1.0 FUNDAMENTALS OF ESTIMATION & COSTING
1.1 Purpose and Importance of Estimation in Quantity Surveying
-
Purpose: To determine the probable cost of a project before construction begins. It is the foundation for financial planning, budgeting, and securing funds.
-
Importance:
-
Decision Making: Helps in deciding project feasibility, choosing alternatives, and finalizing designs.
-
Budget Control: Provides a benchmark for controlling expenditure during execution.
-
Tender & Contract: Forms the basis for inviting tenders and entering into contracts.
-
Resource Planning: Aids in planning for materials, labour, and equipment.
-
1.2 Principles of Units for Various Items of Work
Standard units ensure uniformity and comparability.
-
Length: metre (m)
-
Area: square metre (m²)
-
Volume: cubic metre (m³)
-
Number: each (no.), pairs, etc.
-
Weight: kilogram (kg), tonne (t)
-
Length for Linear Items: metre (m) – e.g., piping, wiring.
-
Area for Surface Items: m² – e.g., plastering, painting, flooring.
-
Volume for Volumetric Items: m³ – e.g., earthwork, concrete, brickwork.
-
Conversion: 1 cum = 1000 litres; 1 sqm = 10.76 sq ft; 1 cum = 35.315 cu ft.
1.3 Types of Estimates
| Type of Estimate | Purpose/Use | Accuracy | Preparation Time |
|---|---|---|---|
| 1.3.1 Rough / Preliminary / Approximate Estimate | Initial feasibility, concept approval. | ±10-20% | Very short |
| * Plinth Area Method | Cost = Plinth Area × Plinth Area Rate | Low | |
| * Cubic Content Method | Cost = Cubic Content × Cubic Rate | Low | |
| * Service Unit Method | Cost per unit (e.g., per bed, per student). | Low | |
| 1.3.2 Detailed / Item-wise Estimate | Final cost for tender, contract, and execution control. | ±5% | Long |
| Prepared from detailed drawings, includes all item quantities and rates. | |||
| 1.3.3 Revised Estimate | Prepared when original estimate is exceeded by >5% due to changes in scope, design, or material rates. | Detailed | |
| 1.3.4 Supplementary Estimate | Prepared for additional/new work not in original estimate, after work commencement. | Detailed | |
| 1.3.5 Detailed Project Report (DPR) | Comprehensive document for project approval and financing. Includes: technical, financial, economic, and implementation details. |
1.4 Difference Between
| Aspect | Detailed Estimate | Abstract Estimate / Sheet |
|---|---|---|
| Definition | Item-wise calculation of quantities from drawings. | Summary sheet showing quantities, rates, and amounts from detailed estimate. |
| Purpose | Basis for calculating cost. | Quick reference for total cost; part of tender document. |
| Content | Detailed measurement, calculations, dimensions. | Item No., Description, Quantity, Rate, Amount. |
| B. Revised Estimate vs. Supplementary Estimate | ||
| Revised Estimate | Original estimate becomes insufficient due to major changes/price escalation. Prepared before work starts or early stage. | Supplementary Estimate |
| C. Value, Cost, and Price | ||
| Cost | Actual expenditure incurred (materials, labour, etc.). | Price |
| Value | Worth/utility of an asset (Market, Book, Salvage). |
[!TIP] Exam Focus: Distinguishing Revised vs. Supplementary is a very high-frequency question. Revised is for changes in original scope, Supplementary is for additional work.
2.0 PREPARATION OF ESTIMATES
2.1 Data Required for Preparation of Detailed Estimate
-
Detailed working drawings (plan, elevation, sections).
-
Specifications for all items of work (material quality, workmanship).
-
Standard Schedule of Rates (SSR/CSOR) for rates.
-
Information on site conditions, accessibility, water, power.
-
Information on local availability of materials and labour rates.
2.2 Procedure for Preparation of Detailed Estimate (Step-by-Step)
-
Study Drawings & Specs: Understand the project fully.
-
Take-off Quantities: Measure items from drawings using standard methods (e.g., long wall-short wall).
-
Abstract Sheet Preparation: Enter item-wise quantities in a tabular form.
-
Rate Analysis: Determine unit rates for each item (from schedule or own analysis).
-
Calculate Amount: Multiply quantity by rate for each item.
-
Add Ancillary Costs: Include water supply, electrification, contingencies, etc. as % of structured cost.
-
Add Contractor's Profit & Taxes.
