1.0 LOAD FLOW ANALYSIS
1.1 Significance and Purpose
Load flow (power flow) analysis determines voltage magnitudes and angles at all buses, and real/reactive power flows in lines for specified generation and load conditions.
Purposes:
-
Planning: Expansion studies, new line additions.
-
Operation: Optimal dispatch, contingency analysis (N-1 security).
-
Optimization: Loss minimization, voltage profile improvement.
-
Stability studies: Provides initial operating point for transient and dynamic stability analysis.
1.2 Classification of Buses
| Bus Type | Specified Quantities | Calculated Quantities | Justification |
|---|---|---|---|
| Slack/Swing | Voltage magnitude \(|V|\) and angle \(\delta\) (usually \(\delta=0^\circ\)) | \(P\), \(Q\) | Balances system losses; provides reference for phase angles. |
| PV/Generator | \(P\), \(|V|\) | \(Q\), \(\delta\) | Represents generators with voltage control (AVR active). |
| PQ/Load | \(P\), \(Q\) | \(|V|\), \(\delta\) | Represents loads where voltage is not controlled. |
1.3 Formation of Nodal Admittance Matrix (Y_bus)
-
Definition: \(Y_{\text{bus}}\) is a sparse \(n \times n\) matrix where \(Y_{ij} = -y_{ij}\) for \(i \neq j\) (off-diagonal), and \(Y_{ii} = \sum_{k=1}^{n} y_{ik}\) (sum of all admittances connected to bus \(i\)).
-
From line data: For line \(i-j\) with series impedance \(z_{ij} = r_{ij} + jx_{ij}\) and shunt admittance \(y_{ij}/2\) at each end:
\[ y_{ij} = \frac{1}{z_{ij}}, \quad Y_{ij} = -y_{ij}, \quad Y_{ii} \text{ includes } y_{ij} + \frac{y_{ij}}{2} \text{ if shunt considered}. \]
-
Systematic formation: Using incidence matrix \(\mathbf{A}\) (size \(n \times b\)) and branch admittance matrix \(\mathbf{y}\) (diagonal \(b \times b\)):
\[ \boxed{Y_{\text{bus}} = \mathbf{A}^T \mathbf{y} \mathbf{A}} \]
-
Example (4-bus system, shunt neglected): Given line impedances (p.u.):
\(1-2: 0.25+j0.1\), \(1-3: 0.20+j0.8\), \(1-4: 0.30+j1.2\), \(2-3: 0.20+j0.8\), \(3-4: 0.15+j0.6\).
Compute \(y_{ij} = 1/z_{ij}\):
\(y_{12} = 3.448 - j1.379\), \(y_{13} = 0.294 - j1.176\), \(y_{14} = 0.196 - j0.784\),
\(y_{23} = 0.294 - j1.176\), \(y_{34} = 0.392 - j1.569\).
Then:
\[ Y_{\text{bus}} = \begin{bmatrix} Y_{11} & Y_{12} & Y_{13} & Y_{14} \\ Y_{21} & Y_{22} & Y_{23} & 0 \\ Y_{31} & Y_{32} & Y_{33} & Y_{34} \\ Y_{41} & 0 & Y_{43} & Y_{44} \end{bmatrix} \]
with:
\[ \begin{aligned} Y_{11} &= 3.938 - j3.340, & Y_{22} &= 3.742 - j2.556, \\ Y_{33} &= 0.980 - j3.922, & Y_{44} &= 0.588 - j2.353, \\ Y_{12} &= -3.448 + j1.379, & Y_{13} &= -0.294 + j1.176, \\ Y_{14} &= -0.196 + j0.784, & Y_{23} &= -0.294 + j1.176, \\ Y_{34} &= -0.392 + j1.569. \end{aligned} \]
1.4 Iterative Solution Methods
1.4.1 Gauss-Seidel Method
-
Algorithm (for PQ buses only):
Initialize voltages (flat start: \(1.0\angle 0^\circ\)). For each PQ bus \(i\):
\[ V_i^{(k+1)} = \frac{1}{Y_{ii}} \left( \frac{P_i - jQ_i}{V_i^{(k)*}} - \sum_{\substack{j=1 \\ j \neq i}}^{n} Y_{ij} V_j^{(k)} \right) \]
Check convergence: \(\max |V_i^{(k+1)} - V_i^{(k)}| < \varepsilon\).
