Skip to content
CE-503 (B) · Construction Planning & Management/Quick Revision Short Notes

Construction Planning & Management (CE-503 (B)) - Unit 3 Short Notes

UNIT 3: CONSTRUCTION ESTIMATION, COSTING & VALUATION

1.0 FUNDAMENTALS OF ESTIMATION & COSTING

1.1 Purpose and Importance of Estimation

  • Purpose: To ascertain the probable cost of a proposed construction project before commencement.

  • Importance:

    • Financial Planning: Determines capital requirement, funding needs, and feasibility.

    • Decision Making: Helps choose between alternatives (e.g., materials, methods).

    • Contract Basis: Forms the foundation for tender documents and contract agreements.

    • Control: Provides a benchmark for cost control during execution.

    • Valuation: Essential for property valuation, sale, purchase, and mortgage.

1.2 Principle of Units

Standard units for measurement ensure uniformity and comparability.

Item of Work Standard Unit
Earthwork (Excavation/Filling) Cubic meter (m³)
Brickwork/Stonework Cubic meter (m³)
Plastering/Painting Square meter (m²)
Flooring, Roofing Square meter (m²)
Doors, Windows, etc. Each (Nr.) or Square meter (m²)
Lumpsum Items Item (L.S.)

1.3 Types of Estimates

Type of Estimate Description When Used Accuracy
Rough/Approximate Based on plinth area, cubic content, or service unit. Quick, no detailed quantities. Preliminary studies, feasibility reports. ±10-20%
Detailed Item-by-item quantity take-off from drawings. Includes Abstract & BOQ. Final sanction, tender, construction. ±2-5%
Revised Prepared when original estimate is exceeded due to material change in scope (e.g., design alteration, site conditions). Requires fresh sanction. Major deviations from original plan. High
Supplementary Prepared for additional/modified work not in original estimate, but within original scope. Requires separate sanction. Minor additions/alterations. Moderate
Detailed vs Abstract Detailed Estimate: Item-wise quantities & rates calculated on paper. Abstract: Summarized cost statement from detailed estimate.

[!TIP] Exam Distinction: Revised Estimate = Material change in scope (fresh sanction). Supplementary Estimate = Additional work within original scope (separate sanction).

1.4 Key Financial & Costing Concepts

  • Overhead Charges (Establishment Charges): Indirect expenses of the project office (site staff salary, office rent, utilities, etc.). Added as a percentage to the total of direct costs.

  • Contingencies: Provision for unforeseen minor items/price fluctuations (typically 2-5%). Not for major scope changes.

  • Contractor's Profit: Added to total cost (direct + overheads) as a percentage (typically 10%).

  • Petty Supervision Charges: Charges for site supervision by owner's engineer (1-2%).

  • Fluctuation of Rates (Escalation): Clause in contract for adjusting material/labour rates due to market inflation beyond a base date.

  • Work Charge Establishment: Temporary facilities at site (sheds, storage, water supply) – part of overheads.


2.0 METHODS OF ESTIMATION & QUANTITY TAKE-OFF

2.1 Building Estimation: Long Wall & Short Wall Method

  • Procedure: For walls with cross walls. Long walls run parallel to the length of the building. Short walls run parallel to the breadth.

  • Formulas:

    • Length of Long Wall = (Center to Center Length of Room) - (2 × Half Width of Wall) + (2 × Length of Wall Beyond Inner Face of Parapet)

    • Length of Short Wall = (Center to Center Breadth of Room) - (2 × Half Width of Wall) + (0.3 m for parapet)

  • Example: For a room 5m x 4m with 0.3m thick walls:

    • Long Wall Length = (5 + 0.3) - (2 × 0.15) = 5.0m (at plinth level)

    • Short Wall Length = (4 + 0.3) - (2 × 0.15) = 4.0m (at plinth level)

  • Centre Line Method: Faster for rectangular buildings without cross walls. Total center line length × width × height. Not suitable for buildings with internal cross walls.

