Skip to content
CE-503 (C) · Quantity surveying & Costing/Quick Revision Short Notes

Quantity surveying & Costing (CE-503 (C)) - Unit 1 Short Notes

UNIT 1: FUNDAMENTALS OF ESTIMATION, COSTING AND VALUATION


1.1 Introduction to Estimation

Purpose and Importance:

  • Purpose: To ascertain the probable cost of construction before commencement, enabling financial planning, budget control, and sanctioning.

  • Importance:

    • Provides basis for tender and contract agreements.

    • Helps in securing loans/financial assistance.

    • Enables comparison of design alternatives.

    • Acts as a control document during execution.

Types of Estimates (Hierarchy of Accuracy & Detail):

Type of Estimate Purpose Accuracy Prepared For
Rough / Approximate Estimate Preliminary cost assessment for feasibility. ±10-20% Initial project approval, concept stage.
Detailed Estimate Item-wise quantity take-off and costing for construction. ±5-10% Tender documentation, contract agreement.
Abstract Estimate Summary of detailed estimate grouped by work categories. Same as detailed Quick cost review, financial summary.
Revised Estimate When original estimate exceeds sanctioned amount (usually >5%). Same as detailed Seeking revised approval/sanction.
Supplementary Estimate For additional/modified work after project start. Same as detailed Approval for variations/extensions.

[!TIP] Exam Focus: Distinguish between Revised (excess over sanctioned estimate) and Supplementary (new/additional items) estimates with examples (e.g., foundation change vs. adding a new room).


1.2 Preparation of Detailed Estimates

Data Required:

  1. Drawings: Plans, elevations, sections, detailed drawings.

  2. Specifications: Detailed description of materials, workmanship, standards.

  3. Rates: Current Schedule of Rates (CSR) or prevailing market rates.

  4. Bye-laws & Standards: Local building regulations, IS codes.

Step-by-Step Procedure:

  1. Take-off Quantities: Measure dimensions from drawings for each item (e.g., length, breadth, depth).

  2. Calculate Net Quantities: Apply deduction rules (see 1.3).

  3. Abstract Quantities: Group similar items (e.g., all brickwork) and sum net quantities.

  4. Apply Rates: Multiply abstract quantities by respective unit rates.

  5. Calculate Total Cost: Sum costs of all items.

  6. Add Contingencies & Overheads: Include petty supervision, contingencies, etc.

  7. Prepare Abstract Sheet: Final summarized cost statement.

Factors to be Considered:

  • Site conditions (soil, accessibility, water table).

  • Material availability & transportation.

  • Labor skill & productivity.

  • Seasonal impacts (monsoon, winter).

  • Proper measurement units (IS 1200).

  • Wastage allowances (material, labor).

[!TIP] Common Pitfall: Forgetting to apply deduction rules for openings (doors, windows) in masonry/plastering, leading to overestimation.

Example: Rough Estimate for Commercial Complex (Plinth Area Method) Given: Plinth Area = 500 m²/floor, No. of storeys = G+2 (3 floors), Total Plinth Area = 1500 m².

Plinth Area Rate = Rs. 3500/m² (assumed for structure).

Additional percentages: WSS 8%, Electrification 6%, Fluctuation 5%, Profit 10%, Petty Sup. & Cont. 3%.

Calculation:

  1. Structured Cost = Total Plinth Area × Rate = 1500 × 3500 = Rs. 52,50,000

  2. Add for Services & Contingencies:

    • WSS: 8% of 52,50,000 = 4,20,000

    • Electrification: 6% = 3,15,000

    • Fluctuation: 5% = 2,62,500

    • Profit: 10% = 5,25,000

    • Petty Sup. & Cont.: 3% = 1,57,500

  3. Total Estimated Cost = 52,50,000 + (4,20,000+3,15,000+2,62,500+5,25,000+1,57,500)

    = 52,50,000 + 16,80,000 = Rs. 69,30,000

Alternatively, using Cubical Content:

Total Volume = Plinth Area × Height per storey × No. of storeys = 500 × 3.5 × 3 = 5250 m³.

Rate = Rs. 1000/m³ → Structured Cost = 52,50,000 (same as above if rate adjusted).


1.3 Estimation Methods and Techniques

A. Building Estimation: Long Wall & Short Wall Method
  • Principle: Walls along the longitudinal direction are "long walls"; those perpendicular are "short walls." Their lengths vary with each course due to footing steps.

  • Procedure:

    1. Find center line lengths of walls from plan.

    2. For each footing/section, calculate individual long/short wall lengths using:

    • Long Wall Length = Center Line Length + (½ × Width of Footing on one side) + (½ × Width of Footing on other side) for that level.

    • Short Wall Length = Center Line Length - (½ × Width of Footing on one side) - (½ × Width of Footing on other side).

    1. Multiply by respective breadth/height and sum.

Example: For a single room 5m × 4m (external dimensions), wall thickness 0.3m.

  • Center Line Length (Long Wall) = 5m, (Short Wall) = 4m.

  • If footing width at foundation = 0.6m, then:

    • Long Wall at foundation = 5 + (0.6/2) + (0.6/2) = 5.6m.

    • Short Wall at foundation = 4 - 0.3 - 0.3 = 3.4m.

[!TIP] Exam Tip: This method is essential for masonry quantity in foundations/plinth where wall lengths change due to footing offsets.

B. Earthwork Calculation for Roads
  • Mid-Sectional Area Method:

    • Area at midpoint of two sections is used.