-
Modification for PV buses: After updating \(V_i\), if \(|V_i| \neq |V_i^{\text{spec}}|\), scale \(V_i\) to specified magnitude and compute new \(Q_i\) from:
\[ Q_i^{(k+1)} = - \left[ V_i^{(k+1)*} \sum_{j=1}^{n} Y_{ij} V_j^{(k)} \right]_{\text{imag}} \]
-
Flow chart for PQ buses only:
-
Initialize \(V_i = 1.0\angle 0^\circ\) for all PQ buses.
-
For each PQ bus \(i\), compute \(V_i^{\text{new}}\) using equation above.
-
Check convergence. If not converged, set \(V_i = V_i^{\text{new}}\) and repeat.
-
-
Advantages: Simple, low memory per iteration.
-
Disadvantages: Slow linear convergence; may diverge for ill-conditioned systems.
-
Convergence: Depends on spectral radius of iteration matrix; typically requires more iterations than NR.
1.4.2 Newton-Raphson Method
-
Formulation (polar coordinates):
State variables: \(\delta_i\) for all non-slack buses, \(|V_i|\) for PQ buses.
Power mismatches:
\[ \Delta P_i = P_i^{\text{spec}} - P_i^{\text{calc}}, \quad \Delta Q_i = Q_i^{\text{spec}} - Q_i^{\text{calc}} \]
where
\[ \begin{aligned} P_i^{\text{calc}} &= |V_i| \sum_{j=1}^{n} |V_j| \left( G_{ij} \cos \delta_{ij} + B_{ij} \sin \delta_{ij} \right), \\ Q_i^{\text{calc}} &= |V_i| \sum_{j=1}^{n} |V_j| \left( G_{ij} \sin \delta_{ij} - B_{ij} \cos \delta_{ij} \right). \end{aligned} \]
-
Jacobian matrix:
\[ J = \begin{bmatrix} \frac{\partial P}{\partial \delta} & \frac{\partial P}{\partial |V|} \\ \frac{\partial Q}{\partial \delta} & \frac{\partial Q}{\partial |V|} \end{bmatrix} \]
Elements computed analytically; sparse structure exploited.
-
Algorithm:
-
Initialize voltages (flat start).
-
Compute \(P_i^{\text{calc}}\), \(Q_i^{\text{calc}}\), and mismatches \(\Delta P_i\), \(\Delta Q_i\).
-
Form Jacobian \(J\).
-
Solve \(J \Delta X = -\Delta PQ\) for corrections \(\Delta \delta\) (non-slack) and \(\Delta |V|\) (PQ buses).
-
Update: \(\delta_i^{\text{new}} = \delta_i^{\text{old}} + \Delta \delta_i\); for PQ buses, \(|V_i|^{\text{new}} = |V_i|^{\text{old}} + \Delta |V_i|\); for PV buses, only \(\delta\) updated, \(|V|\) fixed.
-
Check convergence: \(\max |\Delta| < \varepsilon\).
-
Repeat if needed.
-
-
Flow chart: Standard NR flow chart with initialization, mismatch calculation, Jacobian formation, solution, update, convergence check.
-
Advantages: Quadratic convergence; robust for large systems.
-
Disadvantages: High memory (Jacobian storage); complex per iteration (matrix inversion).
-
Convergence: Typically 3–5 iterations for well-behaved systems.
