \eta_{\text{GCV}} $$ because NCV excludes latent heat of vaporization in fuel moisture.
- Direct Method (Input-Output Method):
$$ \eta = \frac{\text{Energy Output (Heat in Steam)}}{\text{Energy Input (Heat in Fuel)}} \times 100\% $$
Simple, measures actual performance.
- Indirect Method (Heat Loss Method):
$$ \eta = 100\% - (\text{Sum of all % losses}) $$
Losses: Stack loss, dry flue gas loss, moisture in fuel/air, unburnt carbon, radiation/convection.
More detailed, identifies *why* efficiency is low.
Part-Load Efficiency & Multiple Boilers Operation
-
Part-Load Efficiency: Boiler efficiency decreases at part-load due to:
-
Higher radiation/convection losses (constant).
-
Higher excess air (often not controlled down at low load).
-
Poor combustion stability.
-
-
Multiple Boilers Strategy (Example from Past Paper):
-
Scenario: Two identical 15 TPH boilers (82% full load eff.), part-load eff. at 75% = 78%, at 45% = 66%. Need 20 TPH.
-
Option 1: Both at 10 TPH (66.7% load). Eff. ≈ interpolate between 75% & 45%? Not linear! Usually, efficiency drops sharply below 50%. Assume ~70%? (Given data: 75% load=78%, 45% load=66%. At 66.7%, likely ~72%).
-
Option 2: One at 15 TPH (100% load, 82%), other at 5 TPH (33% load, eff. << 66%, say ~50%).
-
Calculation:
-
Total Fuel for Option 1: (20 TPH steam) / (Avg Eff. ~72%) = ~27.8 TPH fuel equivalent.
-
Total Fuel for Option 2: (15 TPH steam / 82%) + (5 TPH steam / 50%) = 18.29 + 10 = 28.29 TPH fuel equivalent.
-
-
Conclusion: Running both at higher part-load (Option 1) saves fuel (~1.7% saving). Never run a boiler below ~50% load if another can share.
-
Steam Distribution Systems & Common Losses
-
Distribution: Steam generated → header → distribution pipes → end-use.
-
Common Losses:
-
Radiative/Convective Heat Loss from uninsulated pipes.
-
Pressure Drop → requires higher generation pressure → lower thermodynamic efficiency.
-
Condensate Drainage (without recovery) → loss of hot water & heat.
-
Steam Leaks from joints, valves.
-
Flash Steam from high-pressure condensate dumped to low-pressure drain.
-
Steam Traps
-
Working Principle: Automatic valve that discharges condensate, air, and non-condensable gases while preventing steam passage.
-
Types & Principles:
| Type | Principle | Typical Application | | :--- | :--- | :--- | | Mechanical (Inverted Bucket, Float & Thermostatic) | Uses buoyancy of condensate (density difference). | General purpose, high capacity. | | Thermostatic (Bimetallic, Bellows) | Uses temperature difference (steam ~hotter than condensate). | Drip legs, tracer lines. | | Thermodynamic (Disc,活塞) | Uses kinetic energy difference of steam vs. condensate. | Main steam lines, high pressure. |
-
Performance Assessment Methods:
-
Visual/Audio Inspection: Listen for continuous flow (steam blow) or no discharge (blockage).
-
Temperature Measurement: Upstream & downstream temp. A cold trap (blocked) or hot trap (blowing steam) indicates failure.
-
Ultrasonic Testing: Detects high-frequency sound of steam leakage.
-
Infrared Thermography: Shows temperature profile; a cold downstream may indicate blockage, hot downstream may indicate live steam loss.
-
Condensate Recovery & Flash Steam Utilization
-
Condensate Recovery:
-
Process: Collect hot condensate from steam traps → return to boiler feed water tank via condensate return lines.
-
Benefits: Saves water, heat (enthalpy), and water treatment chemicals. Improves boiler efficiency.
-
-
Flash Steam Utilization:
-
Process: High-pressure condensate (e.g., from 10 bar process) discharged to a flash vessel at lower pressure. Some condensate flashes into low-pressure steam.
-
Utilization: This flash steam can be used for low-pressure applications (e.g., space heating, domestic hot water, process pre-heat).
-
Benefit: Recovers latent heat that would otherwise be lost.
-
Thermic Fluid Heating Systems
-
Working Principle: Uses a heat transfer oil (thermic fluid) heated in a furnace/coil → circulated by pump → heat exchange with process → returns to heater. Closed loop, no phase change.
