Quantity surveying & Costing (CE-503 (C)) - Important Questions

  1. 7 Marks High Priority Asked: 2025, 2024

    Explain the purpose, importance and principles of estimating and the general rules for measurement of items of work.

    Appeared 3x (2025, 2024)

  2. 7 Marks High Priority Asked: 2025

    Prepare rough estimate by cubical content method for G+2 commercial complex with plinth area $500\, \text{m}^2$/floor, storey height $3.5\text{m}$, and percentage additions for water supply, electrification, rate fluctuation, contractor profit and contingencies.

    Appeared 2x (2025)

  3. 8 Marks High Priority Asked: 2025, 2024

    Explain the long wall and short wall method of estimating a building with example.

    Appeared 2x (2025, 2024)

  4. 6 Marks High Priority Asked: 2025, 2024

    Explain the different types of approximate / rough estimates such as plinth area rate, cubical content rate, preliminary, original, revised and supplementary estimates with example.

    Appeared 2x (2025, 2024)

  5. 7 Marks High Priority Asked: 2025, 2023

    Explain / differentiate between revised estimate and supplementary estimate with suitable example.

    Appeared 2x (2025, 2023)

  6. 7 Marks Medium Priority Asked: 2025

    Explain the methods of taking out quantities of items of work.

    Appeared 1x (2025)

  7. 7 Marks Medium Priority Asked: 2025

    Explain mode of measurement, measurement sheet and abstract sheet.

    Appeared 1x (2025)

  8. 7 Marks Medium Priority Asked: 2025

    Explain the difference between detailed estimate and abstract estimate.

    Appeared 1x (2025)

  9. 8 Marks Medium Priority Asked: 2024

    Prepare approximate estimate by plinth area rate method for a building with given plinth area, plinth area rate and percentage additions for architectural treatment, electrification, water supply, contingencies and supervision.

    Appeared 1x (2024)

  10. 6 Marks Medium Priority Asked: 2024

    Explain the rules for deductions in masonry and plastering work.

    Appeared 1x (2024)

  11. 7 Marks Low Priority Asked: 2023

    Explain the principle of units for various items of work in estimation.

    Appeared 1x (2023)

  12. 7 Marks High Priority Asked: 2025, 2023

    Explain the Current Schedule of Rates (CSR) and its importance.

    Appeared 3x (2025, 2023)

  13. 8 Marks High Priority Asked: 2025, 2024

    Calculate the quantities of cement, sand and aggregate required for R.C.C. concrete work.

    Appeared 2x (2025, 2024)

  14. 6 Marks High Priority Asked: 2025, 2024

    What is rate analysis? Explain the various factors affecting the rate of an item of work.

    Appeared 2x (2025, 2024)

  15. 7 Marks Medium Priority Asked: 2025

    Explain what is meant by task for an average artisan and its significance.

    Appeared 1x (2025)

  16. 6 Marks Medium Priority Asked: 2024

    Define task work and state the factors affecting task work.

    Appeared 1x (2024)

  17. 7 Marks Low Priority Asked: 2023

    Explain the various factors affecting rate analysis.

    Appeared 1x (2023)

  18. 7 Marks Low Priority Asked: 2023

    Prepare the rate analysis for lime concrete in foundation with 40 mm down brick ballast, lime and surkhi in proportion 1:2:6.

    Appeared 1x (2023)

  19. 7 Marks High Priority Asked: 2025

    Explain in detail the cost estimation for building services such as drainage and electrification, including water supply.

    Appeared 2x (2025)

  20. 7 Marks High Priority Asked: 2025, 2023

    Explain the procedure for the preparation of a detailed estimate

    Appeared 2x (2025, 2023)

  21. 7 Marks Medium Priority Asked: 2025

    Discuss the factors to be considered during preparation of a detailed estimate

    Appeared 1x (2025)

  22. 7 Marks Medium Priority Asked: 2025

    Explain earthwork calculations for roads and estimation of R.C.C. works.

    Appeared 1x (2025)

  23. 7 Marks Medium Priority Asked: 2025

    Explain the method of estimating culverts.

    Appeared 1x (2025)

  24. 7 Marks Medium Priority Asked: 2025

    Find the volume of earthwork in an embankment of given length, top width, depth and side slopes.

    Appeared 1x (2025)

  25. 8 Marks Medium Priority Asked: 2024

    Calculate earthwork quantity for a road in embankment and cutting using the mean sectional area method from formation levels and gradients.

    Appeared 1x (2024)

  26. 6 Marks Medium Priority Asked: 2024

    Explain the data required for preparation of detailed estimate

    Appeared 1x (2024)

  27. 14 Marks Low Priority Asked: 2023

    Prepare quantity estimate for earthwork, lime concrete, brickwork and DPC for a 5 m long wall from plan and cross-section

    Appeared 1x (2023)

  28. 7 Marks Low Priority Asked: 2023

    Explain the mid-sectional area method for calculating earthwork quantity in road estimation.

    Appeared 1x (2023)

  29. 7 Marks Low Priority Asked: 2023

    Estimate quantities of brickwork and plastering for a 4 m long, 3 m high, 30 cm thick wall and calculate cost

    Appeared 1x (2023)

  30. 9 Marks High Priority Asked: 2025, 2024, 2023

    Explain overhead charges / overhead cost, expenses included therein, work charge establishment (and contingencies, DPR)

    Appeared 3x (2025, 2024, 2023)

  31. 7 Marks High Priority Asked: 2025

    Explain factors affecting cost of works, key construction stages and approximate cost percentages

    Appeared 2x (2025)

  32. 8 Marks Medium Priority Asked: 2024

    What is DPR? Discuss the content of DPR in detail.

    Appeared 1x (2024)

  33. 8 Marks High Priority Asked: 2025, 2024

    Explain the different methods of valuation of buildings and purpose of valuation.

    Appeared 2x (2025, 2024)

  34. 6 Marks High Priority Asked: 2024, 2023

    Define/explain sinking fund, including how it is determined and its importance

    Appeared 2x (2024, 2023)

  35. 14 Marks Medium Priority Asked: 2025

    Write short notes on overhead charges, sinking fund and dual rate interest

    Appeared 1x (2025)

  36. 7 Marks Medium Priority Asked: 2025

    Explain the method of fixation of standard rent of a building.

    Appeared 1x (2025)

  37. 7 Marks Medium Priority Asked: 2025

    Explain purpose of valuation and define depreciation, sinking fund and scrap value

    Appeared 1x (2025)

  38. 7 Marks Medium Priority Asked: 2025

    Explain the methods of valuation and rent fixation of buildings.

    Appeared 1x (2025)

  39. 7 Marks Low Priority Asked: 2023

    Define Year's Purchase and calculate it for a building with given life and dual interest rates

    Appeared 1x (2023)

  40. 7 Marks Low Priority Asked: 2023

    Differentiate between scrap value vs salvage value and market value vs book value

    Appeared 1x (2023)

  41. 7 Marks Low Priority Asked: 2023

    Differentiate between Value, Cost and Price; define Valuation and function of a Valuer.

    Appeared 1x (2023)

  42. 7 Marks Medium Priority Asked: 2025

    Explain the different methods and techniques used in culvert construction.

    Appeared 1x (2025)

  43. 14 Marks Medium Priority Asked: 2024

    Write short notes on (any four)

    Appeared 1x (2024)