1. Introduction to Prestressed Concrete
Definition: Prestressing is the intentional introduction of compressive stresses into a concrete member before it sustains service loads, to counteract tensile stresses induced by those loads.
Basic Principle: Pre-compression reduces or eliminates tensile stresses in concrete under load, utilizing the high tensile strength of steel and the relatively low tensile strength of concrete.
Historical Development:
-
Eugène Freyssinet (1928): Pioneer of modern prestressing; developed high-strength steel and hydraulic jacks; introduced pre-tensioning and post-tensioning concepts.
-
Gustave Magnel: Developed the Magnel system for post-tensioning with flat jacks and wedge anchors.
-
Other contributors: Hoyer (pre-tensioning), Gifford-Udall (strand systems).
Classification:
| Basis | Types |
|---|---|
| Method | Pre-tensioning (tension before casting), Post-tensioning (tension after hardening) |
| Bond Condition | Bonded (grouted ducts), Unbonded (individual sheathed tendons) |
| Construction | Pre-cast (factory-made), Cast-in-place (in-situ) |
Typical Applications:
- Bridges (spans 20–50 m), building floors/roofs, water tanks, silos, piles.
[!TIP] Exam Key: Pre-tensioning relies on bond for force transfer; post-tensioning uses mechanical anchorage. Unbonded tendons allow individual stressing and are corrosion-protected.
2. Materials for Prestressed Concrete
Concrete
-
Required Properties:
-
High compressive strength (M40–M80 grade).
-
Low creep and shrinkage.
-
High modulus of elasticity (E<sub>c</sub> ≈ 25–40 GPa).
-
Adequate tensile strength for crack control.
-
-
Stress-Strain Behavior: Approximately linear elastic up to ~0.45f<sub>ck</sub> (per IS 1343), parabolic thereafter.
Prestressing Steel
-
Types:
-
Wires: Cold-drawn, 2–7 mm diameter.
-
Strands: 7-wire helical strands (common), 12.7 mm or 15.2 mm.
-
Alloy Bars: High-strength threaded bars (e.g., 26 mm).
-
-
Mechanical Properties:
-
Ultimate tensile strength f<sub>pu</sub>: 1500–2000 MPa.
-
Modulus E<sub>s</sub>: 190–210 GPa.
-
Relaxation: < 2.5% at 70% f<sub>pu</sub> for low-relaxation strands.
-
Ductility: Elongation ≥ 3.5% at failure.
-
-
Why Mild Steel Unsuitable:
-
Low yield strength (~250 MPa) → requires excessive area.
-
High relaxation → significant prestress losses.
-
Low ultimate strength → inefficient.
-
Bond and Adherence
-
Bond strength depends on:
-
Surface texture (ribbed wires/strands enhance mechanical interlock).
-
Concrete strength and compaction.
-
Tendon diameter and configuration.
-
[!TIP] Exam Pitfall: Confusing steel grades. Prestressing steel is high-tensile (f<sub>pu</sub> > 1000 MPa), not mild (f<sub>y</sub> ~ 250 MPa).
3. Prestressing Systems and Methods
Pre-tensioning Process
-
Tendons tensioned against rigid abutments using hydraulic jacks.
-
Concrete cast and cured.
-
Tendons released → force transferred via bond to concrete.
- Equipment: Casting beds, stressing jacks, abutments.
Post-tensioning Process
-
Ducts/sleeves placed in formwork.
-
Concrete cast and cured.
-
Tendons inserted and tensioned using jacks against anchorages.
-
Ducts grouted (bonded) or left unbonded.
-
Anchorage Systems: Wedge-type, bearing plate with nuts.
-
Tendon Arrangements: Bunched (multi-strand) or individual.
