Skip to content
EX-703 (B) · Energy Audit & Management/Quick Revision Short Notes

Energy Audit & Management (EX-703 (B)) - Unit 1 Short Notes

UNIT 1: ENERGY AUDIT & MANAGEMENT - EXAM-FOCUSED SHORT NOTES


A. FUNDAMENTALS OF ENERGY MANAGEMENT & AUDITING

1. Energy Management: Concepts & Principles

  • Definition: A systematic process for optimizing energy use in an organization to achieve cost savings, environmental benefits, and energy security while maintaining or improving operational efficiency.

  • Core Objectives:

    • Reduce energy consumption and costs.

    • Minimize environmental impact (GHG emissions).

    • Enhance energy security and reliability.

    • Comply with regulations and standards.

  • Managerial Functions of an Energy Manager:

    • Planning: Develop energy policy, set targets, plan audits.

    • Organizing: Form teams, allocate resources, define roles.

    • Directing/Leading: Motivate staff, implement projects, train personnel.

    • Controlling: Monitor performance, analyze data, report results, take corrective actions.

  • Benefits: Cost reduction, improved productivity, reduced emissions, better asset management.

  • Common Barriers & Elimination Strategies:

    | Barrier | Elimination Strategy | | :--- | :--- | | Lack of top management commitment | Present strong business case (LCC, NPV) | | High initial investment cost | Use ESCO model, phase implementation, highlight long-term savings | | Lack of awareness/training | Conduct training programs, workshops, awareness campaigns | | Fear of production loss | Pilot projects, detailed planning, maintenance scheduling | | No dedicated manpower | Assign dedicated Energy Manager/team, integrate duties |

[!TIP] Exam Focus: Distinguish between managerial functions (planning, organizing, etc.) and technical actions (audit, retrofits). Always link barriers to specific solutions.

2. Energy Audit: Concepts & Types

  • Definition: A systematic inspection, survey, and analysis of energy flows in a building/industry to identify opportunities for energy conservation without affecting output or comfort.

  • Key Distinction:

    | Aspect | Preliminary (Walk-through) Audit | Detailed (Comprehensive) Audit | | :--- | :--- | :--- | | Scope | Quick visual inspection, major energy uses | In-depth analysis, data logging, detailed measurements | | Data | Utility bills, simple observations | Detailed metering, instrument measurements, process mapping | | Output | List of obvious opportunities, rough estimates | Detailed report with specific projects, calculations, implementation plan | | Cost & Time | Low cost, short duration (1-2 days) | High cost, longer duration (weeks/months) | | Depth | Qualitative | Quantitative |

  • Step-by-Step Audit Procedure:

    1. Planning & Preparation: Define scope, assemble team, collect historical data (bills, manuals).

    2. Pre-Audit Visit (Preliminary): Walk-through, identify major equipment, interview staff.

    3. Detailed Study & Measurement: Conduct measurements using instruments, perform calculations (efficiency, losses).

    4. Data Analysis & Identification: Compare with benchmarks, identify Energy Conservation Opportunities (ECOs).

    5. Report Preparation: Present findings, ECOs with technical details, costs, savings, payback.

    6. Implementation & Follow-up: Assist in project execution, monitor performance, verify savings.

  • BEE Regulations on Manners & Intervals:

    • Designated Consumers (as per Schedule) must conduct periodic energy audits.

    • Interval: Once in every 3 years for industrial consumers; once in every 5 years for commercial/institutional consumers.

    • Audit Type: Must be a Detailed Audit conducted by an accredited Energy Auditor.

    • Compliance: Audit report to be submitted to BEE and designated consumer's designated authority.

3. Energy Auditor: Roles & Responsibilities

  • Duties: Conduct impartial audit, verify data, calculate savings, prepare report, recommend ECOs, maintain confidentiality.

  • Qualifications (BEE Accredited): Relevant engineering degree, experience, pass BEE examination.

  • Code of Conduct: Integrity, objectivity, confidentiality, competence, due care, professional behavior.

