UNIT 3: CONSTRUCTION ESTIMATION, COSTING & VALUATION
1.0 FUNDAMENTALS OF ESTIMATION & COSTING
1.1 Purpose and Importance of Estimation
-
Purpose: To ascertain the probable cost of a proposed construction project before commencement.
-
Importance:
-
Financial Planning: Determines capital requirement, funding needs, and feasibility.
-
Decision Making: Helps choose between alternatives (e.g., materials, methods).
-
Contract Basis: Forms the foundation for tender documents and contract agreements.
-
Control: Provides a benchmark for cost control during execution.
-
Valuation: Essential for property valuation, sale, purchase, and mortgage.
-
1.2 Principle of Units
Standard units for measurement ensure uniformity and comparability.
| Item of Work | Standard Unit |
|---|---|
| Earthwork (Excavation/Filling) | Cubic meter (m³) |
| Brickwork/Stonework | Cubic meter (m³) |
| Plastering/Painting | Square meter (m²) |
| Flooring, Roofing | Square meter (m²) |
| Doors, Windows, etc. | Each (Nr.) or Square meter (m²) |
| Lumpsum Items | Item (L.S.) |
1.3 Types of Estimates
| Type of Estimate | Description | When Used | Accuracy |
|---|---|---|---|
| Rough/Approximate | Based on plinth area, cubic content, or service unit. Quick, no detailed quantities. | Preliminary studies, feasibility reports. | ±10-20% |
| Detailed | Item-by-item quantity take-off from drawings. Includes Abstract & BOQ. | Final sanction, tender, construction. | ±2-5% |
| Revised | Prepared when original estimate is exceeded due to material change in scope (e.g., design alteration, site conditions). Requires fresh sanction. | Major deviations from original plan. | High |
| Supplementary | Prepared for additional/modified work not in original estimate, but within original scope. Requires separate sanction. | Minor additions/alterations. | Moderate |
| Detailed vs Abstract | Detailed Estimate: Item-wise quantities & rates calculated on paper. Abstract: Summarized cost statement from detailed estimate. |
[!TIP] Exam Distinction: Revised Estimate = Material change in scope (fresh sanction). Supplementary Estimate = Additional work within original scope (separate sanction).
1.4 Key Financial & Costing Concepts
-
Overhead Charges (Establishment Charges): Indirect expenses of the project office (site staff salary, office rent, utilities, etc.). Added as a percentage to the total of direct costs.
-
Contingencies: Provision for unforeseen minor items/price fluctuations (typically 2-5%). Not for major scope changes.
-
Contractor's Profit: Added to total cost (direct + overheads) as a percentage (typically 10%).
-
Petty Supervision Charges: Charges for site supervision by owner's engineer (1-2%).
-
Fluctuation of Rates (Escalation): Clause in contract for adjusting material/labour rates due to market inflation beyond a base date.
-
Work Charge Establishment: Temporary facilities at site (sheds, storage, water supply) – part of overheads.
2.0 METHODS OF ESTIMATION & QUANTITY TAKE-OFF
2.1 Building Estimation: Long Wall & Short Wall Method
-
Procedure: For walls with cross walls. Long walls run parallel to the length of the building. Short walls run parallel to the breadth.
-
Formulas:
-
Length of Long Wall = (Center to Center Length of Room) - (2 × Half Width of Wall) + (2 × Length of Wall Beyond Inner Face of Parapet)
-
Length of Short Wall = (Center to Center Breadth of Room) - (2 × Half Width of Wall) + (0.3 m for parapet)
-
-
Example: For a room 5m x 4m with 0.3m thick walls:
-
Long Wall Length = (5 + 0.3) - (2 × 0.15) = 5.0m (at plinth level)
-
Short Wall Length = (4 + 0.3) - (2 × 0.15) = 4.0m (at plinth level)
-
-
Centre Line Method: Faster for rectangular buildings without cross walls. Total center line length × width × height. Not suitable for buildings with internal cross walls.
2.2 Earthwork Estimation for Roads
-
Mid-Sectional Area Method:
-
Volume = Area of Mid-Section × Distance between CS
-
Area of Mid-Section = (B + md) × d (for embankment) where B=top width, m=side slope, d=depth at mid-section.
