UNIT 1: FUNDAMENTALS OF ESTIMATION, COSTING AND VALUATION
1.1 Introduction to Estimation
Purpose and Importance:
-
Purpose: To ascertain the probable cost of construction before commencement, enabling financial planning, budget control, and sanctioning.
-
Importance:
-
Provides basis for tender and contract agreements.
-
Helps in securing loans/financial assistance.
-
Enables comparison of design alternatives.
-
Acts as a control document during execution.
-
Types of Estimates (Hierarchy of Accuracy & Detail):
| Type of Estimate | Purpose | Accuracy | Prepared For |
|---|---|---|---|
| Rough / Approximate Estimate | Preliminary cost assessment for feasibility. | ±10-20% | Initial project approval, concept stage. |
| Detailed Estimate | Item-wise quantity take-off and costing for construction. | ±5-10% | Tender documentation, contract agreement. |
| Abstract Estimate | Summary of detailed estimate grouped by work categories. | Same as detailed | Quick cost review, financial summary. |
| Revised Estimate | When original estimate exceeds sanctioned amount (usually >5%). | Same as detailed | Seeking revised approval/sanction. |
| Supplementary Estimate | For additional/modified work after project start. | Same as detailed | Approval for variations/extensions. |
[!TIP] Exam Focus: Distinguish between Revised (excess over sanctioned estimate) and Supplementary (new/additional items) estimates with examples (e.g., foundation change vs. adding a new room).
1.2 Preparation of Detailed Estimates
Data Required:
-
Drawings: Plans, elevations, sections, detailed drawings.
-
Specifications: Detailed description of materials, workmanship, standards.
-
Rates: Current Schedule of Rates (CSR) or prevailing market rates.
-
Bye-laws & Standards: Local building regulations, IS codes.
Step-by-Step Procedure:
-
Take-off Quantities: Measure dimensions from drawings for each item (e.g., length, breadth, depth).
-
Calculate Net Quantities: Apply deduction rules (see 1.3).
-
Abstract Quantities: Group similar items (e.g., all brickwork) and sum net quantities.
-
Apply Rates: Multiply abstract quantities by respective unit rates.
-
Calculate Total Cost: Sum costs of all items.
-
Add Contingencies & Overheads: Include petty supervision, contingencies, etc.
-
Prepare Abstract Sheet: Final summarized cost statement.
Factors to be Considered:
-
Site conditions (soil, accessibility, water table).
-
Material availability & transportation.
-
Labor skill & productivity.
-
Seasonal impacts (monsoon, winter).
-
Proper measurement units (IS 1200).
-
Wastage allowances (material, labor).
[!TIP] Common Pitfall: Forgetting to apply deduction rules for openings (doors, windows) in masonry/plastering, leading to overestimation.
Example: Rough Estimate for Commercial Complex (Plinth Area Method) Given: Plinth Area = 500 m²/floor, No. of storeys = G+2 (3 floors), Total Plinth Area = 1500 m².
Plinth Area Rate = Rs. 3500/m² (assumed for structure).
Additional percentages: WSS 8%, Electrification 6%, Fluctuation 5%, Profit 10%, Petty Sup. & Cont. 3%.
Calculation:
-
Structured Cost = Total Plinth Area × Rate = 1500 × 3500 = Rs. 52,50,000
-
Add for Services & Contingencies:
-
WSS: 8% of 52,50,000 = 4,20,000
-
Electrification: 6% = 3,15,000
-
Fluctuation: 5% = 2,62,500
-
Profit: 10% = 5,25,000
-
Petty Sup. & Cont.: 3% = 1,57,500
-
-
Total Estimated Cost = 52,50,000 + (4,20,000+3,15,000+2,62,500+5,25,000+1,57,500)
= 52,50,000 + 16,80,000 = Rs. 69,30,000
Alternatively, using Cubical Content:
Total Volume = Plinth Area × Height per storey × No. of storeys = 500 × 3.5 × 3 = 5250 m³.
Rate = Rs. 1000/m³ → Structured Cost = 52,50,000 (same as above if rate adjusted).
1.3 Estimation Methods and Techniques
A. Building Estimation: Long Wall & Short Wall Method
-
Principle: Walls along the longitudinal direction are "long walls"; those perpendicular are "short walls." Their lengths vary with each course due to footing steps.
-
Procedure:
-
Find center line lengths of walls from plan.
-
For each footing/section, calculate individual long/short wall lengths using:
-
Long Wall Length = Center Line Length + (½ × Width of Footing on one side) + (½ × Width of Footing on other side) for that level.
-
Short Wall Length = Center Line Length - (½ × Width of Footing on one side) - (½ × Width of Footing on other side).
- Multiply by respective breadth/height and sum.
-
Example: For a single room 5m × 4m (external dimensions), wall thickness 0.3m.
-
Center Line Length (Long Wall) = 5m, (Short Wall) = 4m.
-
If footing width at foundation = 0.6m, then:
-
Long Wall at foundation = 5 + (0.6/2) + (0.6/2) = 5.6m.
-
Short Wall at foundation = 4 - 0.3 - 0.3 = 3.4m.
-
[!TIP] Exam Tip: This method is essential for masonry quantity in foundations/plinth where wall lengths change due to footing offsets.
B. Earthwork Calculation for Roads
-
Mid-Sectional Area Method:
-
Area at midpoint of two sections is used.
-
Volume between two sections = Average Area × Distance.
