ME-702 (C) · Power Plant Engineering/Important Questions

Power Plant Engineering (ME-702 (C)) - Important Questions

  1. 7 Marks High Priority Asked: 2025, 2024, 2020

    Explain the classification of energy sources/resources for power generation, including primary and secondary sources, their availability/longevity and interconvertibility.

    Appeared 4x (2025, 2024, 2020)

  2. 7 Marks High Priority Asked: 2025, 2024

    Explain how wind energy is converted to electrical energy, including windmill components and turbine operation.

    Appeared 2x (2025, 2024)

  3. 14 Marks Medium Priority Asked: 2025

    Explain the various processes of biomass energy conversion to useful energy.

    Appeared 1x (2025)

  4. 14 Marks Medium Priority Asked: 2025

    Write short notes on any three of: MHD converter, thermal plant draught system, nuclear power in Indian context, estimation of maximum load, interconnected system.

    Appeared 1x (2025)

  5. 7 Marks Medium Priority Asked: 2025

    Explain the working of an MHD converter with a sketch and discuss factors limiting its commercial use.

    Appeared 1x (2025)

  6. 7 Marks Medium Priority Asked: 2025

    Compare solar energy and wind energy for Indian conditions, stating advantages of solar energy and limitations of both systems.

    Appeared 1x (2025)

  7. 7 Marks Low Priority Asked: 2023

    Classify direct methods of converting various energy sources to electric power and explain two methods in detail.

    Appeared 1x (2023)

  8. 7 Marks Low Priority Asked: 2023

    Explain the factors on which solar intensity and wind velocity depend, with data for various locations in India.

    Appeared 1x (2023)

  9. 7 Marks Low Priority Asked: 2023

    Explain what hybrid energy systems are and discuss possible and feasible options in India.

    Appeared 1x (2023)

  10. 7 Marks Low Priority Asked: 2023

    Define a fuel cell and explain the working principle of one type with thermodynamic equations.

    Appeared 1x (2023)

  11. 7 Marks High Priority Asked: 2025, 2024

    Explain the use and working principle of forced draft and induced draft cooling towers with neat sketches.

    Appeared 2x (2025, 2024)

  12. 7 Marks High Priority Asked: 2025, 2023

    Explain the elements and working of a feed water treatment plant for a thermal power station.

    Appeared 2x (2025, 2023)

  13. 7 Marks Medium Priority Asked: 2025, 2020

    Explain the elements of coal handling system in a thermal power plant with neat sketch / block diagram

    Appeared 2x (2025, 2020)

  14. 7 Marks Medium Priority Asked: 2025, 2020

    Explain fluidized bed combustion (FBC) system with sketch and its advantages

    Appeared 2x (2025, 2020)

  15. 7 Marks Medium Priority Asked: 2025

    What are the factors to be considered for selecting a site for thermal power plant.

    Appeared 1x (2025)

  16. 7 Marks Medium Priority Asked: 2025

    Draw and explain layout of ash handling system

    Appeared 1x (2025)

  17. 7 Marks Medium Priority Asked: 2024, 2020

    Draw a general layout of a steam power plant with a neat diagram and explain the working of the different circuits.

    Appeared 2x (2024, 2020)

  18. 7 Marks Medium Priority Asked: 2024, 2020

    Define boiler mountings and accessories.

    Appeared 2x (2024, 2020)

  19. 7 Marks Medium Priority Asked: 2024

    Explain the purpose of feed water heating in a steam power plant and describe the working of a contact type feed water heater with a neat diagram.

    Appeared 1x (2024)

  20. 7 Marks Low Priority Asked: 2023

    Discuss recent trends in Boiler size, selection and operations for a steam power plant.

    Appeared 1x (2023)

  21. 7 Marks Low Priority Asked: 2023

    What do you mean by plant heat balance? Discuss with example for the case of fossil fuel power plant.

    Appeared 1x (2023)

  22. 7 Marks Low Priority Asked: 2023

    Write short technical note on fuel burning systems in fossil fuel power stations

    Appeared 1x (2023)

  23. 7 Marks High Priority Asked: 2025

    Explain the functions of moderators in nuclear reactors and describe commonly used moderator materials with their properties and characteristics

    Appeared 2x (2025)

  24. 7 Marks Medium Priority Asked: 2025

    Explain the working of a pressurized heavy water reactor (PHWR) with a neat sketch.

    Appeared 1x (2025)

  25. 7 Marks Medium Priority Asked: 2025

    Differentiate between nuclear fission and nuclear fusion reactions with examples.