-
Advantages over Steam:
-
No pressure → no boiler regulations, no steam traps, no condensate recovery needed. Safer.
-
High temperature at low pressure (e.g., 300°C at 5 bar vs. steam needs ~70 bar).
-
Precise temperature control.
-
No scale/rust issues (if oil maintained).
-
Disadvantages: Fire risk (oil leak), higher initial cost, oil degradation over time.
-
Furnaces
-
Concept: Enclosed chamber for direct heat transfer from combustion to material (solid, liquid, gas).
-
Classifications:
-
By Heat Source: Oil/gas fired, coal fired, electric.
-
By Material: Metal heating (reheating, annealing), non-metal (glass, ceramic).
-
By Operation: Batch, continuous.
-
By Waste Heat Recovery: Regenerative, recuperative.
-
-
Role in Industries (e.g., Steel): Primary energy consumer for reheating slabs/billets before rolling.
-
Energy Efficiency Considerations:
-
Combustion Efficiency: Optimize excess air (minimize stack loss).
-
Heat Recovery: Use recuperators (sensible heat) or regenerators (sensible + latent) from flue gases.
-
Insulation: High-quality lining to minimize skin losses.
-
Furnace Pressure: Slight negative pressure prevents air infiltration (which increases excess air).
-
Soaking Time: Minimize to reduce heat loss.
-
Insulation: Economic Thickness
-
Concept: The insulation thickness that minimizes total annual cost (sum of capital cost of insulation + annualized heat loss cost).
-
Process:
-
Calculate heat loss per unit area for various thicknesses (using thermal conductivity
k). -
Calculate total annual heat loss cost = (Heat loss rate) × (Operating hours) × (Fuel cost/unit energy).
-
Calculate annualized capital cost of insulation (using CRF - Capital Recovery Factor).
-
Sum (2) + (3) for each thickness.
-
Choose thickness with minimum total cost.
!TIP: Beyond economic thickness, savings in heat loss < additional insulation cost.
-
Combustion Optimization: Minimum Excess Air
-
Advantages:
-
Reduces stack loss (less hot flue gas carrying away heat).
-
Reduces fan power consumption (less gas volume to move).
-
Reduces NOₓ formation (less available N₂ at high temp).
-
-
Methods to Achieve:
-
Regular Tuning: Use flue gas analyzer to measure O₂/CO in flue gas. Adjust air dampers to achieve optimal O₂ level (e.g., 3-5% for gas, 5-8% for coal).
-
Maintain Burners: Clean nozzles, ensure proper atomization (oil), correct air-fuel mixing.
-
Control Combustion Air Temperature: Preheat if possible (using waste heat).
-
Use Oxygen Trim Control: Automated system adjusting air based on real-time O₂ measurement.
-
Refrigeration Plants: Performance & Efficiency Factors
-
Key Performance Indicator: Coefficient of Performance (COP) = $$\displaystyle \frac{\text{Refrigeration Effect (kW)}}{\text{Compressor Input Power (kW)}} $$.
-
Factors Affecting COP:
-
Evaporator Temperature: Lower evaporator temp → lower COP. Operate at highest feasible evaporator temp.
-
Condenser Temperature: Higher condenser temp (due to fouling, high ambient) → lower COP. Keep condensers clean, use cooling tower optimization.
-
Compressor Efficiency: Mechanical, volumetric, isentropic efficiency. Regular maintenance.
-
Expansion Device: Proper sizing (TXV, EEV better than capillary).
-
Suction/Discharge Pressure Drop: Minimize pipe sizing losses.
-
Refrigerant Charge: Correct charge level.
-
Sub-cooling & Superheating: Optimize for system protection, not excessive.
-
-
Energy Conservation Opportunities:
-
Temperature Optimization: Raise evaporator setpoint, lower condenser setpoint (within limits).
-
Preventive Maintenance: Clean coils, check refrigerant charge, replace filters.
-
Variable Speed Drives (VSDs) on compressor motors for part-load.
-
Heat Recovery: Use condenser heat for water heating.
-
Insulation: On cold pipes/equipment.
-
V. Motors, Pumps, and Fans
Energy-Efficient Motors (Premium Efficiency Motors)
-
Construction Differences from Standard Motors:
-
More Copper: Larger cross-section windings → lower I²R loss.
-
Better Steel: Higher grade, thinner laminations (CRGO) → lower core loss.
-
Optimized Design: Longer air gap, improved cooling fan design, better bearings.