-
Prepare Summary: Total all amounts to get the project cost.
2.3 Factors to be Considered During Preparation
-
Accuracy of Measurements: Avoid errors in dimensions.
-
Specification Adherence: Rates must match specified material/grade.
-
Wastage & Overheads: Include in rates (not separately in estimate).
-
Site Conditions: Difficult terrain may increase cost.
-
Phasing & Logistics: Storage, access, sequencing.
-
Legal & Statutory Requirements: Bylaws, permits.
2.4 Preparation of Approximate/Rough Estimate
Example: Plinth Area Method
Given: Plinth Area = 500 m²/floor, No. of storeys = G+2 (3 floors), Plinth Area Rate = Rs. 3500/m².
Total Plinth Area = 500 m² × 3 = 1500 m².
Structured Cost = 1500 m² × Rs. 3500/m² = Rs. 52,50,000.
Example: Cubic Content Method (from past paper)
Given: Plinth Area = 500 m²/floor, Height/storey = 3.5 m, No. of storeys = G+2 (3 floors), Cubic Rate = Rs. 1000/m³.
Total Cubic Content = Plinth Area × Total Height = 500 m² × (3.5 m × 3) = 500 × 10.5 = 5250 m³.
Structured Cost = 5250 m³ × Rs. 1000/m³ = Rs. 52,50,000.
Inclusion of Ancillary Costs (as % of Structured Cost):
-
Water Supply & Sanitary: 8%
-
Electrification: 6%
-
Fluctuation of Rates: 5%
-
Contractor's Profit: 10%
-
Petty Supervision & Contingencies: 3% Total Ancillary % = 32% Total Project Cost = Structured Cost × (1 + 0.32) = Rs. 52,50,000 × 1.32 = Rs. 69,30,000.
2.5 Bill of Quantities (BOQ) and Abstract Sheet
-
BOQ: A list of all items of work (with descriptions, units, quantities, rates) required for construction. It forms the tender document.
-
Abstract Sheet: A summary sheet derived from the detailed measurement book. It groups similar items, shows total quantities, unit rates, and total amounts. It is the financial heart of the detailed estimate.
[!TIP] Exam Focus: Be prepared to prepare a rough estimate using Plinth Area or Cubic Content method and add ancillary costs – a repeated numerical.
3.0 QUANTITY TAKE-OFF METHODS & TECHNIQUES
3.1 For Buildings: Long Wall and Short Wall Method
-
Theory: For a room/building with parallel walls, the long wall length decreases, and short wall length increases as we go from foundation to superstructure.
-
Formulas:
-
Long Wall Length (at a level) = (Centre to Centre length of room) + (½ × Thickness of wall on both sides)
-
Short Wall Length (at a level) = (Centre to Centre length of room) – (½ × Thickness of wall on both sides)
-
-
Procedure:
-
Find centre line lengths from plan.
-
Calculate long/short wall lengths for each level (foundation, plinth, superstructure).
-
Multiply by respective breadth (thickness) and height to get volume.
-
-
Numerical Example (Simplified):
Room size (c/c): 5m × 4m, Wall thickness: 0.3m.
-
Foundation (1st footing): Long wall = 5 + 0.3 = 5.3m; Short wall = 4 - 0.3 = 3.7m.
-
Plinth (above footing): Long wall = 5 + 0.15 = 5.15m; Short wall = 4 - 0.15 = 3.85m.
-
Superstructure: Long wall = 5.15m; Short wall = 3.85m.
-
Volume of brickwork (plinth level):
Long walls: 2 × 5.15m × 0.3m × Plinth Height
Short walls: 2 × 3.85m × 0.3m × Plinth Height
-
3.1.2 Centre Line Method (Brief)
-
Total centre line length of all walls is multiplied by breadth and height.
-
Suitable for: Rectangular buildings without cross walls.
-
Adjustment: For junctions of cross walls, subtract ½ breadth for each junction.
3.1.3 Deduction Rules in Masonry and Plastering
-
For Openings (Doors, Windows, Vents):
-
Masonry: Full deduction of volume of opening.
-
Plastering/Painting: Deduct only once for area of opening (no deduction for sides of opening).
-
-
For Lintels/Beams: Deduct volume of lintel/beam from masonry above it.
-
For Pilasters/Buttresses: Add extra length/area as they are projections.
-
For R.C.C. Work: Deduct full volume of R.C.C. members from masonry.