4. Instruments & Monitoring Systems

Instrument Primary Purpose Key Parameter Measured
Power Analyzer Electrical system analysis V, I, PF, kW, kVA, kWh, harmonics
Flue Gas Analyzer Combustion efficiency O₂, CO, CO₂, stack temperature, excess air
Lux Meter Lighting level assessment Illuminance (Lux)
Anemometer Airflow measurement Velocity (m/s) of air in ducts, at grilles
Tachometer Rotational speed RPM of motors, pumps, fans
Infrared Thermometer/ Camera Temperature & thermal mapping Surface temperatures, hot spots, insulation failure
Data Logger Continuous monitoring Records parameters (V, I, T, etc.) over time

B. ENVIRONMENTAL ASPECTS OF ENERGY

1. Environmental Impact of Energy Consumption

  • Non-Renewable (Fossil Fuels - Coal, Oil, Gas):

    • Air Pollution: SOx (acid rain), NOx (smog, ozone), PM (respiratory issues), VOCs.

    • GHG Emissions: CO₂ (primary), CH₄ (leakages) → Climate change.

    • Water: Usage for cooling, contamination (thermal, chemical spills, ash pond leachate).

    • Land: Degradation from mining, drilling; waste disposal (ash, sludge).

  • Renewable Energy Sources (Solar, Wind, Biomass, Hydro):

    • Lifecycle Assessment (LCA) Impact: Manufacturing, installation, decommissioning phases.

    • Land Use: Large footprint for solar farms, wind farms, hydro reservoirs.

    • Material Sourcing: Mining for PV materials (silicon, rare earths for magnets), steel for towers.

    • Ecosystem Impact: Habitat disruption (wind turbines on bird/bat routes, hydro dams on rivers), visual impact, noise.

    • Biomass Specific: Air pollution from combustion (if not controlled), land-use change for feedstock.

2. Systematic Environmental Assessment

  • Elements: Goal & scope definition, inventory analysis (LCI), impact assessment (LCIA), interpretation.

  • Methodology: Follow ISO 14040/14044 standards for LCA. Identify stressors (emissions, resources) → environmental mechanisms → damage categories (human health, ecosystem quality, resources).


C. ELECTRICAL SYSTEMS & POWER QUALITY (VERY HIGH FREQUENCY)

1. Power Factor (PF) Improvement

  • Significance & Benefits of High PF (≥0.95):

    • Reduces kVA Demand: Same kW at higher PF requires lower kVA. \boxed{\text{kVA}{\text{new}} = \frac{\text{kW}}{\text{PF}{\text{new}}}

    • Lowers Electricity Cost: Avoids penalties for low PF; may get incentives.

    • Reduces System Losses: Lower current (I ∝ 1/PF) → Lower I²R losses in transformers, cables.

    • Improves Voltage Regulation: Less voltage drop.

    • Increases System Capacity: Existing infrastructure can serve more load.

  • Disadvantages of Low PF (<0.9): Higher current, larger cable/transformer size needed, increased losses, voltage drop, penalty charges.

  • Use of Capacitor Banks: Capacitors supply leading reactive power (kVAr), canceling lagging reactive power from inductive loads (motors).

  • Best Location for Capacitors (Energy Conservation View):

    1. Load-side (Individual Motor): Most effective. Reduces current in entire upstream circuit from that point. Ideal for large, constant loads.

    2. Main Distribution Board (MDB): Common for multiple small loads. Reduces current in main feeder.

    3. At Substation (LT/HT): Last resort. Only reduces current in transformer and upstream HT line.

    Rule: Place capacitors as close as possible to the reactive load to minimize losses in non-capacitor circuits.

  • Calculation Problem (PF Correction):

    • Given: P (kW), PF₁ (initial), PF₂ (target).

    • Step 1: Calculate initial reactive power: $$\displaystyle Q_1 = P \cdot \tan(\cos^{-1}(PF_1)) $$

    • Step 2: Calculate target reactive power: $$\displaystyle Q_2 = P \cdot \tan(\cos^{-1}(PF_2)) $$

    • Step 3: Required capacitor kVAr: $$\displaystyle Q_c = Q_1 - Q_2 $$

    • Step 4: New kVA demand: $$\displaystyle \text{kVA}_{\text{new}} = \sqrt{P^2 + Q_2^2} $$ or $$\displaystyle \frac{P}{PF_2} $$

    • Penalty Calculation: If penalty is per % dip below threshold, calculate % dip = (Threshold PF - Actual PF) × 100. Multiply by penalty rate.