-
Tighter Tolerances: Precision manufacturing.
-
-
Advantages:
-
Higher Efficiency (typically 2-5% points higher) across load range.
-
Lower Operating Temperature → longer insulation/bearing life.
-
Lower Energy Costs → higher upfront cost offset by savings.
-
Better Power Factor (often).
-
Smaller Size/Weight for same output (due to better materials).
-
-
Key Features: IE3/IE4 efficiency class (as per IEC/IS), higher service factor (1.15), better starting torque.
Motor Performance Evaluation & Part-Load Efficiency
-
Loading Calculation from Input Parameters:
Given: Voltage (V), Current (I), Power Factor (PF), Rated Output (P_rated).
$$ \text{Input Power (kW)} = \sqrt{3} \times V \times I \times PF \times 10^{-3} \quad (\text{for 3-phase}) $$
$$ \text{Load (\%)} = \frac{\text{Input Power} \times \text{Full Load Efficiency}}{\text{Rated Output (kW)}} \times 100\% $$
> **Note**: Use **nameplate efficiency** to convert input to output. If unknown, assume ~90% for estimation.
-
Example from Past Paper:
Motor: 20 kW, Full Load Eff. = 90%.
Input: 440V, 10A, PF=0.78.
Input kW = $$\displaystyle \sqrt{3} \times 0.440 \times 10 \times 0.78 \times 10^{-3} = 1.732 \times 0.440 \times 10 \times 0.78 \times 0.001 \approx 5.95 $$ kW.
Output kW at this load = $$\displaystyle 5.95 \times 0.90 = 5.36 $$ kW.
% Loading = $$\displaystyle \frac{5.36}{20} \times 100\% = \boxed{26.8\%} $$.
!TIP: Motor efficiency at part-load is lower than full-load efficiency. A motor at 26% load may have eff. ~80%, not 90%. So actual loading might be slightly higher than calculated above.
Pumping Systems: Performance & Energy Conservation
-
Factors Affecting Pump Performance:
-
System Curve: Static head, friction head (pipe length, fittings, roughness), equipment pressure drop.
-
Pump Curve: Head vs. Flow, efficiency vs. Flow, Best Efficiency Point (BEP).
-
NPSH (Net Positive Suction Head): Cavitation risk if insufficient.
-
Fluid Properties: Viscosity, density.
-
-
Energy Conservation Opportunities:
-
Operate at BEP: Avoid running far off BEP (low efficiency, cavitation, vibration).
-
Reduce System Head: Clean pipes, reduce unnecessary fittings, increase pipe diameter (reduces friction loss ∝ 1/D⁵).
-
Reduce Flow Requirement: Check process need; throttling valves waste energy.
-
Install Variable Speed Drives (VSDs): Most effective for variable flow systems. Affinity Laws:
-
$$ Q \propto N, \quad H \propto N^2, \quad P \propto N^3 $$
(Where Q=flow, H=head, N=speed, P=power). **Small speed reduction saves large power**.
5. **Parallel Operation**: Use multiple pumps only when needed; **stagger operation** to keep pumps near BEP.
6. **Replace Inefficient Pumps**: With **high-efficiency models**, correct size.
7. **Prevent Leakage**: Repair seals, glands.
Fan Systems: Design, Selection & Efficient Operation
-
Design & Selection Criteria:
-
Determine system curve (static pressure vs. flow) accurately.
-
Select fan operating point near peak efficiency on its curve.
-
Consider fan type (centrifugal vs. axial) based on pressure/flow requirement.
-
Account for future expansion (margin ~10-15%).
-
-
Performance Evaluation:
-
Measure flow (CFM/m³/s), static pressure (mmWG/Pa), input power (kW).
-
Calculate Fan Efficiency:
-
$$ \eta_{\text{fan}} = \frac{\text{Air Power (kW)}}{\text{Shaft Power (kW)}} \times 100\% $$
$$ \text{Air Power} = \frac{Q \times SP}{102 \times \eta_{\text{total}}} \quad (\text{in kW, Q in m³/s, SP in mmWG}) $$
-
Efficient System Operation:
-
Avoid Throttling/Damper Control: Wastes energy. Use inlet guide vanes or VSDs for flow control.
-
Reduce System Resistance: Clean ducts, remove unnecessary bends/filters.
-
Operate at Highest Efficiency Point: Monitor and adjust.
-
Use Multiple Fans: For variable loads, operate fewer fans at higher efficiency point.