Major Commercial Systems
| System | Key Features | Schematic |
|---|---|---|
| Freyssinet | Multi-wire tendons; conical wedges in anchor plate; used for pre- & post-tensioning | DiagramSEARCH: Freyssinet prestressing system |
| Hoyes | Flat jacks; threaded bars with nuts; bearing plates; post-tensioning only | DiagramSEARCH: Hoyes prestressing system |
| Magnel | Flat jacks; wedge anchors; efficient for large forces; post-tensioning | DiagramSEARCH: Magnel prestressing system |
| Gifford-Udall | Strand tendons; button-type anchors; grouted; common in bridges | DiagramSEARCH: Gifford-Udall system |
Comparative Analysis
-
Pre-tensioning: Economical for repetitive precast units; limited to factory production.
-
Post-tensioning: Flexible for cast-in-place and large spans; higher initial cost but adaptable.
-
Bonded vs Unbonded: Bonded provides composite action, unbonded allows individual monitoring and less friction loss.
[!TIP] Exam Focus: Freyssinet uses conical wedges; Hoyes uses threaded bars with nuts. Know which are pre- vs post-tensioning systems.
4. Fundamental Concepts and Theory
Basic Assumptions in Elastic Analysis
-
Concrete is homogeneous, isotropic, linearly elastic (within service limits).
-
Plane sections remain plane (Bernoulli hypothesis).
-
Prestressing force magnitude constant along tendon (ignoring losses initially).
-
No slip between tendon and concrete (for bonded systems).
-
Effects of shear deformation and torsion neglected.
Stress Concepts
-
Initial Prestress (f<sub>pi</sub>): Stress in tendon immediately after tensioning.
-
Effective Prestress (f<sub>pe</sub>): Stress in tendon after all losses, at service stage.
$$\boxed{f_{pe} = f_{pi} - \Delta f_p}$$
where Δf<sub>p</sub> = total losses.
-
Stages:
-
Transfer: Stress in concrete just after tendon release (pre-tensioning) or stressing (post-tensioning).
-
Service: Under external loads, after losses.
-
Permissible Stresses (IS 1343)
| Stage | Concrete Compression | Concrete Tension |
|---|---|---|
| Transfer | ≤ 0.45 f<sub>ci</sub> | ≤ 1.0 MPa (Class 1: 0) |
| Service | ≤ 0.30 f<sub>ck</sub> | ≤ 0.25 f<sub>ct</sub> (Class 3) |
Advantages
- Increased load capacity, longer spans, reduced deflection, crack control, material savings, durability.
Disadvantages
- Higher initial cost, specialized labor/equipment, complex design/analysis, inspection difficulties.
Partial Prestressing (IS 1343)
-
Definition: Prestressing level such that tensile stresses exceed allowable limits under service loads, but within controlled limits.
-
Classification:
-
Class 1: No tension under moderate loads (full prestressing).
-
Class 2: Tension allowed but within limits; cracks tightly controlled.
-
Class 3: Tension allowed; cracks permitted but limited in width.
-
-
Merits: Economical (less steel), easier construction.
-
Demerits: Some cracking, increased deflection, reduced durability.
[!TIP] Exam Tip: Partial prestressing is a compromise between reinforced and fully prestressed concrete. Class 3 allows visible cracks but limits width.
5. Analysis of Prestressed Concrete Sections
Stress Distribution
-
Prestress Only:
-
Concentric tendon: Uniform compression σ<sub>c</sub> = P/A ± Pe/I.
-
Eccentric tendon: Linear stress distribution with moment Pe.
-
-
With External Loads: Superposition principle.
$$\sigma_c = \frac{P}{A} \pm \frac{Pe}{I} + \frac{M_y}{I} \cdot y$$
- Critical Sections: Midspan (max moment), supports (max shear, possible negative moment), discontinuities (sudden area change).
Load Balancing Concept
-
Principle: Shape tendon profile to provide upward force balancing applied loads, resulting in zero net moment.
-
Balanced Load (for parabolic tendon with eccentricity e at midspan, zero at supports):
$$w_{bal} = \frac{8Pe}{L^2}$$
- Equivalent Loads: From tendon profile, compute forces on concrete (e.g., vertical component for draped tendons).
Primary and Secondary Moments (Continuous Beams)
-
Primary Moments: Direct from prestress in a statically determinate system.