2. Energy Efficient Motors (EEM) vs. Standard Motors

  • Constructional Differences:

    | Feature | Standard Motor | Energy Efficient Motor | | :--- | :--- | :--- | | Core Material | Lower grade steel, higher losses | Higher grade, thinner laminations (low core loss) | | Stator Windings | Less copper, higher resistance | More copper, larger cross-section (lower I²R loss) | | Air Gap | Larger | Optimized, smaller (reduces magnetizing current) | | Manufacturing Tolerances | Standard | Tighter (improves efficiency) | | Cooling System | Standard fan | Optimized fan design (reduces fan power loss) |

  • Advantages of EEM:

    • Higher Efficiency (typically 2-5% points higher at full load).

    • Lower Operating Temperature → longer insulation life, reduced cooling load.

    • Lower Life Cycle Cost (LCC) despite higher initial cost.

    • Better performance at partial loads (flatter efficiency curve).

  • Motor Loading Calculation from Input:

    • Given: V (V), I (A), PF, η (efficiency).

    • Input Power (kW): $$\displaystyle P_{\text{in}} = \frac{\sqrt{3} \cdot V \cdot I \cdot PF}{1000} $$

    • Output Power (kW): $$\displaystyle P_{\text{out}} = P_{\text{in}} \times \eta $$

    • Loading (%): $$\displaystyle \text{Loading \%} = \frac{P_{\text{out}}}{P_{\text{rated}}} \times 100 $$

3. Harmonics in Power Systems

  • Major Problems:

    • Additional Heating: In motors (core losses), transformers (eddy currents), cables (I²R).

    • Resonance: With system capacitance → voltage magnification, equipment damage.

    • Malfunction: Sensitive electronic equipment (computers, PLCs), protective relays.

    • Neutral Current: In 3-phase 4-wire systems, triplen harmonics (3rd, 9th) add in neutral → overheating.

    • Torque Pulsations: In motors → vibration, noise.

  • Sources (Non-linear Loads):

    • Rectifiers/Front-ends: UPS, VFDs, battery chargers, DC drives.

    • Arc Furnaces & Welding Machines.

    • Fluorescent/LED Lamps with electronic ballasts/drivers.

    • Computers, Printers, TVs.

  • Mechanism: Non-linear loads draw non-sinusoidal current (clipped/flat-top) from a sinusoidal voltage source. This current waveform is decomposed by Fourier analysis into fundamental (50/60 Hz) + harmonics (150 Hz, 250 Hz, etc.).

  • Harmonic Distortion Evaluation:

    1. Measure: Use power quality analyzer/harmonic analyzer at PCC (Point of Common Coupling).

    2. Calculate Total Harmonic Distortion (THD):

      • Current THD: $$\displaystyle \text{THD}_I = \frac{\sqrt{\sum_{h=2}^{\infty} I_h^2}}{I_1} \times 100\% $$

      • Voltage THD: $$\displaystyle \text{THD}_V = \frac{\sqrt{\sum_{h=2}^{\infty} V_h^2}}{V_1} \times 100\% $$

      (where $$\displaystyle I_1, V_1 $$ are fundamental RMS values, $$\displaystyle I_h, V_h $$ are harmonic RMS values).

    3. Spectrum Analysis: Identify magnitude of individual harmonic orders (5th, 7th, 11th, 13th are common from 6-pulse converters).

    4. Compare with Standards: IEEE 519 limits for voltage/current distortion.

4. Transformers

  • Losses:

    • Core (Iron) Losses: Hysteresis (reorientation of magnetic domains) + Eddy Currents (induced currents in core). Constant (occur even at no-load). Reduced by using CRGO steel laminations.

    • Copper (Load) Losses: $$\displaystyle I^2R $$ loss in windings. Vary with square of load.