-
VI. Lighting Systems and Conservation
Scope for Energy Conservation in Lighting
-
Replace inefficient lamps: Incandescent → CFL → LED.
-
Optimize lighting levels: Use task lighting, reduce overlit areas.
-
Improve maintenance: Clean fixtures, lamps, replace old lamps (lumen depreciation).
-
Use daylight: Daylight harvesting with photosensors.
-
Install occupancy sensors (vacancy sensors) in low-usage areas.
-
Use efficient ballasts: Electronic vs. magnetic.
-
Select proper luminaires: High reflectance, good optical control.
-
Implement lighting control strategies: Zoning, scheduling, dimming.
LED Lighting: Advantages & Applications
-
Advantages:
-
Very High Efficacy (100-150+ lm/W vs. 15-60 for incandescent/CFL).
-
Long Life (50,000+ hours).
-
Instant On, no warm-up.
-
Dimmable (with compatible drivers).
-
Rugged, no filament.
-
Directional light (no need for reflectors).
-
Low heat emission.
-
Environmentally friendly (no mercury).
-
-
Applications: General lighting, street lighting, automotive, indicators, displays, horticulture.
Lighting Calculations & Retrofit Analysis
-
Illumination Level (Lux): $$\displaystyle E = \frac{\text{Luminous Flux (lm)}}{\text{Area (m²)}} $$.
-
Energy & Cost Savings from Retrofit:
Step 1: Calculate annual energy consumption of existing system.
$$ \text{Energy}_{\text{old}} = \text{No. of Lamps} \times \text{Wattage}_{\text{old}} \times \text{Operating Hours} \times 10^{-3} \text{ (kWh)} $$
**Step 2**: Calculate annual energy of new system.
$$ \text{Energy}_{\text{new}} = \text{No. of Lamps} \times \text{Wattage}_{\text{new}} \times \text{Operating Hours} \times 10^{-3} \text{ (kWh)} $$
**Step 3**: Annual Savings.
$$ \text{Energy Savings} = \text{Energy}_{\text{old}} - \text{Energy}_{\text{new}} \text{ (kWh)} $$
$$ \text{Cost Savings} = \text{Energy Savings} \times \text{Electricity Rate (Rs/kWh)} $$
- Simple Payback Period (SPP):
$$ \text{SPP} = \frac{\text{Total Investment Cost (Rs)}}{\text{Annual Cost Savings (Rs/year)}} \text{ (years)} $$
-
Example from Past Paper:
Replace 500W → 350W, 350W → 150W, 125W → 60W. Same light output. 4500 hrs/yr, Rs 5.5/unit.
Assumption: 1:1 lamp replacement. Let number of each type = N.
-
Old Total Wattage = N*(500 + 350 + 125) = N*975 W.
-
New Total Wattage = N*(350 + 150 + 60) = N*560 W.
-
Savings per lamp set = 975 - 560 = 415 W = 0.415 kW.
-
Annual Energy Savings per set = 0.415 kW × 4500 hrs = 1867.5 kWh.
-
Annual Cost Savings per set = 1867.5 × 5.5 = Rs. 10,271.25.
-
Investment per set = Cost(350W) + Cost(150W) + Cost(60W) - (Scrap value of old lamps). [Investment cost not given in question, so SPP cannot be computed without it. In exam, investment cost would be provided.]
-
Procedures for Energy Saving in Lighting Systems
-
Audit: Measure existing lux levels, inventory lamps/luminaires, operating hours.
-
Benchmark: Compare with recommended lux levels (IS/CIE standards).
-
Identify ECMs: Retrofit, delamping, controls, daylighting.
-
Calculate Savings: For each ECM (as above).
-
Economic Evaluation: SPP, NPV, IRR.
-
Implementation Plan: Phasing, procurement, installation.
-
Post-Implementation M&V: Measure new lux, verify energy savings.
VII. Financial and Economic Analysis
Life Cycle Costing (LCC)
-
Concept: Total cost of owning and operating an asset over its entire life (investment + O&M + disposal).
-
Process:
-
Identify all cost components: Initial Investment, Installation, Operation, Maintenance, Energy, Replacement, Disposal.
-
Convert all future costs to Present Worth (PW) using discount rate.
-
Sum all present worths → LCC.
-
-
Applications: Compare alternative projects (e.g., standard motor vs. premium motor, window vs. split AC), select most economical.