1.4.3 Comparison of Gauss-Seidel and Newton-Raphson
| Aspect | Gauss-Seidel | Newton-Raphson |
|---|---|---|
| Convergence | Linear, slow (10–50 iterations) | Quadratic, fast (3–5 iterations) |
| Memory | Low (stores \(Y_{\text{bus}}\) only) | High (stores and updates Jacobian) |
| Per iteration cost | Low (simple substitutions) | High (matrix factorization) |
| Initial guess | Sensitive; may diverge | Robust; flat start acceptable |
| Suitable for | Small systems, educational | Large practical systems |
1.4.4 Fast Decoupled Load Flow (FDLF)
-
Based on assumptions:
-
Voltage magnitudes close to 1.0 p.u.
-
Lines highly reactive (\(R \ll X\)).
-
-
Decouples \(P-\delta\) and \(Q-|V|\) equations:
\[ \begin{aligned} \Delta P &= B' \Delta \delta, \\ \Delta Q &= B'' \Delta |V|, \end{aligned} \]
where \(B'\) and \(B''\) are constant approximations of Jacobian submatrices.
-
Advantages: Faster per iteration, reduced memory.
-
Disadvantages: May require more iterations for systems with high \(R/X\) ratios; less robust.
2.0 POWER SYSTEM STABILITY ANALYSIS
2.1 Fundamental Concepts
-
Steady-state stability: Ability to maintain synchronism under small disturbances (e.g., load fluctuations). Analyzed using linearized models around an operating point.
-
Transient stability: Ability to maintain synchronism after large disturbances (e.g., faults, line outages). Requires nonlinear time-domain simulation.
-
Factors affecting steady-state stability:
-
Higher voltage levels.
-
Lower transmission reactance.
-
Higher generator excitation.
-
Faster excitation systems.
-
-
Factors affecting transient stability:
-
Fault type and location (3-phase worst).
-
Clearing time (shorter better).
-
System strength (lower \(X/R\) ratio improves stability).
-
Generator inertia (higher \(H\) slows rotor acceleration).
-
Post-fault network strength.
-
2.2 Swing Equation and Rotor Dynamics
-
Derivation (single machine-infinite bus):
Rotor dynamics: \(M \frac{d^2 \delta}{dt^2} = T_m - T_e\), where \(M = \frac{2H}{\omega_s}\) (inertia constant \(H\) in seconds, \(\omega_s = 2\pi f_s\) rad/s).
In power terms (\(P = T \omega\)):
\[ \boxed{M \frac{d^2 \delta}{dt^2} = P_m - P_e} \]
where \(P_e = \frac{E V}{X} \sin \delta\) for simple model.
-
Physical significance: Describes rotor acceleration/deceleration due to imbalance between mechanical input \(P_m\) and electrical output \(P_e\). Stability depends on whether \(\delta\) remains bounded.
-
Linearized swing equation (small disturbances):
Let \(\delta = \delta_0 + \Delta\delta\), \(P_e \approx P_{e0} + K \Delta\delta\), where \(K = \left. \frac{dP_e}{d\delta} \right|_{\delta_0}\).
\[ M \frac{d^2 \Delta\delta}{dt^2} = \Delta P_m - K \Delta\delta \]
For constant \(\Delta P_m\), this is a second-order system.
-
Steady-state stability limit: From linearized equation, maximum \(\Delta P_m\) without instability occurs when \(K \Delta\delta_{\max} = \Delta P_m\). But for nonlinear \(P_e(\delta)\), the limit is at \(\frac{dP_e}{d\delta} = 0\), i.e., \(\delta = 90^\circ\) for simple model, so \(P_{\max} = \frac{EV}{X}\).
2.3 Equal Area Criterion (EAC)
-
Statement: For a single machine-infinite bus system, the system is stable if the accelerating area \(A_1\) (when \(P_m > P_e\)) equals the decelerating area \(A_2\) (when \(P_e > P_m\)) during a disturbance.
-
Derivation: Multiply swing equation by \(d\delta/dt\) and integrate:
\[ \int_{\delta_0}^{\delta} (P_m - P_e) d\delta = \frac{1}{2} M \left( \frac{d\delta}{dt} \right)^2 \Big|_{\delta_0}^{\delta} \]
At \(\delta = \delta_{\text{cr}}\), \(\frac{d\delta}{dt} = 0\), so \(\int_{\delta_0}^{\delta_{\text{cr}}} (P_m - P_e) d\delta = 0 \Rightarrow A_1 = A_2\).