    • Stray Losses: Due to leakage flux causing eddy currents in tank, structural parts. Part load dependent.

  • Minimization Methods:

    • Use high-grade core material (thin, high-resistance laminations).

    • Optimize design for operating load profile (avoid light load operation).

    • Ensure good maintenance (tight connections, clean cooling).

5. HT vs. LT Systems

Aspect Low Tension (LT) High Tension (HT)
Voltage Level ≤ 1000 V (typically 415V, 230V) > 1000 V (typically 11kV, 33kV)
Current High for same power Low
Conductor Size Thicker (to carry high current) Thinner
Insulation Cost Lower Higher
Transmission Losses Higher (I²R loss ∝ I²) Lower
Use in Industry Final distribution to loads Main power receipt from utility, main distribution in large plants

D. THERMAL SYSTEMS & BOILERS (VERY HIGH FREQUENCY)

1. Boilers & Steam Systems

  • Boiler Efficiency:

    • Direct Method (Input-Output):

$$\eta_{\text{direct}} = \frac{\text{Steam Output (kcal/hr)} \times (\text{Enthalpy of Steam} - \text{Enthalpy of Feedwater})}{\text{Fuel Input (kcal/hr)}} \times 100\%$$

    *Simple, quick, used for routine monitoring.*

*   **Indirect Method (Heat Loss):**

$$\eta_{\text{indirect}} = 100 - (\text{Sum of all percentage losses})$$

    Losses include: **Flue gas loss, Loss due to moisture in fuel/air, Loss due to unburnt carbon (CO, C in ash), Radiation & convection loss.**

    *Detailed, identifies loss sources.*
  • Efficiency Conversion (GCV to NCV Basis):

    • GCV (Gross Calorific Value) includes latent heat of vaporization in fuel moisture/hydrogen.

    • NCV (Net Calorific Value) excludes it.

    • Conversion: $$\displaystyle \eta_{\text{NCV}} = \eta_{\text{GCV}} \times \frac{\text{GCV}}{\text{NCV}} $$

    • For Coal: $$\displaystyle \frac{\text{GCV}}{\text{NCV}} \approx 0.95 $$ (typical). Higher GCV efficiency will be lower on NCV basis.

  • Significance of Low-Pressure Steam:

    • Higher Quality of Heat: Latent heat content is high at lower pressure.

    • Reduced Enthalpy Drop: Less heat loss in steam traps, valves, and distribution.

    • Lower Safety Risks: Less severe in case of leaks.

    • Energy Conservation: Use steam at lowest feasible pressure for the process.

  • Minimum Excess Air for Combustion:

    • Significance: Excess air carries heat up the stack (flue gas loss). Optimal excess air (typically 10-20%) minimizes losses while ensuring complete combustion.

    • Achievement Methods:

      1. Flue Gas Analysis: Measure O₂% in flue gas. Use formula: $$\displaystyle \text{Excess Air \%} = \frac{\text{Measured O₂\%} - \text{Theoretical O₂\%}}{21 - \text{Theoretical O₂\%}} \times 100 $$

      2. Oxygen Trim System: Automatic control of air/fuel ratio using continuous O₂ sensor feedback.

      3. Regular Maintenance: Clean heat transfer surfaces, ensure proper burner tuning.

  • Steam Distribution Systems:

    • Layout: Short, straight runs; proper grading for condensate flow.

    • Insulation: All steam lines, valves, flanges must be insulated (use Economic Thickness concept).

    • Steam Traps: Critical for removing condensate and non-condensables without losing steam.

    • Condensate Recovery: Mandatory for energy/water conservation. Return to boiler feedwater system after proper treatment.

2. Steam Traps

  • Working Principle: Automatic valve that discharges condensate, air, and CO₂ while blocking steam.

  • Types:

    | Type | Mechanism | Best Application | Key Feature | | :--- | :--- | :--- | :--- | | Mechanical (Float & Thermostatic) | Float rises with condensate level → opens valve. | High pressure, large capacity. | 100% condensate discharge, fails open (safe). | | Thermostatic (Bimetallic, Bellows) | Temperature sensing element expands/contracts. | Small loads, drip service. | Sensitive to superheat, fails closed (can cause water hammer). | | Thermodynamic (Disc) | Steam pressure vs. condensate pressure on disc. | Wide range, robust. | Discharges air initially, modulating, fails open. |

  • Performance Assessment Methods:

    • Visual: Sight glass (if fitted) shows water/steam.