3.2 For Earthwork (Roads, Embankments)
3.2.1 Mid-Sectional Area Method
-
Volume = Area of mid-section × Distance between sections.
-
Area of mid-section (Aₘ) = (B + md) × d, where B = formation width, m = side slope (horizontal:vertical), d = mean depth.
-
Best for: Uniform cross-section over short lengths.
3.2.2 Mean Sectional Area Method
-
Volume = \frac{(A₁ + A₂)}{2} × L, where A₁, A₂ = cross-sectional areas at two chainages, L = distance between them.
-
More accurate for varying ground levels.
3.2.3 Calculation of Volume (Trapezoidal/Pyramidoidal Formula)
- Trapezoidal Formula (for prismoidal shape):
$$V = \frac{L}{6} \left( A_1 + 4A_m + A_2 \right)$$
where Aₘ = area of mid-section.
- Pyramidoidal Formula (for wedge/triangular shape):
$$V = \frac{L}{6} \left( A_1 + A_2 \right)$$
- General Rule: Use Prismoidal Formula for accuracy when area changes linearly.
[!TIP] Exam Focus: Earthwork volume calculation using Mean Sectional Area or Prismoidal Formula is a guaranteed numerical. Always draw cross-sections, calculate areas correctly (including side slopes), then apply formula.
3.3 For Specific Construction Items
-
3.3.1 Earthwork in Excavation for Foundations: Measure net volume (length × breadth × depth) from drawing levels. Include offset for working space if needed.
-
3.3.2 Lime Concrete in Foundation: Volume = area of foundation bed × thickness.
-
3.3.3 Brickwork: Calculate volume separately for foundation, plinth, superstructure. Use long wall-short wall method. Note mortar ratio (1:4, 1:6) affects rate, not quantity.
-
3.3.4 Damp Proof Course (DPC): Measured in square metres (m²). Deduct openings. Thickness (usually 2.5 cm) is considered in rate analysis, not quantity.
-
3.3.5 Plastering: Measured in m². Deduct openings (doors, windows) once. No deduction for reveals/jambs. Ceiling plastering measured separately.
3.4 Material Statement Preparation
3.4.1 For R.C.C. Work (M20 Grade 1:2:4)
-
Step 1: Total volume of concrete (say, 25 m³).
-
Step 2: Total dry volume of ingredients = 25 m³ × 1.54 (wastage factor) = 38.5 m³.
-
Step 3: Sum of ratio = 1+2+4 = 7.
-
Step 4: Quantity of Cement = \frac{1}{7} × 38.5 = 5.5 m³.
- No. of cement bags = \frac{5.5 × 1440}{50} = 158.4 bags (approx 159 bags).
-
Step 5: Quantity of Sand = \frac{2}{7} × 38.5 = 11 m³.
-
Step 6: Quantity of Aggregate = \frac{4}{7} × 38.5 = 22 m³.
-
Material Statement Table:
| Material | Ratio | Volume (m³) | Bags/Units | | :--- | :--- | :--- | :--- | | Cement | 1 | 5.5 | 159 bags | | Sand | 2 | 11.0 | - | | Aggregate | 4 | 22.0 | - |
3.4.2 General Principles: Identify total volume of concrete/mortar, apply mix ratio, convert to weight/numbers using densities (Cement=1440 kg/m³, 1 bag=50 kg).
[!TIP] Exam Focus: Material statement for RCC (e.g., M20 1:2:4) is a very common 7-mark question. Remember the 1.54 factor for dry volume and conversion to bags.
4.0 RATE ANALYSIS & COST COMPONENTS
4.1 Definition and Objective of Rate Analysis
-
Definition: The process of determining the rate per unit of an item of work by breaking down its cost components.
-
Objective: To arrive at a realistic, economic, and fair unit rate for billing and payment. It helps in cost control and preparing detailed estimates.
4.2 Factors Affecting Rate Analysis
| Component | Factors Included |
|---|---|
| 4.2.1 Material Costs | Cost of material at source + transportation + loading/unloading + taxes + wastage (2-5%). |
| 4.2.2 Labour Costs | Skilled/unskilled wages, overtime, allowances, productivity (output per day). |
| 4.2.3 Equipment/Machinery | Hire charges, fuel, maintenance, operator charges. |
| 4.2.4 Overhead Charges | Site Overhead: Site office, staff, utilities, security. Head Office Overhead: Admin, management, corporate costs (usually 5-10% of total cost). |
| 4.2.5 Contractor’s Profit | Risk reward, typically 5-10% of total cost. |
| 4.2.6 Taxes & Duties | GST, cess, etc. (now subsumed mostly in GST). |
| Fluctuation of Rates: Clause for adjusting material/labour rates during contract period. |
4.3 Preparation of Rate Analysis for a Specific Item (e.g., Lime Concrete 1:2:6)
-
Material Quantities: For 1 m³ of lime concrete (1:2:6).