2.2 Earthwork Estimation for Roads

  • Mid-Sectional Area Method:

    • Volume = Area of Mid-Section × Distance between CS

    • Area of Mid-Section = (B + md) × d (for embankment) where B=top width, m=side slope, d=depth at mid-section.

    • Application: When cross-sections are taken at regular intervals (chainages).

  • Mean Sectional Area Method:

    • Volume = (A₁ + A₂) / 2 × L

    • Where A₁, A₂ = areas of two consecutive cross-sections, L = distance between them.

    • Application: When only two end sections are known.

2.3 Deduction Rules for Masonry & Plastering

  • No deduction for openings < 0.1 m².

  • For openings ≥ 0.1 m²:

    • Masonry: Deduct full opening area. Add lintel/sill volume (if specified).

    • Plastering/Painting: Deduct only one face of the opening area. For jambs, add perimeter of opening × thickness of plaster.

  • For RCC bands, lintels, etc.: Deduct full volume from masonry if they replace masonry.

2.4 Material Statement Preparation

  • For R.C.C. (M20 = 1:1.5:3): For 1 m³ concrete:

    • Cement = $$\displaystyle \frac{1}{1+1.5+3} \times 1.54 $$ (dry volume factor) = 0.272 m³ ≈ 8 bags (since 1 bag = 0.035 m³)

    • Sand = $$\displaystyle \frac{1.5}{5.5} \times 1.54 $$ = 0.42 m³

    • Aggregate = $$\displaystyle \frac{3}{5.5} \times 1.54 $$ = 0.84 m³

    • Water-Cement Ratio = 0.5 → Water = 0.5 × 0.272 × 1000 = 136 liters

    • Note: 1.54 accounts for voids in dry mix. For M15 (1:2:4), adjust ratios.

  • For Brickwork (1:6): For 1 m³ brickwork:

    • Bricks = 500 (standard size 19x9x9 cm with mortar)

    • Mortar = 0.3 m³ (approx). Cement = $$\displaystyle \frac{1}{7} \times 0.3 \times 1.54 $$ = 0.066 m³ ≈ 2 bags. Sand = $$\displaystyle \frac{6}{7} \times 0.3 \times 1.54 $$ = 0.396 m³.


3.0 PREPARATION OF DETAILED ESTIMATE

3.1 Data Required

  1. Drawings: Plan, elevation, section, foundation details.

  2. Specifications: Material quality, workmanship standards, mortar/concrete grades.

  3. Rates: Current schedule of rates (CSR) or prevailing market rates.

  4. Dimensions: All measurements from drawings.

  5. Site Conditions: Soil report, access, water availability.

3.2 Step-by-Step Procedure

  1. Take-off Quantities: Item-wise measurement from drawings using standard units.

  2. Calculate Abstract: Enter quantities and compute cost (Qty × Rate) for each item.

  3. Add Miscellaneous: Include contingencies, supervision charges.

  4. Add Contractor's Profit: On total (direct + overheads).

  5. Prepare Abstract Sheet & BOQ: Summarize all items and costs.

3.3 Factors to Consider

  • Site conditions (soil, terrain, access).

  • Availability of materials and labour.

  • Construction sequence and methodology.

  • Local bylaws and regulations.

  • Seasonal variations (monsoon impact).

  • Waste and wastage percentages.

3.4 Abstract of Estimate & BOQ

  • Abstract Sheet: Summary table showing item no., description, quantity, rate, amount, and total cost.

  • Bill of Quantities (BOQ): Detailed list of all work items with quantities, units, and rates. Forms part of tender document.