    • Audible: Listen for continuous blowing sound (failure) or no sound (stuck closed).

    • Temperature: Trap outlet cold (working) or hot (stuck closed). Use IR thermometer.

    • Ultrasonic: Most reliable. High-pitched "hiss" indicates steam blowing (failure). Lower frequency "gurgle" indicates condensate discharge (working).

3. Condensate & Flash Steam Utilization

  • Condensate Recovery Process: Collect hot condensate from traps → filter (remove rust, scale) → pump (if pressure low) → return to boiler feedwater tank.

    • Benefits: Saves water, fuel (heat), and chemical treatment costs.
  • Flash Steam Utilization:

    • Concept: When high-pressure condensate is discharged to a lower pressure, a portion flashes into steam (flash steam) at the lower pressure.

    • Example - Cascading: High-pressure (e.g., 10 bar) condensate from process → flash vessel → flash steam at 2 bar used for low-pressure process → remaining hot water (at 2 bar) used for feedwater heating or other low-temp uses.

    • Example - Pressure Reduction: Flash steam used directly after passing through a pressure reducing valve for a lower-pressure application.

4. Economic Thickness of Insulation

  • Concept: The insulation thickness where sum of annual heat loss cost + annual capital recovery cost of insulation is minimum.

  • Process: Calculate heat loss ($Q$) for varying thickness ($x$) → Annual heat loss cost = $Q \times \text{Fuel Cost} \times \text{Operating Hours}$. Annual capital cost = $$\displaystyle \frac{\text{Insulation Cost}}{ \text{Present Worth Factor} } $$. Find $x$ where total cost is minimum.

    Rule of Thumb: For pipes, 2.5-5 cm; for vessels, 5-10 cm. Always calculate for critical/high-temperature surfaces.

5. Furnaces

  • Concept: Enclosed structure for heat treatment of materials at high temperatures.

  • Classification (by Heat Source): Oil/Gas fired, Electric (resistance/induction), Coal fired, Biomass.

  • Applications in Steel Industry: Reheating furnace (slabs/billets before rolling), ** soaking pit**, annealing furnace, cupola (melting).

  • Energy Conservation Opportunities:

    • Reduce heat loss: Improve insulation (linings, doors), minimize openings.

    • Reduce excess air: Optimize combustion with O₂ trim.

    • Recover waste heat: Air preheater (preheat combustion air), waste heat boiler (generate steam from flue gases).

    • Minimize radiation losses: Proper door sealing, reduce opening time.

    • Use proper burner management and pulse combustion.


E. PUMPING, FANS & BLOWERS, THERMIC FLUIDS

1. Centrifugal Pumps

  • Factors Affecting Performance:

    • System Curve: Static head + Friction head (∝ Flow²). Pump must operate at intersection of pump curve & system curve.

    • Affinity Laws: For a given pump:

      $Q \propto N$, $$\displaystyle H \propto N^2 $$, $$\displaystyle P \propto N^3 $$ (Speed change)

      $Q \propto D$, $$\displaystyle H \propto D^2 $$, $$\displaystyle P \propto D^3 $$ (Impeller diameter change)

    • Cavitation: Formation & collapse of vapor bubbles → damage, noise, loss of head. Prevent by ensuring NPSH_available > NPSH_required.

    • Wear: Impeller, casing, wear ring wear → reduced efficiency, increased flow recirculation.

  • Energy Conservation Opportunities:

    • Variable Speed Drives (VSD/VFD): Match pump output to system demand (most effective, saves up to 50%).

    • Impeller Trimming: Reduce diameter if permanent reduction in flow/head needed.

    • Parallel/Series Operation Optimization: Use only required number of pumps; avoid throttling.

    • System Design: Reduce unnecessary static head, minimize friction (larger pipes, fewer bends).