-
Dry volume = 1 m³ × 1.54 = 1.54 m³.
-
Lime = \frac{1}{1+2+6} × 1.54 = 0.154 m³ (or bags if bagged).
-
Surkhi/Brick Aggregate = \frac{2}{9} × 1.54 = 0.342 m³.
-
Brick Ballast 40mm = \frac{6}{9} × 1.54 = 1.027 m³.
-
-
Cost of Materials: Calculate cost for each material at site.
-
Cost of Labour: Mason, helper, etc. for 1 m³.
-
Cost of Equipment: Mixer, compactor, etc.
-
Sum of (2+3+4) = Direct Cost.
-
Add Overhead Charges (e.g., 5% of Direct Cost).
-
Add Contractor's Profit (e.g., 10% of (Direct Cost + Overhead)).
-
Total Rate per m³ = Direct Cost + Overhead + Profit.
4.4 Concept of Task Work (Definition & Factors)
-
Definition: The amount of work (output) a skilled worker can complete in a standard day (8 hours) under normal conditions.
-
Factors Affecting Task Work:
-
Skill and efficiency of labour.
-
Type and quality of materials.
-
Type of equipment/tools used.
-
Work environment (weather, site conditions).
-
Supervision and method of work.
-
Specifications and finish required.
-
4.5 Cost Percentages in Building Construction (Typical Distribution)
| Stage/Item | Approx. % of Total Cost | Remarks |
|---|---|---|
| Structure (Substructure & Superstructure) | 60-70% | Largest component. Includes masonry, R.C.C., etc. |
| Water Supply & Sanitary | 4-8% | Pipes, fittings, fixtures. |
| Electrification | 5-8% | Wiring, switches, fixtures, DBs. |
| Finishes (Flooring, Plaster, Paint) | 10-15% | Varies with specification. |
| Contingencies | 2-5% | For unforeseen items. |
| Petty Supervision & Site Expenses | 2-3% | |
| Contractor's Profit | 5-10% | |
| Architect/Engineer Fees | 1-3% | |
| Land Cost | Variable | Often separate from construction cost. |
[!TIP] Exam Focus: Cost percentages for key stages (structure, WS&S, electrification) are frequently asked. Remember structure is the major chunk (~65%).
5.0 VALUATION PRINCIPLES & METHODS
5.1 Purpose and Functions of Valuation / Role of a Valuer
-
Purpose: To determine the market value or worth of a property at a given time.
-
Functions of Valuer: Inspect property, collect data, apply valuation methods, prepare report, give expert evidence.
-
Uses: Sale/purchase, mortgage, insurance, taxation, rent fixation, dispute resolution, accounting (depreciation).
5.2 Key Concepts
| Term | Definition |
|---|---|
| Market Value | Price at which a property would sell in open market between willing buyer & seller. |
| Book Value | Value shown in accounts = Original Cost – Accumulated Depreciation. |
| Scrap Value | Value of dismantled materials (very old/obsolete asset). |
| Salvage Value | Value of asset if sold as is (without dismantling). |
| Gross Income | Total annual rental income (potential + actual). |
| Net Income | Gross Income – Outgoings (taxes, repairs, management). |
5.3 Methods of Valuation
-
Direct Comparison Method (Sales Comparison): Compare with recent sales of similar properties. Adjust for differences. Most common for residential plots.
-
Cost Method (Replacement/Reproduction):
-
Value = Present Cost of Construction (Replacement Cost) – Depreciation + Land Value.
-
Used for new/specialized buildings, insurance.
-
-
Income Capitalization Method:
-
Value = \frac{Net Annual Income}{Capitalization Rate (Yield)}.
-
Yield (Y) = \frac{Net Income}{Value} × 100%.
-
Years’ Purchase (Y.P.) = \frac{1}{Y} (see 5.5).
-
5.4 Sinking Fund
-
Definition: A fund accumulated periodically (annually) to accumulate a lump sum equal to the original cost of the asset at the end of its useful life, for replacement.