-
Graphical interpretation:
DiagramCANVAS: Plot P_e vs δ curve. Draw horizontal line at P_m. Mark pre-fault curve (P_e1), during-fault curve (P_e2, lower), post-fault curve (P_e3). Accelerating area A1 between P_m and P_e2 from δ0 to δ_cr. Decelerating area A2 between P_e3 and P_m from δ_cr to δ_max where P_e3 = P_m again. Shade areas. -
Critical clearing angle \(\delta_{\text{cr}}\): Angle at which \(A_1 = A_2\). Found by solving:
\[ \int_{\delta_0}^{\delta_{\text{cr}}} (P_m - P_e^{\text{fault}}) d\delta = \int_{\delta_{\text{cr}}}^{\delta_{\max}} (P_e^{\text{post}} - P_m) d\delta \]
where \(\delta_{\max}\) satisfies \(P_e^{\text{post}}(\delta_{\max}) = P_m\).
-
Critical clearing time \(t_{\text{cr}}\): Time corresponding to \(\delta_{\text{cr}}\) from integration of swing equation during fault.
-
Application to faults with changed reactance:
-
Pre-fault: \(X = X_1\), \(P_{e1} = \frac{EV}{X_1} \sin \delta\).
-
During fault: \(X = X_f\), \(P_{e2} = \frac{EV}{X_f} \sin \delta\).
-
Post-fault: \(X = X_2\), \(P_{e3} = \frac{EV}{X_2} \sin \delta\).
Compute areas accordingly.
-
2.4 Methods for Improving Transient Stability
-
Fast valving: Rapidly reduce steam input to turbine during fault.
-
Dynamic braking: Insert resistors in generator terminals to absorb power.
-
Excitation control: High initial response excitation (e.g., PSS) to increase \(P_e\) during fault.
-
HVDC links: Fast power flow control.
-
Series capacitors: Reduce line reactance, increase \(P_{\max}\).
-
Load shedding: Reduce \(P_m\) during emergency.
-
Single-pole switching: For line faults, open only faulty pole to maintain coupling.
3.0 LOAD FREQUENCY CONTROL (LFC) AND GOVERNOR MODELING
3.1 Importance of Strict Frequency Control
-
Frequency variation affects:
-
Induction motor speeds (industrial processes).
-
Synchronous motor speeds (constant-speed drives).
-
Consumer devices (clocks, electronics).
-
System stability (frequency instability can cause cascading outages).
-
-
Standards: Typically \(\pm 0.5\ \text{Hz}\) for interconnected systems.
3.2 Modeling of Turbine Speed Governing System
-
Components:
-
Governor: Senses speed/frequency, adjusts valve position.
-
Speed changer (set point): Manual/automatic adjustment of desired speed.
-
Turbine: Converts steam/water flow to mechanical power.
-
Valve motor: Time delay due to inertia.
-
-
Transfer function block diagram:
DiagramCANVAS: Block diagram: Speed changer (gain 1/R) → Governor (1/(1+sT_g)) → Valve motor (1/(1+sT_v)) → Turbine (1/(1+sT_t)) → ΔP_m. Input: ΔP_ref - Δf (with feedback from Δf).Standard model:
\[ \Delta P_m(s) = \frac{1}{1+sT_g} \cdot \frac{1}{1+sT_t} \cdot \frac{1}{R} \left( \Delta P_{\text{ref}}(s) - \Delta f(s) \right) \]
where \(R\) is droop (Hz per unit power).
3.3 Inertia Constant (H) and Rotor Dynamics
-
Definition:
\[ \boxed{H = \frac{\frac{1}{2} I \omega_s^2}{S_{\text{base}}} \ \text{(seconds)}} \]
where \(I\) = moment of inertia (kg·m²), \(\omega_s = 2\pi f_s\) rad/s, \(S_{\text{base}}\) = generator MVA rating.