    • Maintenance: Regular bearing lubrication, wear ring clearance check, impeller balancing.

  • Significance of Parallel Operation:

    • Increases Flow: Total flow ≈ sum of individual flows at same head.

    • Provides Redundancy: One pump can be taken for maintenance.

    • Load Sharing: Pumps with identical curves share load equally. Dissimilar curves lead to unstable operation (one pump may "hog" flow).

    • Efficiency: System efficiency may drop at low loads if too many pumps run. Use VFDs or staging (turn pumps ON/OFF) to maintain high efficiency.

2. Fans & Blowers

  • Fan Design & Selection Criteria:

    • System Resistance Curve: Calculate Total Pressure = Static Pressure + Velocity Pressure.

    • Type Selection: Centrifugal (high pressure, dirty air), Axial (high flow, low pressure).

    • Efficiency: Select fan operating near peak efficiency point on its curve.

    • Material: Construction material for abrasion/corrosion resistance.

  • Fan Performance Evaluation:

    • Fan Laws: Similar to pumps: $Q \propto N$, $$\displaystyle P \propto N^2 $$, $$\displaystyle \text{Power} \propto N^3 $$.

    • Performance Curves: Plot of Pressure vs. Flow for given speed. System curve (parabolic) intersects fan curve at operating point.

    • Measurement: Use anemometer (velocity), manometer (pressure), power analyzer (kW).

  • Efficient Operation & Control:

    • Inlet/Outlet Dampers: Throttling (wastes energy, avoid if possible).

    • Variable Inlet Guide Vanes (VIGV): Better than dampers.

    • Variable Speed Drive (VFD): Most efficient control method. Power ∝ N³.

    • Parallel Operation: Similar considerations as pumps.

3. Thermic Fluid Heating Systems

  • Working Principle: Closed-loop system. Thermic fluid (e.g., mineral oil, synthetic) heated in a heater coil (fired or electric) → circulates by pump → transfers heat to process via heat exchanger → returns to heater.

  • Advantages over Steam:

    • No Pressure: Operates at low pressure even for high temperatures (up to 350-400°C). No boiler regulations, no risk of explosion.

    • No Condensate: No condensate recovery system, no water treatment.

    • Precise Temperature Control: Easy, accurate (±1-2°C).

    • Simpler System: No steam traps, condensate return, blowdown.

    • No Scale/Fouling: In heater coil (if fluid is clean).

  • Applications: Preferable for temperature-sensitive processes, high-temperature low-pressure needs, indirect heating where water/steam is undesirable (e.g., food, pharmaceuticals, chemical reactors, dryers).


F. LIGHTING SYSTEMS (HIGH FREQUENCY)

1. Lighting Fundamentals & Conservation

  • Key Terms:

    • Luminous Flux (Lumen, lm): Total light output of a source.

    • Illuminance (Lux, lx): Luminous flux per unit area (1 lx = 1 lm/m²). Measure of light falling on a surface.

    • Efficacy (lm/W): Light output per unit power input. Key efficiency metric.

    • Luminance (cd/m²): Light reflected/emitted from a surface (brightness).

  • Scope of Energy Conservation:

    • Source Efficiency: Replace inefficient lamps (GLS, CFL) with LEDs.

    • Design Efficiency: Use task lighting, zoning, proper spacing, reflectors.

    • Control Efficiency: Occupancy sensors, daylight sensors, timers, dimmers.

    • Maintenance: Regular cleaning of fixtures/luminaires, timely lamp replacement.

  • Procedure to Save Energy:

    1. Audit Existing System: Measure existing lux levels, count fixtures, note lamp types/wattages, operating hours.

    2. Determine Required Lux: Use standards (CIBSE, IS) for each area/activity.

    3. Redesign: Optimize number, type, and placement of fixtures. Use daylighting where possible.

    4. Select Efficient Sources: LEDs are default choice.

    5. Install Controls: Sensors, scheduling.

    6. Implement Maintenance Plan.

2. LED Lighting

  • Technology: Light Emitting Diode. Semiconductor device electroluminescence.