-
Secondary Moments: Induced by reactions at redundant supports in continuous beams.
-
Resultant Moment: Vector sum of primary and secondary moments at each section.
-
Calculation Methods:
-
Force Method: Release redundants, compute compatibility.
-
Displacement Method: Use stiffness matrix.
-
Linear Transformation of Tendon Profile
-
Concept: Adding a straight line to tendon profile (keeping end eccentricities constant) does not change support reactions or secondary moments.
-
Condition: For continuous beams, linear transformation possible if end eccentricities unchanged; alters primary moments but resultant moments same.
Shear Analysis
- Shear Stress in Uncracked Section:
$$\tau = \frac{VQ}{Ib} + \frac{P e}{I} \cdot \frac{dA}{dx}$$
(for draped tendons, vertical component contributes).
-
Contribution of Prestress: Increases shear capacity by providing compressive stress on shear plane.
-
Shear Resistance at Supports: Check concrete shear capacity V<sub>c</sub> enhanced by prestress:
$$V_c = \tau_c b d + \sigma_{cp} b d$$
where σ<sub>cp</sub> = P/A + P e/I.
[!TIP] Exam Focus: Load balancing simplifies design for simply supported beams. In continuous beams, always consider secondary moments. Shear design includes prestress effect via σ<sub>cp</sub>.
6. Design of Prestressed Concrete Members
Design Approaches
-
Working Stress Method (WSM): Elastic analysis, service loads. Used for stress checks at transfer/service.
-
Limit State Method (LSM): Ultimate strength design, factored loads. Primary for flexure/shear design per IS 1343.
-
Code: IS 1343 (Indian Standard for Prestressed Concrete).
Flexural Design
-
Rectangular Section (LSM):
-
Strain compatibility: Concrete strain ε<sub>c</sub> = 0.0035 (ultimate), steel strain ε<sub>s</sub> = (d - x)/x * ε<sub>c</sub>.
-
Stress block: 0.36 f<sub>ck</sub> for concrete in compression (IS 1343 similar to IS 456).
-
Ultimate moment:
-
$$M_u = 0.87 f_y A_p \left(d - 0.42 x_u\right)$$
(under-reinforced, x<sub>u</sub> ≤ 0.48 d for Fe 415).
-
T-Section:
-
Check if neutral axis in flange (x<sub>u</sub> ≤ D<sub>f</sub>).
-
Flange contribution: b<sub>f</sub> D<sub>f</sub> * 0.36 f<sub>ck</sub>.
-
Shear Design
- Concrete Shear Capacity:
$$V_c = \tau_c b d + \sigma_{cp} b d$$
where τ<sub>c</sub> from IS 1343 Table, σ<sub>cp</sub> = P/A + P e/I (prestress contribution).
- Shear Reinforcement: Required if V > V<sub>c</sub>. Design as per IS 1343.
Stress Checks
-
At Transfer:
-
Compression: σ<sub>c</sub> ≤ 0.45 f<sub>ci</sub>
-
Tension: σ<sub>t</sub> ≤ allowable (1 MPa for Class 1).
-
-
At Service:
-
Compression: σ<sub>c</sub> ≤ 0.30 f<sub>ck</sub>
-
Tension: σ<sub>t</sub> ≤ 0.25 f<sub>ct</sub> (Class 3).
-
Design Examples (Past Paper Patterns)
-
Post-tensioned Girder: Given span, loads, materials, loss ratio → determine tendon area.
-
Pre-tensioned I-Beam: Check stresses at transfer/service, compute moment capacity.
-
Incorporate Loss Ratio: Use λ = f<sub>pe</sub>/f<sub>pi</sub> in design.
[!TIP] Common Error: Forgetting to check both transfer and service stresses. In T-sections, always verify flange effectiveness (x<sub>u</sub> ≤ D<sub>f</sub>).