-
Effect on Investment Decisions: Reveals true cost. A higher upfront, high-efficiency option often has lower LCC due to reduced energy costs.
Payback Period (PP)
-
Definition: Time required for cumulative cash inflows (savings) to equal initial investment.
-
Calculation:
$$ \text{Simple Payback Period} = \frac{\text{Initial Investment (Rs)}}{\text{Annual Net Cash Savings (Rs/year)}} $$
**Discounted Payback Period**: Considers time value of money; uses **discounted cash flows**.
-
Significance of Risk Analysis:
-
Shorter PP → lower risk (capital recovered faster).
-
Long PP projects are riskier (future savings uncertain, discount rate changes).
-
Sensitivity Analysis: Vary key assumptions (energy cost escalation, savings realization) to see impact on PP.
-
-
Merits: Simple, easy to understand, focuses on liquidity & risk.
-
Demerits: Ignores cash flows beyond PP, ignores time value of money (in simple PP), arbitrary cutoff.
Net Present Value (NPV)
- Concept: Sum of all present values of future cash inflows and outflows over project life, discounted at a required rate of return (discount rate).
$$ \text{NPV} = \sum_{t=0}^{n} \frac{CF_t}{(1 + r)^t} $$
Where $$\displaystyle CF_t $$ = net cash flow in year t (t=0 is initial investment, negative), $r$ = discount rate, $n$ = life.
-
Decision Rule: Accept if NPV > 0 (project adds value).
-
Advantages over Simple PP:
-
Considers entire project life.
-
Incorporates time value of money.
-
Additive (NPV of combined projects = sum of individual NPVs).
-
Directly measures increase in wealth.
-
-
Example from Past Paper:
Investment = Rs 2000, Life = 2 years, Discount rate = 15%, Savings = Rs 22000 each year.
Year 0: CF₀ = -2000 → PV = -2000.
Year 1: CF₁ = 22000 → PV = 22000 / (1.15)¹ = 22000 / 1.15 ≈ 19130.43.
Year 2: CF₂ = 22000 → PV = 22000 / (1.15)² = 22000 / 1.3225 ≈ 16635.03.
NPV = -2000 + 19130.43 + 16635.03 = \boxed{33765.46 Rs}.
!TIP: Positive NPV indicates project is financially attractive at 15% discount rate.
Internal Rate of Return (IRR)
- Definition: The discount rate (r) that makes the NPV = 0.
$$ 0 = \sum_{t=0}^{n} \frac{CF_t}{(1 + \text{IRR})^t} $$
-
Interpretation: The effective annual return on the invested capital.
-
Decision Rule: Accept if IRR > Required Rate of Return (hurdle rate).
-
Merits: Expressed as percentage, easy to compare with other investments, considers time value & all cash flows.
-
Demerits: Can have multiple IRRs for non-conventional cash flows, reinvestment assumption (IRR assumes cash flows reinvested at IRR, which may be unrealistic).
Discount Period & Time Value of Money
-
Time Value of Money (TVM): A rupee today is worth more than a rupee in the future due to its earning potential (interest, inflation).
-
Discounting: Process of converting future cash flows to present value using a discount rate.
-
Discount Period: The time interval (usually yearly) over which discounting is applied. The factor is $$\displaystyle \frac{1}{(1+r)^t} $$ for year
t.
Energy Service Company (ESCO)
-
Concept: A company that provides comprehensive energy solutions to clients: audit, design, finance, implement, and guarantee savings of ECMs.
-
Business Models:
-
Shared Savings: ESCO finances, implements; client pays ESCO a percentage of verified savings over contract period.
-
Guaranteed Savings: ESCO guarantees a certain level of savings; client pays ESCO a fixed fee from savings.
-
Energy Supply Contract: ESCO supplies energy (e.g., steam, heat) at a price lower than client's current cost.
-
-
Role in Conservation Projects:
-
Overcomes barrier of high upfront cost (ESCO provides financing).
-
Provides technical expertise.
-
Assumes performance risk (guarantees savings).
-
Enables public sector/institutions with budget constraints to implement projects.
-
VIII. Additional Cross-Cutting Topics (Integrated Above)
-
Parallel Operation of Pumps: Covered in Section V (Pumping Systems). Key: System curve changes, ensure pumps have similar characteristics, avoid one pump running far off BEP.
-
Refrigeration Plant Performance Factors: Covered in Section IV (Refrigeration Plants).
-
Illumination Lux: Covered in Section VI (Lighting Calculations).