-
Application: When cross-sections are taken at regular intervals (chainages).
-
-
Mean Sectional Area Method:
-
Volume = (A₁ + A₂) / 2 × L
-
Where A₁, A₂ = areas of two consecutive cross-sections, L = distance between them.
-
Application: When only two end sections are known.
-
2.3 Deduction Rules for Masonry & Plastering
-
No deduction for openings < 0.1 m².
-
For openings ≥ 0.1 m²:
-
Masonry: Deduct full opening area. Add lintel/sill volume (if specified).
-
Plastering/Painting: Deduct only one face of the opening area. For jambs, add perimeter of opening × thickness of plaster.
-
-
For RCC bands, lintels, etc.: Deduct full volume from masonry if they replace masonry.
2.4 Material Statement Preparation
-
For R.C.C. (M20 = 1:1.5:3): For 1 m³ concrete:
-
Cement = $$\displaystyle \frac{1}{1+1.5+3} \times 1.54 $$ (dry volume factor) = 0.272 m³ ≈ 8 bags (since 1 bag = 0.035 m³)
-
Sand = $$\displaystyle \frac{1.5}{5.5} \times 1.54 $$ = 0.42 m³
-
Aggregate = $$\displaystyle \frac{3}{5.5} \times 1.54 $$ = 0.84 m³
-
Water-Cement Ratio = 0.5 → Water = 0.5 × 0.272 × 1000 = 136 liters
-
Note: 1.54 accounts for voids in dry mix. For M15 (1:2:4), adjust ratios.
-
-
For Brickwork (1:6): For 1 m³ brickwork:
-
Bricks = 500 (standard size 19x9x9 cm with mortar)
-
Mortar = 0.3 m³ (approx). Cement = $$\displaystyle \frac{1}{7} \times 0.3 \times 1.54 $$ = 0.066 m³ ≈ 2 bags. Sand = $$\displaystyle \frac{6}{7} \times 0.3 \times 1.54 $$ = 0.396 m³.
-
3.0 PREPARATION OF DETAILED ESTIMATE
3.1 Data Required
-
Drawings: Plan, elevation, section, foundation details.
-
Specifications: Material quality, workmanship standards, mortar/concrete grades.
-
Rates: Current schedule of rates (CSR) or prevailing market rates.
-
Dimensions: All measurements from drawings.
-
Site Conditions: Soil report, access, water availability.
3.2 Step-by-Step Procedure
-
Take-off Quantities: Item-wise measurement from drawings using standard units.
-
Calculate Abstract: Enter quantities and compute cost (Qty × Rate) for each item.
-
Add Miscellaneous: Include contingencies, supervision charges.
-
Add Contractor's Profit: On total (direct + overheads).
-
Prepare Abstract Sheet & BOQ: Summarize all items and costs.
3.3 Factors to Consider
-
Site conditions (soil, terrain, access).
-
Availability of materials and labour.
-
Construction sequence and methodology.
-
Local bylaws and regulations.
-
Seasonal variations (monsoon impact).
-
Waste and wastage percentages.
3.4 Abstract of Estimate & BOQ
-
Abstract Sheet: Summary table showing item no., description, quantity, rate, amount, and total cost.
-
Bill of Quantities (BOQ): Detailed list of all work items with quantities, units, and rates. Forms part of tender document.
3.5 Item-wise Estimation (Foundation to Superstructure)
-
Earthwork in Excavation: Measure net volume (length × breadth × depth). Deduct for plinth.
-
Lime Concrete in Foundation: Measure over plinth area × average thickness (usually 30 cm).
-
Brickwork in Foundation/Plinth: Use long/short wall method for lengths. Deduct for openings if any.
-
Brickwork in Superstructure: Similar to above, up to top of lintel level.
-
Damp Proof Course (DPC): Measured in square meters over plinth area.
-
Plastering: Measured in square meters of surface area. Deduct openings (one face), add jambs.