3.5 Item-wise Estimation (Foundation to Superstructure)

  1. Earthwork in Excavation: Measure net volume (length × breadth × depth). Deduct for plinth.

  2. Lime Concrete in Foundation: Measure over plinth area × average thickness (usually 30 cm).

  3. Brickwork in Foundation/Plinth: Use long/short wall method for lengths. Deduct for openings if any.

  4. Brickwork in Superstructure: Similar to above, up to top of lintel level.

  5. Damp Proof Course (DPC): Measured in square meters over plinth area.

  6. Plastering: Measured in square meters of surface area. Deduct openings (one face), add jambs.


4.0 RATE ANALYSIS & COST DETERMINATION

4.1 Definition & Objective

  • Definition: Breaking down the cost of an item into its constituents (material, labour, equipment, overheads, profit) to determine a rational rate per unit.

  • Objective: To fix a fair price for the item, understand cost drivers, and prepare accurate estimates.

4.2 Factors Affecting Rate Analysis

Factor Considerations
Material Costs Cost of basic material + wastage (5-10%) + transport.
Labour Costs No. of workers, skill level, daily wages, productivity (output/day).
Equipment/Tool Costs Hire charges or depreciation of tools/plants.
Overheads & Profit Site overheads (1-2%), establishment (2-5%), contractor's profit (10%).

4.3 Procedure for Rate Analysis (Example: 1:4 Brickwork)

  1. Calculate Material Cost:

    • Bricks for 1 m³ = 500 nos. @ Rs. X/brick.

    • Mortar (1:4) for 1 m³ = 0.3 m³. Cement = $$\displaystyle \frac{1}{5} \times 0.3 \times 1.54 $$ = 0.0924 m³ (≈ 2.6 bags). Sand = $$\displaystyle \frac{4}{5} \times 0.3 \times 1.54 $$ = 0.37 m³.

    • Total Material Cost = (Bricks + Cement + Sand).

  2. Calculate Labour Cost: Based on output (e.g., 1 mason + 2 helpers can build 1 m³/day).

  3. Add Tools & Tackles: 1-2% of labour cost.

  4. Add Overheads: 2-5% of (Material + Labour).

  5. Add Profit: 10% of (Material + Labour + Overheads).

  6. Total Rate/Unit = Sum of all above.

4.4 Cost Estimates for Specific Services

  • Water Supply & Sanitary: Typically 5-8% of structural cost. Includes pipes, fittings, fixtures, septic tank, soak pit.

  • Electrification: Typically 6-8% of structural cost. Includes wiring, switches, fixtures, distribution boards.

  • Drainage Works: Typically 3-5% of structural cost. Includes external drains, inspection chambers, connections.


5.0 SCHEDULE OF RATES (SOR) & PROJECT REPORTS

5.1 Current Schedule of Rates (CSR)

  • Definition: A document issued by government/public works departments (PWD, CPWD, NHAI) listing standardized rates for various items of work in a specific region/period.

  • Purpose: Provides uniform rates for estimating, tendering, and payment. Prevents disputes.

  • Preparation Authority: PWD (State), CPWD (Central), MES, etc.

  • Components:

    • Material rates (at site/stockyard).

    • Labour rates (skilled, semi-skilled, unskilled).

    • Hire charges for equipment.

    • Standard constants (e.g., output of labour, material consumption per m³).

5.2 Detailed Project Report (DPR)

  • Purpose: Comprehensive document for project appraisal, financing, and execution. Required for bank loans, government approval.

  • Contents:

    1. Executive Summary: Project snapshot.

    2. Technical Feasibility: Location, site details, design parameters, construction methodology.

    3. Cost Estimates: Detailed abstract, year-wise phasing, escalation.

    4. Financial Analysis: Sources of finance, loan schedule, profitability, IRR, NPV.

    5. Implementation Schedule: Bar chart/PERT chart, milestones.

    6. Market Analysis: Demand, supply, pricing strategy (for commercial projects).

    7. Risk Analysis & Mitigation.


6.0 VALUATION PRINCIPLES & METHODS

6.1 Definitions & Differentiation

Term Definition
Value Worth of property in open market at a given time.
Cost Actual expenditure incurred in construction/purchase.
Price Amount asked/offered in a transaction (may differ from value).
Valuation Process of estimating the Market Value of a property.
Valuer Professional who performs valuation. Functions: estimate value, prepare reports, expert witness.