-
Physical meaning: Time (in seconds) for which generator can supply full load without input power. Higher \(H\) means more stored kinetic energy, slower frequency changes.
-
Equivalent inertia constant for multiple machines:
\[ H_{\text{eq}} = \frac{\sum_{i=1}^{n} H_i S_i}{\sum_{i=1}^{n} S_i} \]
-
Kinetic energy stored:
\[ \text{KE} = 2 H S_{\text{base}} \ \text{(MW·s or MJ)} \]
-
Rotor acceleration: From swing equation in per unit:
\[ M \frac{d^2 \delta}{dt^2} = P_m - P_e, \quad M = \frac{2H}{\omega_s} \]
Since \(\frac{d\delta}{dt} = \Delta \omega = 2\pi \Delta f\),
\[ \frac{d(\Delta f)}{dt} = \frac{f_s}{2H} (P_m - P_e) \]
For constant power imbalance \(\Delta P\) during acceleration phase (before governor response):
\[ \boxed{\Delta f = \frac{f_0}{2H} \Delta P \cdot t} \]
where \(\Delta P\) in per unit on system base, \(t\) in seconds.
3.4 Load Frequency Control in Interconnected Systems
-
Automatic Load Frequency Control (ALFC) / Automatic Generation Control (AGC):
-
Primary control (Governor droop):
-
Droop \(R = \frac{\Delta f}{\Delta P}\) (Hz per MW or per unit).
-
For a load change \(\Delta P_D\), frequency changes by \(\Delta f = -\frac{\Delta P_D}{1/R + \sum 1/R_i}\) (for parallel generators).
-
Generators share load proportional to \(1/R\) (inverse droop).
-
Frequency regulation: \(R\) determines steady-state frequency deviation.
-
-
Secondary control (Area Control Error - ACE):
-
ACE = \(\Delta P_{\text{tie}} + B \Delta f\), where \(\Delta P_{\text{tie}}\) = tie-line power deviation from schedule, \(B\) = frequency bias constant (often \(B = 1/R\) or based on area load).
-
ACE integrated to adjust speed changer set points (\(\Delta P_{\text{ref}}\)) to drive ACE to zero, restoring frequency and tie-line power to schedule.
-
-
Tie-line modeling: For two areas, tie-line power deviation:
\[ \Delta P_{\text{tie}}(s) = T_{12} \left( \Delta \delta_1(s) - \Delta \delta_2(s) \right) \]
where \(T_{12} = \frac{V_1 V_2}{X_{12}} \cos \delta_{12}^0\). Since \(\Delta \delta_i(s) = \frac{2\pi}{s} \Delta f_i(s)\),
\[ \Delta P_{\text{tie}}(s) = \frac{2\pi T_{12}}{s} (\Delta f_1 - \Delta f_2) = \frac{K_{\text{tie}}}{s} (\Delta f_1 - \Delta f_2) \]
with \(K_{\text{tie}} = 2\pi T_{12}\).
-
3.5 Numerical Problem Example
Problem: A 100 MVA, 50 Hz turbo alternator with \(H = 4.5\ \text{kW·s/kVA}\) (i.e., 4.5 s) operates at no load. A load of 25 MW is suddenly applied. Steam valves open after 0.6 s due to governor delay. Find frequency before steam flow increases.
Solution:
\(\Delta P = 25/100 = 0.25\ \text{p.u.}\), \(t = 0.6\ \text{s}\), \(f_0 = 50\ \text{Hz}\), \(H = 4.5\ \text{s}\).
Acceleration phase:
\[ \Delta f = \frac{f_0}{2H} \Delta P \cdot t = \frac{50}{2 \times 4.5} \times 0.25 \times 0.6 = \frac{50}{9} \times 0.15 = 0.833\ \text{Hz} \]
Frequency drops to \(50 - 0.833 = 49.167\ \text{Hz}\).