-
$$ \text{Volume} = \left( \frac{A_1 + A_2}{2} \right) \times d $$
where \(A_1, A_2\) are cross-sectional areas at chainages.
-
Mean Sectional Area Method (for long embankments/cuttings):
-
Calculate area at both ends of a length.
-
Mean Area = \( \frac{A_1 + A_2}{2} \)
-
Volume = Mean Area × Distance between sections.
-
For Embankment/Cutting with Slopes:
-
Cross-sectional area depends on side slopes.
-
Embankment: \( A = (B + Z \cdot H) \cdot H \)
where \(B\) = top width, \(H\) = height, \(Z\) = slope (horizontal:vertical).
-
Cutting: \( A = (B + Z \cdot H) \cdot H \) (same formula, but \(H\) is depth of cutting).
-
-
Example (from Jun 2025):
Length = 0.5 km = 500 m, Top width \(B\) = 4 m, Depth \(H\) = 2 m, Slope \(Z\) = 1.5:1.
Assuming uniform cross-section:
\( A = (4 + 1.5 \times 2) \times 2 = (4 + 3) \times 2 = 14 \, \text{m}^2 \)
Volume = \( 14 \times 500 = 7000 \, \text{m}^3 \).
C. Material Statements
-
For M20 Grade Concrete (1:1.5:3 by volume, but often 1:2:4 by volume for RCC):
-
Note: IS 10262:2019 uses design mix, but for site estimates, nominal mix ratios are used.
-
For 1 m³ of R.C.C. (1:2:4):
-
Total parts = 1+2+4 = 7.
-
Cement = \( \frac{1}{7} \) m³ = 0.1428 m³ → Bags (50kg/bag, density 1440 kg/m³) = \( \frac{0.1428 \times 1440}{50} \) ≈ 4.11 bags.
-
Sand = \( \frac{2}{7} \) m³ = 0.2857 m³.
-
Aggregate = \( \frac{4}{7} \) m³ = 0.5714 m³.
-
-
Add 5-10% wastage for bulkage (sand) and wastage.
-
D. Deduction Rules (IS 1200)
-
In Masonry Work:
-
No deduction for opening ≤ 0.1 m².
-
For openings > 0.1 m²:
-
Deduct area of opening only (not extra for lintels, sills) if opening area ≤ 0.5 m².
-
Deduct area of opening + area of lintel/sill (if specified) if opening area > 0.5 m².
-
For rectangular openings, deduct full area; for arched, deduct area up to springing line + ½ of arch area.
-
-
-
In Plastering/Painting:
-
Deduct area of opening if opening area > 0.5 m².
-
No deduction for openings ≤ 0.5 m².
-
No addition for jambs, reveals, soffits.
-
[!TIP] Common Error: Confusing rules for masonry (deduct lintel area only for large openings) vs. plastering (deduct only opening area for large openings).
E. Quantity Take-off for Specific Items
-
Earthwork in Excavation (Foundation): Measure net volume after deducting for column/pedestal pits if specified.
-
Lime Concrete in Foundation: Area × Thickness (usually 150-300 mm).
-
Brickwork:
-
Foundation/Plinth: Use long wall/short wall method with step lengths.
-
Superstructure: Use center line method (if no footing steps) or individual wall lengths.
-
-
Damp Proof Course (DPC): Length × Breadth (usually 2.5 cm thick).
-
Drainage: Pipes (length), manholes (nos.), chambers (volume).
-
Electrification: Points (nos.), wiring (length), sub-station (volume).
-
Culvert: Components (abutments, wing walls, bed, slab/pipe) – measure individually.
1.4 Rate Analysis and Costing Principles
Definition & Objectives:
-
Definition: Determining the rate per unit of work by breaking down costs of materials, labor, equipment, overheads, and profit.
-
Objectives:
-
To fix fair rates for items of work.
-
To control costs during execution.
-
To compare contractor bids.
-
To prepare detailed estimates.
-
Factors Affecting Rate Analysis:
-
Material Costs: Purchase price + transportation + taxes + wastage (typically 5-10% for bricks/sand, 2-5% for cement).
-
Labor Costs: Skilled/unskilled wages, task work rates, overtime, welfare.
-
Equipment & Tools: Depreciation, hire charges, fuel, maintenance.
-
Overhead Charges: Site establishment, supervision, utilities, insurance (usually 5-10% of total).
-
Contractor's Profit: Risk factor, competition, project size (usually 10-15%).
-
Fluctuation of Rates: Market volatility of materials/labor.
Principle of Units:
-
Follow IS 1200 for standard units:
-
m, m², m³ for length, area, volume.
-
kg, quintal, tonne for weight.
-
no., each for countable items (doors, windows).
-
running meter (rm) for pipes, wires.
-
Preparation of Rate Analysis: Example for Lime Concrete (1:2:6 with brick ballast) Assume 1 m³ of lime concrete in foundation.
| Item | Quantity | Unit | Rate (Rs.) | Amount (Rs.) |
|---|---|---|---|---|
| Materials: | ||||
| Lime | 0.25 m³ | m³ | 2500 | 625 |
| Surkhi | 0.50 m³ | m³ | 1200 | 600 |
| Brick Ballast (40mm) | 0.75 m³ | m³ | 900 | 675 |
| Labor: | ||||
| Mason (1st class) | 0.8 | no. | 600 | 480 |
| Mason (2nd class) | 1.2 | no |