4.0 RATE ANALYSIS & COST DETERMINATION
4.1 Definition & Objective
-
Definition: Breaking down the cost of an item into its constituents (material, labour, equipment, overheads, profit) to determine a rational rate per unit.
-
Objective: To fix a fair price for the item, understand cost drivers, and prepare accurate estimates.
4.2 Factors Affecting Rate Analysis
| Factor | Considerations |
|---|---|
| Material Costs | Cost of basic material + wastage (5-10%) + transport. |
| Labour Costs | No. of workers, skill level, daily wages, productivity (output/day). |
| Equipment/Tool Costs | Hire charges or depreciation of tools/plants. |
| Overheads & Profit | Site overheads (1-2%), establishment (2-5%), contractor's profit (10%). |
4.3 Procedure for Rate Analysis (Example: 1:4 Brickwork)
-
Calculate Material Cost:
-
Bricks for 1 m³ = 500 nos. @ Rs. X/brick.
-
Mortar (1:4) for 1 m³ = 0.3 m³. Cement = $$\displaystyle \frac{1}{5} \times 0.3 \times 1.54 $$ = 0.0924 m³ (≈ 2.6 bags). Sand = $$\displaystyle \frac{4}{5} \times 0.3 \times 1.54 $$ = 0.37 m³.
-
Total Material Cost = (Bricks + Cement + Sand).
-
-
Calculate Labour Cost: Based on output (e.g., 1 mason + 2 helpers can build 1 m³/day).
-
Add Tools & Tackles: 1-2% of labour cost.
-
Add Overheads: 2-5% of (Material + Labour).
-
Add Profit: 10% of (Material + Labour + Overheads).
-
Total Rate/Unit = Sum of all above.
4.4 Cost Estimates for Specific Services
-
Water Supply & Sanitary: Typically 5-8% of structural cost. Includes pipes, fittings, fixtures, septic tank, soak pit.
-
Electrification: Typically 6-8% of structural cost. Includes wiring, switches, fixtures, distribution boards.
-
Drainage Works: Typically 3-5% of structural cost. Includes external drains, inspection chambers, connections.
5.0 SCHEDULE OF RATES (SOR) & PROJECT REPORTS
5.1 Current Schedule of Rates (CSR)
-
Definition: A document issued by government/public works departments (PWD, CPWD, NHAI) listing standardized rates for various items of work in a specific region/period.
-
Purpose: Provides uniform rates for estimating, tendering, and payment. Prevents disputes.
-
Preparation Authority: PWD (State), CPWD (Central), MES, etc.
-
Components:
-
Material rates (at site/stockyard).
-
Labour rates (skilled, semi-skilled, unskilled).
-
Hire charges for equipment.
-
Standard constants (e.g., output of labour, material consumption per m³).
-
5.2 Detailed Project Report (DPR)
-
Purpose: Comprehensive document for project appraisal, financing, and execution. Required for bank loans, government approval.
-
Contents:
-
Executive Summary: Project snapshot.
-
Technical Feasibility: Location, site details, design parameters, construction methodology.
-
Cost Estimates: Detailed abstract, year-wise phasing, escalation.
-
Financial Analysis: Sources of finance, loan schedule, profitability, IRR, NPV.
-
Implementation Schedule: Bar chart/PERT chart, milestones.
-
Market Analysis: Demand, supply, pricing strategy (for commercial projects).
-
Risk Analysis & Mitigation.
-
6.0 VALUATION PRINCIPLES & METHODS
6.1 Definitions & Differentiation
| Term | Definition |
|---|---|
| Value | Worth of property in open market at a given time. |
| Cost | Actual expenditure incurred in construction/purchase. |
| Price | Amount asked/offered in a transaction (may differ from value). |
| Valuation | Process of estimating the Market Value of a property. |
| Valuer | Professional who performs valuation. Functions: estimate value, prepare reports, expert witness. |
6.2 Purpose of Valuation
- Sale/Purchase, Mortgage/Loan, Insurance, Taxation (property tax, wealth tax), Rent fixation, Compulsory acquisition, Litigation.