  • Advantages over Incandescent/Fluorescent:

    • Very High Efficacy (100-150+ lm/W vs. 10-15 for GLS, 50-70 for CFL).

    • Long Life (50,000-100,000 hrs vs. 1,000-2,000 for GLS).

    • Instant On/Off, no warm-up time.

    • Directional Light (no need for reflectors, less waste).

    • Durable (no filament, shock resistant).

    • Dimmable (with compatible drivers).

    • No UV/IR radiation, low heat.

  • Lamp Replacement Calculation (Numerical):

    • Given: Replace N old lamps (W_old, hrs/yr) with new lamps (W_new, cost_new). Electricity cost = Rs C/kWh.

    • Annual Energy Saving (kWh): $$\displaystyle \text{ Saving } = N \times (\text{W}_{\text{old}} - \text{W}_{\text{new}}) \times \text{Operating Hours} / 1000 $$

    • Annual Cost Saving (Rs): $$\displaystyle \text{ Saving }_{\text{cost}} = \text{ Saving } \times C $$

    • Simple Payback Period (Years): $$\displaystyle \text{SPP} = \frac{\text{Total Investment Cost (N × Cost}_{\text{new}})}{\text{Annual Cost Saving}} $$

    Note: If replacing in kind (same number), investment = N × Cost_new. If changing quantity, investment = (N_new × Cost_new) - (Salvage of old).

3. Daylighting & Lighting Controls

  • Daylighting: Use of natural light via windows, skylights, light tubes. Reduces artificial lighting load.

  • Controls:

    • Occupancy Sensors (PIR/Microwave): Switch OFF when area unoccupied.

    • Daylight Sensors (Photocells): Dim or switch OFF artificial light when sufficient daylight.

    • Timers & Scheduling: For non-critical areas.

    • Dimming Systems: For manual or automatic adjustment.


G. ECONOMIC ANALYSIS & FINANCIAL TOOLS (VERY HIGH FREQUENCY)

1. Life Cycle Costing (LCC)

  • Definition: A method to evaluate the total cost of ownership of an asset or project over its entire life, from acquisition to disposal.

  • Process:

    1. Define system/alternative.

    2. Identify all cost components over life.

    3. Convert all costs to a common base year (Present Worth) using discount rate.

    4. Sum present worths → Total LCC.

    5. Compare LCCs of alternatives.

  • Components:

    • Initial Cost (capital, installation).

    • Operating Cost (energy, water, maintenance labor).

    • Replacement Cost (major overhauls, component replacement).

    • Salvage Value (at end of life, subtracted).

    • Non-monetary benefits (environmental, comfort) can be quantified if possible.

  • Effect on Investment Decisions: LCC favors energy-efficient options with higher upfront cost but lower operating costs. It avoids "first-cost" bias.

2. Payback Period

  • Definition: The time required for cumulative net savings from an investment to equal the initial investment cost.

  • Simple Payback Period (SPP) Calculation:

    $$\displaystyle \text{SPP} = \frac{\text{Initial Investment (Rs)}}{\text{Annual Net Savings (Rs/year)}} $$

    (Annual Net Savings = Annual Cost Saving - Annual Maintenance Cost, if any).

  • Significance of Risk Analysis: Shorter payback → lower financial risk (capital recovered quickly). Longer payback projects are riskier due to uncertainties in future energy prices, equipment life, maintenance costs.

  • Merits: Simple, easy to understand, emphasizes liquidity & quick recovery.

  • Demerits: Ignores cash flows after payback, ignores time value of money, arbitrary cutoff, not a measure of profitability.

3. Net Present Value (NPV)

  • Concept: The sum of all future cash flows (savings - costs) discounted back to present value at a chosen discount rate (reflects cost of capital, risk, inflation). Decision Rule: Accept if NPV > 0.

  • Formula:

$$\text{NPV} = -I_0 + \sum_{t=1}^{n} \frac{S_t - C_t}{(1 + r)^t}$$

Where:

*   $$\displaystyle I_0 $$ = Initial Investment (at t=0)

*   $$\displaystyle S_t $$ = Savings in year t

*   $$\displaystyle C_t $$ = Costs (operating, maintenance) in year t

*   $r$ = Discount rate (per year)

*   $n$ = Life of project (years)
  • Advantages over SPP:

    • Considers time value of money (discounting).