4.0 VOLTAGE CONTROL AND REACTIVE POWER MANAGEMENT
4.1 Relationship between Reactive Power Flow and Voltage Profile
-
From transmission line equations (ignoring resistance for long lines):
\[ |V_s| - |V_r| \approx \frac{Q X}{|V|} \]
where \(Q\) is reactive power flow at receiving end.
-
\(Q > 0\) (inductive, absorbing reactive) → voltage drop.
-
\(Q < 0\) (capacitive, generating reactive) → voltage rise.
-
-
Methods for protection and absorption of reactive power:
-
Protection (voltage support): Shunt capacitors, series capacitors, synchronous condensers (over-excited), SVC/STATCOM (generating mode).
-
Absorption (voltage reduction): Shunt reactors, synchronous condensers (under-excited), SVC/STATCOM (absorbing mode).
-
4.2 Generation and Absorption of Reactive Power by Components
| Component | Reactive Power Behavior | Notes |
|---|---|---|
| Synchronous generator | Generates (over-excited) or absorbs (under-excited) | Limited by capability curve. |
| Transmission line | Generates (shunt capacitance) at light load; absorbs (series inductance) always | Net reactive depends on load level. |
| Transformer | Absorbs (magnetizing current + leakage reactance) | Increases with loading. |
| Load | Mostly absorbs (inductive) | Some loads (e.g., arc furnaces) may generate. |
| Shunt capacitor | Generates | Switched, used for voltage support. |
| Shunt reactor | Absorbs | Switched, used for voltage control at light load. |
| Series capacitor | Compensates line reactance, effectively reduces \(X\) | Increases power transfer and stability. |
4.3 Voltage Control Methods
4.3.1 Excitation Systems
-
Need and function: Maintain terminal voltage, control reactive power output, improve transient stability.
-
Types:
-
DC exciters with amplidyne: DC generator driven by prime mover, output amplified by amplidyne (high-gain DC amplifier). Largely obsolete.
-
AC static exciters:
-
AC generator (brushless) with rotating rectifier, or static thyristor rectifier from stator terminals.
-
Fast response, common in modern plants.
-
-
Brushless excitation system:
DiagramCANVAS: Functional block diagram: AC exciter (small AC generator) on same shaft → rotating rectifier (thyristor/diode) → DC output to main generator rotor field. Excitation control via stationary regulator sending firing pulses to rotating thyristors via transformer/telemetry.- Advantages: No brushes/slip rings, low maintenance, fast response.
-
Limiting features:
-
V/Hz limit: Prevents core overflux at low frequency/high voltage.
-
Over-excitation limit: Thermal limit on field winding.
-
Under-excitation limit: Stability limit to prevent loss of synchronism.
-
-
-
Automatic Voltage Regulator (AVR) for turbo generators:
DiagramCANVAS: Block diagram: Voltage sensor (PT) → comparator (with reference \(V_{\text{ref}}\)) → error amplifier → exciter (static/rotating) → generator field. Optional: Power system stabilizer (PSS) input from speed/power.Components: Sensing, excitation control, power stage, limiters.
4.3.2 Shunt and Series Compensation
-
Shunt capacitors/Reactors:
-
Capacitors: Generate reactive power, boost voltage at buses.
-
Reactors: Absorb reactive power, lower voltage.
-
Switched based on voltage levels (e.g., on/off at substations).
-
-
Series capacitors:
-
Connected in series with line to compensate reactance.
-
Increase power transfer capability: \(P_{\max} \propto 1/X_{\text{eq}}\).
-
Issues: Subsynchronous resonance (SSR), need protection (e.g., bypass switch).
-
4.3.3 Tap-changing Transformers
-
On-load tap changers (OLTC): Adjust turns ratio under load to control voltage at a bus. Used for voltage regulation along feeders.
-
Off-circuit tap changers: Manual adjustment when de-energized.
4.3.4 SVC and STATCOM
-
SVC (Static VAR Compensator): Combination of thyristor-controlled reactor (TCR) and thyristor-switched capacitor (TSC). Provides continuous reactive power control.