6.3 Methods of Valuation
| Method | Principle | Formula / Key |
|---|---|---|
| 1. Rental Method | Value = Capitalized Net Income. Used for income-producing properties. | Value = $$\displaystyle \frac{\text{Net Annual Income}}{\text{Rate of Capitalization}} $$ |
| 2. Direct Comparison | Compare with similar recent transactions in same locality. Adjust for differences. | Value = Adjusted Sale Price of Comparable. |
| 3. Cost Method | Value = Replacement/Reproduction Cost - Depreciation. Used for new/specialized properties. | Value = (Land Value + Cost of Construction) - Depreciation |
| 4. Development Method | Value = Anticipated Sale Value of Developed Property - Total Development Cost. Used for vacant land/development potential. | Residual Value = Sale Value - (Construction Cost + Interest + Profit) |
6.4 Key Valuation Concepts
-
Sinking Fund: Fund accumulated to replace an old asset at end of its life. Importance: Provides capital for renewal without burdening current revenue.
- Calculation: Annual Sinking Fund = $$\displaystyle \frac{C \times i}{(1+i)^n - 1} $$ where C = Replacement Cost, i = interest rate, n = life.
-
Year's Purchase (Y.P.): Multiplier used to capitalize net annual income into capital value.
-
Formula (Dual Rate): Y.P. = $$\displaystyle \frac{1}{i + \frac{1}{S}} $$ where i = interest rate on capital, $$\displaystyle \frac{1}{S} $$ = sinking fund factor.
-
Example: Life=15 yrs, i=7%, S.F. rate=4% → Y.P. = $$\displaystyle \frac{1}{0.07 + 0.0267} $$ = 10.35.
-
-
Dual Rate of Interest: One rate (i) for return on capital, another (s) for sinking fund to replace asset. Used in Rental Method for old buildings.
-
Gross Income vs Net Income:
-
Gross Income: Total rent receivable (may include vacancies).
-
Net Income: Gross Income - Outgoings (taxes, repairs, insurance, management).
-
-
Scrap Value vs Salvage Value:
-
Scrap Value: Value of completely worn-out asset (only as scrap).
-
Salvage Value: Value of asset at end of useful life if sold as working unit.
-
-
Market Value vs Book Value:
-
Market Value: Current open market price.
-
Book Value: Value shown in accounts (Cost - Depreciation).
-
7.0 SPECIALIZED CONSTRUCTION ESTIMATION
7.1 Estimation for Culverts & Minor Bridges
-
Key Items: Earthwork (excavation, filling), masonry/cement concrete in abutments, wing walls, bed, wearing coat, piers (if any), approaches.
-
Method: Measure quantities from drawings. For earthwork, use mid-sectional area method along the length.
-
Techniques: Pre-cast vs cast-in-situ, foundation type (open, pile), material (brick, stone, RCC).
7.2 Cost Distribution in Building Projects (Approximate %)
| Stage | Typical % of Total Cost | Remarks |
|---|---|---|
| Foundation & Plinth | 8-12% | Earthwork, concrete, masonry. |
| Superstructure (Walls) | 25-30% | Brickwork, RCC columns/beams/slabs. |
| Finishes (Plaster, Floor) | 15-20% | Internal/external plaster, flooring, painting. |
| Water Supply & Sanitary | 5-8% | Pipes, fittings, fixtures. |
| Electrification | 6-8% | Wiring, switches, fixtures. |
| Miscellaneous (DPC, doors, windows) | 10-15% | |
| Overheads, Contingencies, Profit | 15-20% |
7.3 Rough Estimate for Commercial Complex (Cubical Content Method)
-
Step 1: Calculate Total Cubical Content = Plinth Area per floor × Height of each storey × No. of storeys.
-
Given: PA = 500 m², Ht = 3.5 m, Storeys = G+2 = 3.
-
Cubical Content = 500 × 3.5 × 3 = 5250 m³.
-
-
Step 2: Structural Cost = Cubical Content × Rate = 5250 × 1000 = Rs. 52,50,000.
-
Step 3: Add percentages for services (on structural cost):
-
Water Supply & Sanitary = 8% of 52,50,000 = 4,20,000
-
Electrification = 6% = 3,15,000
-
Fluctuation = 5% = 2,62,500
-
-
Step 4: Total (a) = Structural + Services = 52,50,000 + 4,20,000 + 3,15,000 + 2,62,500 = 62,47,500.