    • Volume between two sections = Average Area × Distance.

$$ \text{Volume} = \left( \frac{A_1 + A_2}{2} \right) \times d $$

where \(A_1, A_2\) are cross-sectional areas at chainages.

  • Mean Sectional Area Method (for long embankments/cuttings):

    • Calculate area at both ends of a length.

    • Mean Area = \( \frac{A_1 + A_2}{2} \)

    • Volume = Mean Area × Distance between sections.

    • For Embankment/Cutting with Slopes:

      • Cross-sectional area depends on side slopes.

      • Embankment: \( A = (B + Z \cdot H) \cdot H \)

        where \(B\) = top width, \(H\) = height, \(Z\) = slope (horizontal:vertical).

      • Cutting: \( A = (B + Z \cdot H) \cdot H \) (same formula, but \(H\) is depth of cutting).

Example (from Jun 2025):

Length = 0.5 km = 500 m, Top width \(B\) = 4 m, Depth \(H\) = 2 m, Slope \(Z\) = 1.5:1.

Assuming uniform cross-section:

\( A = (4 + 1.5 \times 2) \times 2 = (4 + 3) \times 2 = 14 \, \text{m}^2 \)

Volume = \( 14 \times 500 = 7000 \, \text{m}^3 \).

C. Material Statements
  • For M20 Grade Concrete (1:1.5:3 by volume, but often 1:2:4 by volume for RCC):

    • Note: IS 10262:2019 uses design mix, but for site estimates, nominal mix ratios are used.

    • For 1 m³ of R.C.C. (1:2:4):

      • Total parts = 1+2+4 = 7.

      • Cement = \( \frac{1}{7} \) m³ = 0.1428 m³ → Bags (50kg/bag, density 1440 kg/m³) = \( \frac{0.1428 \times 1440}{50} \) ≈ 4.11 bags.

      • Sand = \( \frac{2}{7} \) m³ = 0.2857 m³.

      • Aggregate = \( \frac{4}{7} \) m³ = 0.5714 m³.

    • Add 5-10% wastage for bulkage (sand) and wastage.

D. Deduction Rules (IS 1200)
  • In Masonry Work:

    • No deduction for opening ≤ 0.1 m².

    • For openings > 0.1 m²:

      • Deduct area of opening only (not extra for lintels, sills) if opening area ≤ 0.5 m².

      • Deduct area of opening + area of lintel/sill (if specified) if opening area > 0.5 m².

      • For rectangular openings, deduct full area; for arched, deduct area up to springing line + ½ of arch area.

  • In Plastering/Painting:

    • Deduct area of opening if opening area > 0.5 m².

    • No deduction for openings ≤ 0.5 m².

    • No addition for jambs, reveals, soffits.

[!TIP] Common Error: Confusing rules for masonry (deduct lintel area only for large openings) vs. plastering (deduct only opening area for large openings).

E. Quantity Take-off for Specific Items
  1. Earthwork in Excavation (Foundation): Measure net volume after deducting for column/pedestal pits if specified.

  2. Lime Concrete in Foundation: Area × Thickness (usually 150-300 mm).

  3. Brickwork:

    • Foundation/Plinth: Use long wall/short wall method with step lengths.

    • Superstructure: Use center line method (if no footing steps) or individual wall lengths.

  4. Damp Proof Course (DPC): Length × Breadth (usually 2.5 cm thick).

  5. Drainage: Pipes (length), manholes (nos.), chambers (volume).

  6. Electrification: Points (nos.), wiring (length), sub-station (volume).

  7. Culvert: Components (abutments, wing walls, bed, slab/pipe) – measure individually.


1.4 Rate Analysis and Costing Principles

Definition & Objectives:

  • Definition: Determining the rate per unit of work by breaking down costs of materials, labor, equipment, overheads, and profit.

  • Objectives:

    • To fix fair rates for items of work.

    • To control costs during execution.

    • To compare contractor bids.

    • To prepare detailed estimates.

Factors Affecting Rate Analysis:

  1. Material Costs: Purchase price + transportation + taxes + wastage (typically 5-10% for bricks/sand, 2-5% for cement).

  2. Labor Costs: Skilled/unskilled wages, task work rates, overtime, welfare.

  3. Equipment & Tools: Depreciation, hire charges, fuel, maintenance.

  4. Overhead Charges: Site establishment, supervision, utilities, insurance (usually 5-10% of total).

  5. Contractor's Profit: Risk factor, competition, project size (usually 10-15%).

  6. Fluctuation of Rates: Market volatility of materials/labor.

Principle of Units:

  • Follow IS 1200 for standard units:

    • m, m², m³ for length, area, volume.

    • kg, quintal, tonne for weight.

    • no., each for countable items (doors, windows).

    • running meter (rm) for pipes, wires.

Preparation of Rate Analysis: Example for Lime Concrete (1:2:6 with brick ballast) Assume 1 m³ of lime concrete in foundation.

Item Quantity Unit Rate (Rs.) Amount (Rs.)
Materials:
Lime 0.25 m³ m³ 2500 625
Surkhi 0.50 m³ m³ 1200 600
Brick Ballast (40mm) 0.75 m³ m³ 900 675
Labor:
Mason (1st class) 0.8 no. 600 480
Mason (2nd class) 1.2 no
Go to where you left off?

Quick Add to Notes

Save questions, your own notes and screenshots into notes filed by unit. It takes a free account.

Create free account

Have an account? Log in