-
STATCOM (Static Synchronous Compensator): Voltage source converter (VSC) based. Better dynamic response, wider operating range (can generate/absorb), and supports low voltage better.
4.4 Modern Voltage Control Strategies
-
Coordinated control: Multiple devices (AVR, OLTC, SVC, STATCOM) coordinated via centralized or distributed control.
-
Wide-area measurement systems (WAMS): Use PMU data for global voltage stability assessment and control.
-
Adaptive and predictive control: Based on real-time system conditions and forecasts.
5.0 ECONOMIC DISPATCH AND ENERGY PRICING
5.1 Economic Operation of Power Systems
-
Objective: Minimize total fuel cost while meeting load demand and operating constraints (generation limits, line flows).
-
Economic dispatch: Determine optimal power output of each committed generating unit.
5.2 Economic Dispatch Problem
-
Neglecting transmission losses:
-
Incremental fuel cost: \(\lambda_i = \frac{dF_i}{dP_i}\) ($/MWh).
-
Equal incremental cost criterion: \(\lambda_i = \lambda\) for all generators at optimum.
-
Solution: Find \(\lambda\) such that \(\sum P_i = P_D\).
-
-
Including transmission losses:
-
Losses approximated by B-coefficients (loss formula):
\[ P_{\text{loss}} = \sum_{i=1}^{n} \sum_{j=1}^{n} B_{ij} P_i P_j \]
where \(B_{ij}\) are symmetric constants (\(B_{ii} > 0\), \(B_{ij} \geq 0\)).
-
Lagrangian method:
\[ \mathcal{L} = \sum_{i=1}^{n} F_i(P_i) + \lambda \left( P_D + P_{\text{loss}} - \sum_{i=1}^{n} P_i \right) \]
Conditions:
\[ \frac{\partial \mathcal{L}}{\partial P_i} = \frac{dF_i}{dP_i} + \lambda \left( \frac{\partial P_{\text{loss}}}{\partial P_i} - 1 \right) = 0 \]
\[ \Rightarrow \frac{dF_i}{dP_i} = \lambda \left(1 - \frac{\partial P_{\text{loss}}}{\partial P_i} \right) \]
-
Penalty factor for plant \(i\):
\[ \boxed{L_i = \frac{1}{1 - \frac{\partial P_{\text{loss}}}{\partial P_i}}} \]
Then condition becomes: \(\frac{dF_i}{dP_i} \cdot L_i = \lambda\). Plants with high loss contribution (large \(\partial P_{\text{loss}}/\partial P_i\)) have higher \(L_i\), meaning their effective incremental cost is higher.
-
5.3 Pricing of Energy and Transmission Service
-
In deregulated markets, locational marginal pricing (LMP) is common:
\[ \text{LMP}_i = \text{Marginal generation cost} + \text{Loss component} + \text{Congestion component} \]
-
Marginal generation cost: Incremental cost of the marginal generator at that location.
-
Loss component: Cost of incremental losses.
-
Congestion component: Arises when transmission constraints cause price differences across locations.
-
-
Transmission service pricing:
-
Congestion rent: Revenue from LMP differences.
-
Grid usage charges: Postage stamp, path-based, or nodal charges.
-
Ancillary services: Separate markets for frequency control, voltage support, etc.
-
6.0 MODERN POWER SYSTEM ISSUES: DEREGULATION & RESTRUCTURING
6.1 Need for Interconnected Power Systems
-
Necessity:
-
Reliability: Backup during outages, reserve sharing.
-
Economy: Peak load sharing, use of distant cheap generation (e.g., hydro-thermal complementation).
-
Reduced spinning reserve: Shared reserves lower overall requirement.
-
-
Problems:
-
Complex control and operation: Need for coordination among many control areas.
-
Stability issues: Synchronizing many machines, interarea oscillations.
-
Protection coordination: More complex fault currents.
-
Communication and coordination: Essential for AGC and emergency control.
-
6.2 Deregulation and Restructuring
-
Concepts: Unbundling of generation, transmission, distribution into independent entities; introduction of competition in generation and retail.