-
Importance: Ensures funds are available for future replacement without sudden financial burden.
-
Determination:
- Sinking Fund Coefficient (s):
$$s = \frac{i}{(1+i)^n - 1}$$
where `i` = rate of interest (decimal), `n` = useful life (years).
* **Annual Sinking Fund (A.S.F.)** = Original Cost × `s`.
* **Example:** For a building costing Rs. 10,00,000, life 50 years, interest 5%:
$$s = \frac{0.05}{(1.05)^{50} - 1} = 0.00072$$
A.S.F. = 10,00,000 × 0.00072 = Rs. 720/year.
5.5 Years’ Purchase (Y.P.)
-
Concept: The present worth of a property that yields a net income of Re. 1 per year indefinitely, considering interest and sinking fund for replacement.
-
Calculation (Considering Interest
iand Sinking Funds):
$$Y.P. = \frac{1}{i + s}$$
* `i` = rate of interest on capital (e.g., 7% = 0.07).
* `s` = sinking fund coefficient for asset life (from 5.4).
-
Numerical (from past paper):
-
Future life
n= 15 years, Interesti= 7% (0.07), Sinking Fund rate = 4% (0.04). -
First, find
sfor 15 years at 4%:
-
$$s = \frac{0.04}{(1.04)^{15} - 1} = \frac{0.04}{1.8009 - 1} = \frac{0.04}{0.8009} = 0.0499$$
* Then,
$$Y.P. = \frac{1}{0.07 + 0.0499} = \frac{1}{0.1199} = 8.34$$
* \boxed{Y.P. = 8.34}
5.6 Dual Rate of Interest (Concept & Application)
-
Concept: In valuation of old properties, two different interest rates are considered:
-
Higher rate (
i) on the capital invested (for return on investment). -
Lower rate (
s) for the sinking fund (for replacement).
-
-
Application: Used in Years’ Purchase formula: Y.P. = 1/(i + s). Reflects that investor expects higher return on capital but sets aside a smaller sinking fund for an old asset with shorter remaining life.
5.7 Standard Rent Fixation of a Building (Methodology)
-
Find Present Value of Building (V_b): Using Cost Method (Replacement Cost – Depreciation).
-
Find Land Value (V_l): by comparison.
-
Total Property Value (V) = V_b + V_l.
-
Determine Years’ Purchase (Y.P.) based on:
-
Interest rate on capital (e.g., 6-8%).
-
Sinking fund rate for building life.
-
(Land has no sinking fund, so Y.P. for land = 1/i).
-
-
Annual Net Income Required = V × Y.P.
-
Gross Annual Rent = Net Income + Outgoings (taxes, repairs, insurance, management).
-
Standard Monthly Rent = Gross Annual Rent / 12.
[!TIP] Exam Focus: Years’ Purchase calculation with dual rates is a classic numerical. Memorize the formula Y.P. = 1/(i+s). Also, know the difference between scrap and salvage value.
6.0 ADMINISTRATIVE & CONTRACTUAL ASPECTS
6.1 Current Schedule of Rates (CSOR)
-
Purpose & Importance: Standardized document issued by government/agencies (CPWD, PWD). Provides baseline rates for materials, labour, and equipment for estimating, billing, and contract agreements. Ensures uniformity and fairness.
-
Components:
-
Material Rates: At source/despatch point + transportation to site.
-
Labour Rates: Basic wages + allowances + overheads.
-
Equipment Rates: Hire charges, operator, fuel.
-
Item Rates: Composite rates for common items (often derived from above).
-
-
Use: Basis for preparing estimates, analyzing rates, and forming contract agreements. Revised periodically.
6.2 Work Charge Establishment (Definition & Components)
-
Definition: Temporary, on-site facilities and staff required for project execution, whose cost is included in the project estimate.
-
Components:
-
Site office, stores, staff quarters, labour camps.
-
Site water supply, electricity, sanitation.
-
Site vehicles, communication.
-
Field staff (engineer, supervisor, clerk).
-
Not included: Head office overheads (separate %).
-
6.3 Tender Notice – Essential Elements
-
Name and address of employer/consultant.
-
Brief description of work and location.
-
Estimated cost/range.
-
Time for completion.
-
Earnest Money Deposit (EMD).
-
Cost of tender documents.
-
Eligibility criteria for contractors.
-
Date, time, place of tender submission and opening.
-
Security deposit details.
-
Terms of payment.
