CE-503-C Quantity Surveying and Costing - Nov 2023 Question Paper

Under each question, How to answer lists the points an answer should cover, outlined by CampusPrep from the syllabus. Check the details against your textbook.

  1. 7 Marks
    aWhat are the various factors affecting the rate analysis?
    How to answer
    • Define rate analysis and its purpose
    • List factors: materials cost, labour cost, location, specifications, quantities, overhead, profit
    • Explain influence of each factor briefly
  2. 7 Marks
    bWhat is the principle of units for various items of works in estimation?
    How to answer
    • State principle of units for measurement
    • Explain unit per item type: length, area, volume, number, weight
    • Give examples for various works
  3. 7 Marks
    aDifferentiate between revised and supplementary estimate.
    How to answer
    • Define revised estimate
    • Define supplementary estimate
    • Compare purpose, timing, contents in table
  4. 7 Marks
    bExplain the procedure for the preparation of a Detailed Estimate.
    How to answer
    • Define detailed estimate
    • List steps: drawings, specifications, quantities, rates, abstract
    • Explain sequence of preparation
  5. 7 Marks
    aPrepare the rate analysis for lime concrete in foundation with 40 mm down brick ballast, lime and surkhi proportional 1:2:6.
    How to answer
    • State proportion 1:2:6 lime:surkhi:brick ballast
    • Assume data for 1 cu m and lead rates
    • Calculate material quantities, labour, total rate per cu m
  6. 7 Marks
    bWrite explanatory note on Schedule of rates?
    How to answer
    • Define schedule of rates
    • Explain purpose and types
    • Explain use in estimates and contracts
  7. 7 Marks
    aExplain mid-sectional area method of calculating the quantity of earthwork for road estimating.
    How to answer
    • Define mid-sectional area method formula
    • Explain mean cross-section x length
    • Explain application to road earthwork
  8. 7 Marks
    bEstimate the quantities of brickwork and plastering required in a wall 4 m long, 3 m high and 30 cm thick. Calculate also the cost if the rate of brickwork is Rs. 320 per cu. m and of plastering is Rs. 8.50 per sq m.
    How to answer
    • Calculate volume of brickwork: 4m x 3m x 0.30m
    • Calculate plastering area
    • Apply rates Rs. 320 per cu m and Rs. 8.50 per sq m for cost
  9. 14 Marks
    Fig. shows the plan and cross-section for a wall 5 metre in length. Prepare quantity estimate for the following items-
    1. i)Earthwork in excavation in foundation
    2. ii)Lime concrete in foundation
    3. iii)1st class brickwork (1:4) in foundation and plinth
    4. iv)1st class brickwork (1:6) in superstructure wall
    5. v)2.5 cm thick DPC (1:2:4) with water proofing compound
    Cross-section of wall footing: lime concrete 70 cm wide x 20 cm thick at bottom; 1st footing 50 cm wide x 20 cm high; 2nd footing 40 cm wide x 20 cm high; plinth wall 30 cm wide; superstructure wall 20 cm wide with 2.5 cm DPC at plinth level; vertical dimensions for plinth height and superstructure height up to roof/floor level (approx 3.5 m). Plan below shows 5.0 m long wall strip with outside of wall and plinth offset marks.
    How to answer
    • Take length 5.0 m from plan, widths from cross-section
    • Compute earthwork, lime concrete, brickwork, DPC quantities
    • Present in measurement sheet form
  10. 14 Marks
    Explain the following terms-
    1. i)Overhead charges
    2. ii)Work charge establishment
    3. iii)DPR and its preparation
    How to answer
    • Define overhead charges with examples
    • Define work charge establishment
    • Define DPR and steps of preparation
  11. 7 Marks
    aWhat is Year's Purchase (Y.P.)? Work out the value of year's purchase for an old building if its future life is 15 years and the rate of interest is 7% on capital and 4% for sinking fund.
    How to answer
    • Define Year's Purchase (Y.P.)
    • State dual rate formula with 7% and 4%
    • Substitute n=15 years to compute Y.P. value
  12. 7 Marks
    bDifferentiate between-
    1. i)Scrap Value and Salvage Value
    2. ii)Market Value and Book Value
    How to answer
    • Define scrap value vs salvage value
    • Define market value vs book value
    • Tabulate differences with examples
  13. 7 Marks
    aDefine Sinking Fund. Explain how it is determined?
    How to answer
    • Define sinking fund
    • Explain purpose for depreciation
    • Explain determination with formula and example
  14. 7 Marks
    bDifferentiate between Value, Cost and Price. What is Valuation? What is the function of a Valuer?
    How to answer
    • Differentiate Value, Cost and Price
    • Define valuation
    • Explain functions/duties of a valuer