    • Considers entire project life.

    • Direct measure of profitability (absolute Rs value added).

    • Mathematically sound for comparing mutually exclusive projects.

  • Calculation Example (from Dec 2024):

    • $$\displaystyle I_0 = 2000 $$ Rs, $$\displaystyle S_1 = S_2 = 22000 $$ Rs/yr, $$\displaystyle r=15\% $$, $$\displaystyle n=2 $$ yrs.

    • $$\displaystyle \text{NPV} = -2000 + \frac{22000}{1.15} + \frac{22000}{(1.15)^2} $$

    • $$\displaystyle \text{NPV} = -2000 + 19130.43 + 16635.59 = \boxed{33765.02 \text{ Rs}} $$

4. Internal Rate of Return (IRR)

  • Definition: The discount rate ($r$) that makes the NPV of a project equal to zero.

    $$\displaystyle \text{NPV}(IRR) = 0 $$

  • Significance: Represents the true annual rate of return on the invested capital. Decision Rule: Accept if IRR > Required Rate of Return (hurdle rate). Higher IRR is more desirable.

5. ESCO (Energy Service Company) Concept

  • Basic Concept: A specialized company that identifies, finances, implements, and guarantees energy efficiency (or renewable energy) projects for clients (industries, buildings).

  • Business Models:

    • Shared Savings: ESCO finances, implements. Client pays ESCO a pre-agreed share of the verified savings over contract period (5-10 yrs). Client pays nothing upfront.

    • Guaranteed Savings: ESCO guarantees a certain level of annual savings. Client may finance (loan) or ESCO arranges finance. Client pays ESCO a fixed fee from savings. If savings < guarantee, ESCO pays the shortfall.

  • Role: Overcome barriers of high upfront cost, lack of expertise, and performance risk. Provides turnkey solution and performance guarantee.


H. REGULATORY FRAMEWORK & CASE STUDIES

1. Bureau of Energy Efficiency (BEE) Regulations

  • Manners & Intervals (Recap from A.2):

    • Designated Consumers (listed in Schedule) must conduct detailed energy audits.

    • Frequency: Every 3 years for industries, every 5 years for commercial/institutional.

    • Auditor: Must be BEE-accredited Energy Auditor.

    • Submission: Report to BEE and consumer's designated authority within specified timeline.

  • Compliance: Non-compliance can lead to penalties under Energy Conservation Act.

2. Integrated Energy Audit Case Study (Institutional - University Campus)

  • Holistic Approach:

    1. Data Collection: Electricity bills (kW, kWh, PF), fuel bills (diesel, LPG, biomass), water bills, building area, occupancy, equipment inventory.

    2. Electrical Systems Audit:

      • Measure PF at main substation → calculate capacitor requirement.

      • Audit lighting: Measure lux, count fixtures, calculate lamp replacement savings (GLS/CFL → LED).

      • Check for harmonics in UPS/VFD-heavy labs.

      • Assess motor loading in HVAC, pumps, workshops.

    3. Thermal Systems Audit:

      • If boiler exists: Calculate efficiency (direct/indirect), flue gas analysis, insulation check.

      • Audit kitchen (LPG burners), canteen, hostels (geysers) for efficiency.

      • Check steam/hot water distribution, traps, insulation.

    4. HVAC & Pumping: Audit AHUs, chillers, water pumps for VFD opportunities, maintenance.

    5. Renewable Potential: Assess solar PV on rooftops, solar water heating.

    6. Economic Analysis: For each ECO (LED retrofit, capacitor, VFD), calculate savings, investment, SPP, NPV.

    7. Report: Prioritize ECOs based on savings-to-investment ratio, NPV, SPP. Propose implementation plan and monitoring mechanism.


\boxed{\text{END OF UNIT 1 NOTES}}

Go to where you left off?

Quick Add to Notes

Save questions, your own notes and screenshots into notes filed by unit. It takes a free account.

Create free account

Have an account? Log in