6.4 Fluctuation of Rates in Contracts (Clauses & Mechanisms)
-
Purpose: To protect contractor/client from sudden price changes in materials/labour during long-duration contracts.
-
Mechanism (Price Variation Clause):
-
Base Date: Prices on date of tender submission are "base".
-
Indices: Use official price indices (e.g., Wholesale Price Index - WPI for materials, Consumer Price Index - CPI for labour).
-
Formula: Adjustable amount = (Current Index / Base Index – 1) × Base Cost × Weightage.
-
Weightage: Pre-determined % for materials, labour, fuel in the contract.
-
Ceiling: Often a maximum % (e.g., 10-15%) beyond which contractor bears risk.
-
7.0 SPECIALIZED ESTIMATION (APPLICATIONS)
7.1 Cost Estimates for Drainage and Electrification Works
-
Methodology:
-
Drainage: Estimate based on length of pipes (sewers, stormwater) + number of manholes/inspection chambers + earthwork for trenches. Rates per metre or per number.
-
Electrification: Estimate based on length of conduiting/wiring (point-to-point) + number of points (switches, sockets, fixtures) + sub-distribution boards + main panel. Often uses percentage method (5-8% of building cost) for preliminary estimates.
-
-
Percentage Method: For quick preliminary estimates, take a % (e.g., 6% for electrification) of the plinth area rate or structured cost.
7.2 Estimation for Culvert Construction (Different Methods & Techniques – Brief)
-
Methods:
-
Detailed Item-wise Estimate: For major culverts (box, pipe, arch). Quantities for excavation, foundation, substructure (abutments, piers), superstructure (deck, wearing coat).
-
Approximate Estimate: For minor pipe culverts, use per metre length or per culvert rates based on standard designs.
-
Unit Rate Method: Rate per square metre of deck area or per cubic metre of concrete.
-
-
Techniques: Similar to building estimates but focus on hydraulic structures. Key items: earthwork, concrete, reinforcement, masonry, scour protection.
7.3 Valuation of Special Structures (e.g., Marine/Port Structures – Contextual Link)
-
Challenges: Limited comparable sales, specialized design, high capital cost, long life, income from dues (berthing, cargo).
-
Approach:
-
Cost Method: Dominant. Calculate Replacement Cost New (RCN) of breakwaters, docks, jetties. Apply physical and functional depreciation (difficult, often low as structures are durable).
-
Income Method: If operational, capitalize net income from port operations (berth fees, cargo handling). Requires accurate financial data.
-
Direct Comparison: Rare, only if similar port sold recently.
-
8.0 SYNTHESIS & APPLICATION
8.1 Inter-relationship between Estimate, Rate Analysis, and Valuation
-
Estimate uses Rate Analysis to determine item rates → gives Project Cost.
-
Valuation (for existing property) may use Cost Method, which requires current replacement cost → derived from updated Rate Analysis.
-
Thus, Rate Analysis is the common link: it feeds into both estimating new work and valuing existing assets.
8.2 Common Errors in Estimation and Their Avoidance
| Error | Consequence | How to Avoid |
|---|---|---|
| Wrong measurement units | Major cost error. | Strictly follow standard units. Double-check. |
| Omitting items (e.g., DPC, lintels) | Underestimation. | Use standard BOQ formats, check specifications. |
| Incorrect deduction rules (plaster, masonry) | Over/under estimation. | Memorize standard deduction rules (e.g., no deduction for plaster reveals). |
| Using outdated rates | Unrealistic estimate. | Use latest CSOR/SSR, adjust for location & time. |
| Ignoring wastage & contingencies | Cash crunch during execution. | Include standard % for wastage (materials) and contingencies (2-5%). |
| Not considering site conditions | Increased cost. | Visit site, note access, terrain, water availability. |
8.3 Role of Quantity Surveyor in Project Planning & Cost Management
-
Pre-Construction: Prepare estimates, BOQ, cost plans, value engineering, tender documentation.
-
During Construction: Cost control, variation assessment, progress billing, claim evaluation, cost reporting.
-
Post-Construction: Final account settlement, depreciation studies, asset valuation.
-
Overall: Cost consultant ensuring project delivered within budget, maximizing value for money.
[!TIP] Final Exam Strategy: For any 7-mark question, structure your answer: Definition → Explanation/Procedure → Example (if numerical) → Key Points. For differences, use a table. Always highlight standard units and common percentages (ancillary costs, overheads). Practice long wall-short wall and earthwork volume numericals thoroughly.