-
Objectives: Reduce costs, improve efficiency, encourage innovation, customer choice.
-
Models:
-
POOL: Single buyer (system operator) purchases all generation and sells to retailers/consumers.
-
Bilateral: Direct contracts between generators and consumers/retailers.
-
Hybrid: Combination of pool and bilateral markets.
-
-
Effects and challenges:
-
Positive: Lower prices, innovation, customer choice.
-
Challenges:
-
Transmission congestion: Need for congestion management (e.g., LMP).
-
Market power: Abuse by dominant players; mitigation via market design.
-
Investment incentives: Transmission and generation investment in competitive environment.
-
Ancillary services: Separate procurement and pricing.
-
Reliability assurance: Independent system operator (ISO) responsibilities.
-
-
6.3 Distributed Generation (DG)
-
Definition: Small generators (renewable: solar, wind; or conventional: diesel, gas) connected at distribution level or near load centers.
-
Impact:
-
Positive: Reduced transmission losses, improved voltage profile (if properly placed), renewable integration.
-
Challenges:
-
Protection coordination: Bi-directional flows complicate relay settings.
-
Voltage regulation: Reverse power flows may cause overvoltage.
-
Islanding: Unintentional islands during outages.
-
Power quality: Harmonics, flicker.
-
-
Requires smart grid technologies (advanced inverters, communication).
-
6.4 Transmission Open Access (TOA)
-
Definition: Non-discriminatory access to transmission network for all generators and consumers.
-
Role of system operator: Independent entity to:
-
Operate grid securely.
-
Facilitate markets (dispatch, congestion management).
-
Procure ancillary services.
-
Ensure reliability (N-1 security).
-
-
Issues:
-
Tariff design: Fair transmission charges (postage stamp, path-based, nodal).
-
Congestion management: Methods like re-dispatch, load shedding, LMP.
-
Coordination with distribution networks: Especially with DG.
-
Key Formulas Summary (Boxed)
-
Y_bus formation: \(Y_{\text{bus}} = \mathbf{A}^T \mathbf{y} \mathbf{A}\)
-
Swing equation: \(M \frac{d^2 \delta}{dt^2} = P_m - P_e\), \(M = \frac{2H}{\omega_s}\)
-
Linearized swing: \(M \frac{d^2 \Delta\delta}{dt^2} = \Delta P_m - K \Delta\delta\)
-
Frequency deviation (acceleration): \(\Delta f = \frac{f_0}{2H} \Delta P \cdot t\)
-
Tie-line power deviation: \(\Delta P_{\text{tie}}(s) = \frac{K_{\text{tie}}}{s} (\Delta f_1 - \Delta f_2)\)
-
Penalty factor: \(L_i = \frac{1}{1 - \frac{\partial P_{\text{loss}}}{\partial P_i}}\)
-
Loss formula: \(P_{\text{loss}} = \sum_i \sum_j B_{ij} P_i P_j\)
[!TIP] Exam Tips and Common Pitfalls
- Y_bus formation: Always include shunt admittance if given; off-diagonals are negative.
- Gauss-Seidel: For PV buses, after updating voltage, scale to specified |V| and recalculate Q.
- Newton-Raphson: Remember the structure of Jacobian; for PV buses, rows/columns for |V| are omitted.
- Swing equation: Use consistent units. \(H\) in seconds, \(f_0\) in Hz, \(\Delta P\) in per unit.
- EAC: Accelerating area is above \(P_m\) and below \(P_e^{\text{fault}}\); decelerating area is below \(P_m\) and above \(P_e^{\text{post}}\).
- LFC: Primary control reduces frequency deviation but does not restore nominal frequency; secondary control (ACE) does.
- Voltage control: Reactive power flow primarily affects voltage magnitude; active power affects angle.
- Economic dispatch: With losses, plants with high loss contribution (large \(\partial P_{\text{loss}}/\partial P_i\)) have higher penalty factors.
- Deregulation: Understand the difference between pool (single buyer) and bilateral (direct contracts) models.