7. Losses of Prestress
Categories
| Immediate Losses | Time-Dependent Losses |
|---|---|
| Elastic shortening | Creep of concrete |
| Friction | Shrinkage of concrete |
| Anchorage slip | Relaxation of steel |
Calculation Methods
-
Elastic Shortening (Δf<sub>pES</sub>):
- Pre-tensioning: All tendons lose simultaneously.
$$\Delta f_{pES} = \frac{A_p E_p}{A_c E_c} f_{c}$$
- Post-tensioning (successive): Earlier tendons lose due to later tensioning.
$$\Delta f_{pES} = \frac{A_p E_p}{A_c E_c} \cdot \frac{\sum (P_i \cdot e_i)}{I_c} \cdot y_p$$
- Friction Loss (Δf<sub>pF</sub>):
$$\Delta f_{pF} = f_{pi} \left(1 - e^{-(\mu \theta + k x)}\right)$$
where μ = wobble coefficient, k = curvature coefficient, θ = total angular change, x = length.
- Anchorage Slip (Δf<sub>pA</sub>):
$$\Delta f_{pA} = \frac{P_{slip} A_p}{A_p E_p} \cdot e^{-\mu \theta}$$
(loss over slip length).
-
Creep & Shrinkage (IS 1343):
-
Creep loss: Δf<sub>pCR</sub> = (E<sub>p</sub>/E<sub>c</sub>) · f<sub>c</sub> · φ(t, t<sub>i</sub>)
-
Shrinkage loss: Δf<sub>pSH</sub> = (E<sub>p</sub>/E<sub>c</sub>) · ε<sub>sh</sub> · (A<sub>c</sub>/A<sub>p</sub>) (approx.)
-
-
Relaxation (Δf<sub>pR</sub>): From IS 1343 graphs/tables based on f<sub>pi</sub>/f<sub>pu</sub> and time.
Total Loss & Effective Prestress
$$\boxed{f_{pe} = f_{pi} - \sum \Delta f_p}$$
- Loss Ratio: λ = f<sub>pe</sub>/f<sub>pi</sub> (typically 0.7–0.85). Used in preliminary design to size tendons.
[!TIP] Exam Calculation: For successive tensioning in post-tensioning, compute elastic loss for each tendon sequentially. Friction loss depends on tendon profile; use μ and k from code.
8. Anchorage Zone and End Block Reinforcement
Anchorage Zone Concept
-
End Block: Region behind anchor where stress disperses.
-
Transmission Zone: Where prestress spreads to uniform stress.
-
Bearing Zone: Under anchor plate.
Stresses in Anchorage Zone
-
Bursting Tension: Horizontal tension due to stress dispersion (like a bottle bursting).
-
Spalling Tension: Vertical tension near top/bottom surfaces.
-
Splitting Tension: Radial tension around anchor.
Design of End Block Reinforcement (IS 1343 Annex)
- Bursting Force:
$$F_{br} = \sigma_{br} \cdot A_{br}$$
where σ<sub>br</sub> from stress distribution (linear dispersion assumed).
-
Spalling Force: Vertical tension at edges.
-
Splitting Force: Radial tension, resisted by spiral or circular reinforcement.
- Reinforcement: Provide steel (grid, spiral, or distributed bars) to resist computed forces. Minimum reinforcement as per code.
Anchorage Devices
- Wedge-type (Freyssinet), bearing plate with nuts (Magnel/Hoyes), button-type (Gifford-Udall).
[!TIP] Exam Focus: Bursting tension governs horizontal reinforcement. Use IS 1343 Annex formulas for F<sub>br</sub>. Sketch end block with reinforcement detailing.
9. Composite Construction
Definition and Types
-
Precast Pretensioned Beam + Cast-in-situ Slab
-
Precast Post-tensioned Beam + Cast-in-situ Slab
Composite Action
-
Shear Transfer: At interface via:
-
Roughened surface.
-
Shear keys.
-
Studs (for steel beams).
-
-
Effective Width of Flange (IS 456):
$$b_f = b_w + \frac{L_0}{6} \text{ or } b_w + 0.5 \times \text{spacing},$$
whichever less.