-
Step 5: Add Contractor's Profit (10%) & Petty Supervision/Contingencies (3%):
-
Profit = 10% of 62,47,500 = 6,24,750
-
Petty/Supervision = 3% of 62,47,500 = 1,87,425
-
-
Step 6: Total Estimated Cost = 62,47,500 + 6,24,750 + 1,87,425 = \boxed{Rs. 70,59,675}.
8.0 PRACTICAL APPLICATIONS & SHORT NOTES
8.1 Earthwork Volume in Embankment (Numerical)
Given: Length L = 0.5 km = 500 m, Top Width B = 4 m, Depth d = 2 m, Side Slope m = 1.5:1. Volume (for uniform section): $$\displaystyle V = (B + m \cdot d) \times d \times L $$ $$\displaystyle V = (4 + 1.5 \times 2) \times 2 \times 500 $$ $$\displaystyle V = (4 + 3) \times 2 \times 500 = 7 \times 2 \times 500 = 7000 \ \mathbf{m^3} $$.
8.2 Cost Calculation from Quantities
Given: Wall 4m long, 3m high, 0.3m thick.
-
Brickwork Volume = 4 × 3 × 0.3 = 3.6 m³.
- Cost @ Rs. 320/m³ = 3.6 × 320 = Rs. 1,152.
-
Plastering Area (both sides) = 2 × (4 × 3) = 24 m² (ignoring deductions for simplicity).
- Cost @ Rs. 8.50/m² = 24 × 8.5 = Rs. 204.
-
Total Cost = 1152 + 204 = Rs. 1,356.
8.3 Short Notes on High-Frequency Topics
[!TIP] Exam Focus: These are 5m/4m questions. Define clearly, list components/purposes, and give a small example/calculation if relevant.
a) Overhead Charges
Definition: Indirect project expenses not attributable to a specific work item but necessary for project execution.
Components:
- Site office rent, electricity, water.
- Salaries of project manager, engineers, clerks.
- Communication, travel, insurance.
- Taxes, permits, security.
- Typically added as 2-5% to total direct cost.
b) Sinking Fund
Definition: A fund accumulated periodically (annually) to replace a depreciating asset at the end of its useful life.
Importance: Ensures capital availability for renewal without straining current finances; used in valuation of old buildings.
Calculation: Annual Sinking Fund = $$\displaystyle \frac{C \times i}{(1+i)^n - 1} $$ where C = Replacement Cost, i = interest rate, n = life in years.
c) Dual Rate of Interest
Concept: In valuation (Rental Method), two rates are used:
- Interest Rate (i): Return on capital invested (e.g., 7%).
- Sinking Fund Rate (s): Rate at which fund accumulates to replace asset (e.g., 4%).
Application: Year's Purchase (Y.P.) = $$\displaystyle \frac{1}{i + \frac{1}{S}} $$ where $$\displaystyle \frac{1}{S} $$ is sinking fund factor. Used for valuing old properties with limited remaining life.
d) Bill of Quantities (BOQ) & Abstract Sheet
- BOQ: Detailed list of all work items with quantities, units, and rates. Part of tender document. Allows contractors to price uniformly.
- Abstract Sheet: Summary of BOQ showing item-wise cost and total estimated cost. Prepared after detailed estimate.
Difference: BOQ is detailed; Abstract is condensed summary.
e) Tender Notice
Definition: Public advertisement inviting bids from contractors for a project.
Contents: Name of work, estimated cost, time for completion, earnest money, date of submission, address for sale of tender documents, eligibility criteria, last date, place of opening.
Purpose: To obtain competitive bids, ensure transparency, select lowest qualified bidder.
f) Task Work
Definition: Standard output of work (quantity) that a worker should complete in a normal working day (8 hours).
Factors Affecting:
- Type of work (masonry, plastering).
- Skill and efficiency of worker.
- Tools and equipment used.
- Site conditions (space, height).
- Material availability at work point.
- Supervision and method of work.