    Appeared 1x (2025)

  26. 7 Marks Medium Priority Asked: 2025

    Describe an advanced gas-cooled nuclear reactor and discuss nuclear fission in this context.

    Appeared 1x (2025)

  27. 7 Marks Medium Priority Asked: 2024, 2020

    Explain chain reaction, its maintenance, and difference between controlled and uncontrolled chain reactions with sketches and examples.

    Appeared 2x (2024, 2020)

  28. 7 Marks Medium Priority Asked: 2024

    What do you mean by 'Binding Energy'? What are the total binding energy and binding energy per nucleon for the $_6C^{12}$ nucleus?

    Appeared 1x (2024)

  29. 7 Marks Medium Priority Asked: 2024

    Describe with a neat sketch the construction and working of a Pressurized Water Reactor (PWR) nuclear power plant, along with its advantages and disadvantages.

    Appeared 1x (2024)

  30. 7 Marks Medium Priority Asked: 2024

    Describe a breeder reactor with a suitable diagram and discuss its advantages and disadvantages.

    Appeared 1x (2024)

  31. 7 Marks Low Priority Asked: 2023

    Compare thermal reactors and fast breeder reactors.

    Appeared 1x (2023)

  32. 7 Marks Low Priority Asked: 2023

    Discuss the reliability features of a nuclear power plant.

    Appeared 1x (2023)

  33. 7 Marks High Priority Asked: 2025, 2024

    Explain the function and classification/types of hydraulic turbines with characteristics, and the factors/criteria for selecting a turbine for a hydel power plant.

    Appeared 2x (2025, 2024)

  34. 7 Marks High Priority Asked: 2025, 2023

    Compare Micro and Pico hydro machines.

    Appeared 2x (2025, 2023)

  35. 14 Marks Medium Priority Asked: 2025

    Explain the following terms related with hydro power station.

    Appeared 1x (2025)

  36. 7 Marks Medium Priority Asked: 2025

    Discuss the parameters / criteria on which the selection of site for a hydraulic (hydro) power plant depends.

    Appeared 1x (2025)

  37. 7 Marks Medium Priority Asked: 2024

    Draw and explain the hydrologic cycle.

    Appeared 1x (2024)

  38. 7 Marks Medium Priority Asked: 2024

    Explain the construction of flow duration curve and its importance in comparing power potential of different storages for power generation.

    Appeared 1x (2024)

  39. 7 Marks Medium Priority Asked: 2024

    Discuss briefly on the essential elements of hydro power plant.

    Appeared 1x (2024)

  40. 7 Marks Low Priority Asked: 2023

    Discuss site selection criteria for hydro power stations and compare fossil fuel power plant, hydro power plant and renewable energy power plants.

    Appeared 1x (2023)

  41. 7 Marks High Priority Asked: 2025, 2023, 2020

    Define maximum demand, load factor, diversity factor and plant factor related to power plant economics.

    Appeared 4x (2025, 2023, 2020)

  42. 14 Marks Medium Priority Asked: 2025

    Write short notes on diversity factor and load factor, fuel cells, firing principles, spillways.

    Appeared 1x (2025)

  43. 7 Marks Medium Priority Asked: 2025

    Compare hydro and nuclear power.

    Appeared 1x (2025)

  44. 7 Marks Medium Priority Asked: 2025

    Calculate maximum demand on station and annual energy supplied given individual peak loads, diversity factor and annual load factor.

    Appeared 1x (2025)

  45. 7 Marks Medium Priority Asked: 2024, 2020

    Write an explanatory note on the economics of power generation.

    Appeared 2x (2024, 2020)

  46. 7 Marks Medium Priority Asked: 2024

    Explain load factor and diversity factor and prove that load factor is improved by increase in diversity of load.

    Appeared 1x (2024)

  47. 7 Marks Low Priority Asked: 2023

    A power plant costs Rs. 90,000 and has a useful life of 15 years. If the salvage value is 5,000 determine the amount which should be saved annually for both methods: sinking fund method and straight line method. Assume 6% rate of interest.

    Appeared 1x (2023)

  48. 7 Marks Medium Priority Asked: 2025

    How "reheating" improves the thermal efficiency of a simple open cycle gas turbine plant? Explain.

    Appeared 1x (2025)

  49. 14 Marks Low Priority Asked: 2023

    Write short notes on following (any two)

    Appeared 1x (2023)