CE-503-B Construction Planning & Management - Dec 2025 Question Paper
Under each question, How to answer lists the points an answer should cover, outlined by CampusPrep from the syllabus. Check the details against your textbook.
-
7 MarksaExplain preliminary and detailed investigation methods in construction projects.
How to answer
- Define preliminary investigation: objectives, desk study, site reconnaissance, feasibility.
- Define detailed investigation: soil exploration, surveys, material, hydrological studies.
- List methods: borings, trial pits, geophysical, lab tests.
- Role in cost, design and planning decisions.
-
7 MarksbExplain different methods of construction, formwork and centering.
How to answer
- Outline construction methods: traditional, reinforced concrete, steel, precast.
- Define formwork: purpose, types - timber, steel, plywood, slip forms.
- Define centering: support for arches, slabs, removal time.
- Requirements: strength, stability, economy, reuse.
-
7 MarksaExplain principles of construction management and job layout.
How to answer
- Define construction management: planning, organizing, directing, controlling.
- Explain principles: economy, quality, time, safety, resource optimization.
- Define job layout: site layout for materials, equipment, labour, access.
- Factors and neat layout diagram for efficiency.
-
7 MarksbA project consists of activities A-B-C with durations 4, 6 and 5 days respectively. Draw the network and find the total project duration.
How to answer
- Draw sequential network with nodes for activities A-B-C.
- Show durations 4, 6, 5 days on arrows.
- Compute total duration as sum for series path.
- Result total project duration = 15 days.
-
7 MarksaExplain factors affecting selection of construction equipment.
How to answer
- List factors: nature and size of work, soil and site conditions.
- Consider cost, availability, transportation, fuel and spares.
- Consider output rate, versatility, labour and climate.
- Explain selection for economy and timely completion.
-
7 MarksbExplain investment cost, operating cost and output of construction equipment.
How to answer
- Define investment cost: purchase, transport, installation, interest, depreciation.
- Define operating cost: fuel, repairs, wages, maintenance, overheads.
- Define output: production per hour/day and factors affecting it.
- Relation for owning and operating cost per unit output.
-
7 MarksaDescribe various construction equipments used for earthwork, concreting, hoisting and compaction.
How to answer
- Earthwork equipment: excavators, dozers, scrapers, dumpers.
- Concreting: mixers, batching plant, vibrators, pumps.
- Hoisting: cranes, hoists, derricks, lifts.
- Compaction: rollers, rammers, vibratory compactors.
-
7 MarksbA concrete mixer produces $8 \, m^3$ of concrete per hour. Calculate the total output in an 8-hour working day.
How to answer
- Given output rate $8 \, m^3/hour$.
- Formula: Total output = rate $\times$ working hours.
- Calculation: $8 \times 8 = 64 \, m^3$.
- State total output per 8-hour day.
-
7 MarksaExplain different types of contracts used in construction works.
How to answer
- Define contract and need in construction.
- Explain types: lump sum, item rate, percentage, cost-plus, labour, BOT.
- Merits, demerits and suitability of each.
- Selection criteria for different works.
-
7 MarksbExplain notice inviting tender, contract documents and security deposit.
How to answer
- Define notice inviting tender: contents and publicity.
- Explain contract documents: agreement, drawings, specs, BOQ, conditions.
- Define security deposit: purpose, earnest money, retention.
- Procedure for refund and forfeiture.
-
7 MarksaExplain importance and types of specifications used in engineering works.
How to answer
- Define specification and its importance for quality and payment.
- Types: general, detailed, standard, special provisions.
- Contents for materials and workmanship.
- Role in estimation and dispute avoidance.
-
7 MarksbExplain various public works accounts such as measurement book, cash book and imprest account.
How to answer
- Define measurement book: recording measurements for billing.
- Define cash book: daily receipts and payments.
- Define imprest account: petty advance to sub-engineer.
- Rules for maintenance and audit.
-
7 MarksaExplain different types of running bills, secured advance and final bill.
How to answer
- Define running bills: interim payments for work done.
- Explain secured advance: advance against materials brought to site.
- Define final bill: settlement on completion.
- Conditions for payment and recovery.
-
7 MarksbIf the total value of work done is ₹8,00,000 and secured advance paid is 75%, calculate the amount of secured advance.
How to answer
- Given work value $\text{₹}8,00,000$ and $75\%$ advance.
- Formula: Secured advance = $0.75 \times$ value of work.
- Calculation: $0.75 \times 8,00,000 = 6,00,000$.
- State amount of secured advance as ₹6,00,000.
-
7 MarksaExplain site organization, welfare facilities and safety engineering in construction projects.
How to answer
- Define site organization: hierarchy, duties, communication.
- Explain welfare facilities: housing, water, medical, sanitation.
- Explain safety engineering: hazards, PPE, training, regulations.
- Importance for productivity and accident prevention.
-
7 MarksbExplain systems approach to planning and applications of assignment, transportation and waiting line models.
How to answer
- Define systems approach to planning: inputs, process, feedback.
- Explain assignment model for optimal job allocation.
- Explain transportation model for cost minimization.
- Explain waiting line (queuing) model for service facilities.