Differential Effects
-
Shrinkage & Creep: Cast-in-situ slab shrinks/creeps more than precast beam → induces stresses.
-
Shrinkage Stress Calculation:
-
Compute free shrinkage strain ε<sub>sh</sub> of cast-in-situ part.
-
Use transformed section to find compatible strain → stress in each material.
-
Example: For T-beam composite, shrinkage in slab causes negative moment in beam.
-
Design Considerations
-
Interface shear check.
-
Differential deflection.
-
Construction sequence (precast beam must support wet slab).
[!TIP] Exam Problem: Given differential shrinkage ε<sub>sh</sub>, find stresses using transformed section method. Assume no slip at interface.
10. Partial Prestressing
Concept and Necessity
-
Concept: Prestressing level such that tensile stresses exceed allowable under service loads but within limits for controlled cracking.
-
Necessity: Economical for moderate spans where full prestressing is overkill.
Methods to Achieve
-
Reduce prestressing steel area A<sub>p</sub>.
-
Use lower grade steel (lower f<sub>pu</sub>).
-
Permit controlled cracking (Class 3 per IS 1343).
Merits and Demerits
| Merits | Demerits |
|---|---|
| Lower initial cost | Some cracking under service loads |
| Less steel → easier placement | Increased long-term deflection |
| Suitable for moderate spans | Reduced durability if cracks wide |
Suitable Applications
- Floor slabs, parking structures, where slight cracking acceptable.
[!TIP] Partial prestressing is a middle ground. Class 3 allows visible cracks but limits width (< 0.2 mm per IS 1343).
11. Special Topics
Tendon Profiles
-
Straight: Constant eccentricity; simple but limited moment control.
-
Draped/Harped: Two or more straight segments; used for moment variation.
-
Parabolic: For uniformly distributed loads; gives linear moment diagram.
-
Concordant Profile: Produces zero secondary moments in continuous beams (requires solving linear equations).
Guyon's Method
-
For moment redistribution in continuous prestressed beams by adjusting tendon profiles.
-
Ensures resultant moments within limits without overstressing concrete.
Flexural Failure Modes
-
Tension Failure: Steel yields before concrete crushes (ductile).
-
Compression Failure: Concrete crushes prematurely (brittle).
-
Balanced Failure: Both steel yields and concrete crushes simultaneously (ideal).
Deflection Behavior
-
Short-term: Elastic analysis, includes prestress effect.
-
Long-term: Increased by creep, shrinkage, sustained loads.
-
Calculation (IS 456/1343):
-
Compute short-term deflection.
-
Apply multipliers for creep, shrinkage (e.g., α = 2.0 for sustained loads).
-
[!TIP] Concordant profile eliminates secondary moments in continuous beams. Deflection calculations require effective moment of inertia for cracked sections.
12. Design Examples and Case Studies
Based on past papers (RGPV CE-702(A)):
-
Post-tensioned Girder:
-
Given: span, loads (dead/live), concrete grade, permissible stresses, loss ratio.
-
Determine: Number of wires/strands, tendon profile, check stresses.
-
-
Pre-tensioned I-beam:
-
Given: span, load, concrete/steel grades, initial stress.
-
Design: Section dimensions, tendon area, stress checks.
-
-
Anchorage Zone Design:
-
Given: end block dimensions, cable arrangement, jacking force.
-
Design: Bursting/spalling reinforcement as per IS 1343 Annex.
-
-
Loss Calculation:
-
Multi-stage tensioning → compute elastic losses sequentially.
-
Include friction, creep, shrinkage, relaxation.
-
-
Composite Beam:
-
Given: precast beam + cast-in-situ slab, differential shrinkage ε<sub>sh</sub>.
-
Determine: Shrinkage stresses in each part using transformed section.
-
[!TIP] Always start design with loss ratio (λ) to estimate f<sub>pe</sub>. For anchorage design, compute bursting force first. In composite sections, use modular ratio m = E<sub>c2</sub>/E<sub>c1</sub>.