6.2 Purpose of Valuation

  • Sale/Purchase, Mortgage/Loan, Insurance, Taxation (property tax, wealth tax), Rent fixation, Compulsory acquisition, Litigation.

6.3 Methods of Valuation

Method Principle Formula / Key
1. Rental Method Value = Capitalized Net Income. Used for income-producing properties. Value = $$\displaystyle \frac{\text{Net Annual Income}}{\text{Rate of Capitalization}} $$
2. Direct Comparison Compare with similar recent transactions in same locality. Adjust for differences. Value = Adjusted Sale Price of Comparable.
3. Cost Method Value = Replacement/Reproduction Cost - Depreciation. Used for new/specialized properties. Value = (Land Value + Cost of Construction) - Depreciation
4. Development Method Value = Anticipated Sale Value of Developed Property - Total Development Cost. Used for vacant land/development potential. Residual Value = Sale Value - (Construction Cost + Interest + Profit)

6.4 Key Valuation Concepts

  • Sinking Fund: Fund accumulated to replace an old asset at end of its life. Importance: Provides capital for renewal without burdening current revenue.

    • Calculation: Annual Sinking Fund = $$\displaystyle \frac{C \times i}{(1+i)^n - 1} $$ where C = Replacement Cost, i = interest rate, n = life.
  • Year's Purchase (Y.P.): Multiplier used to capitalize net annual income into capital value.

    • Formula (Dual Rate): Y.P. = $$\displaystyle \frac{1}{i + \frac{1}{S}} $$ where i = interest rate on capital, $$\displaystyle \frac{1}{S} $$ = sinking fund factor.

    • Example: Life=15 yrs, i=7%, S.F. rate=4% → Y.P. = $$\displaystyle \frac{1}{0.07 + 0.0267} $$ = 10.35.

  • Dual Rate of Interest: One rate (i) for return on capital, another (s) for sinking fund to replace asset. Used in Rental Method for old buildings.

  • Gross Income vs Net Income:

    • Gross Income: Total rent receivable (may include vacancies).

    • Net Income: Gross Income - Outgoings (taxes, repairs, insurance, management).

  • Scrap Value vs Salvage Value:

    • Scrap Value: Value of completely worn-out asset (only as scrap).

    • Salvage Value: Value of asset at end of useful life if sold as working unit.

  • Market Value vs Book Value:

    • Market Value: Current open market price.

    • Book Value: Value shown in accounts (Cost - Depreciation).


7.0 SPECIALIZED CONSTRUCTION ESTIMATION

7.1 Estimation for Culverts & Minor Bridges

  • Key Items: Earthwork (excavation, filling), masonry/cement concrete in abutments, wing walls, bed, wearing coat, piers (if any), approaches.

  • Method: Measure quantities from drawings. For earthwork, use mid-sectional area method along the length.

  • Techniques: Pre-cast vs cast-in-situ, foundation type (open, pile), material (brick, stone, RCC).

7.2 Cost Distribution in Building Projects (Approximate %)

Stage Typical % of Total Cost Remarks
Foundation & Plinth 8-12% Earthwork, concrete, masonry.
Superstructure (Walls) 25-30% Brickwork, RCC columns/beams/slabs.
Finishes (Plaster, Floor) 15-20% Internal/external plaster, flooring, painting.
Water Supply & Sanitary 5-8% Pipes, fittings, fixtures.
Electrification 6-8% Wiring, switches, fixtures.
Miscellaneous (DPC, doors, windows) 10-15%
Overheads, Contingencies, Profit 15-20%

7.3 Rough Estimate for Commercial Complex (Cubical Content Method)

  • Step 1: Calculate Total Cubical Content = Plinth Area per floor × Height of each storey × No. of storeys.

    • Given: PA = 500 m², Ht = 3.5 m, Storeys = G+2 = 3.

    • Cubical Content = 500 × 3.5 × 3 = 5250 m³.

  • Step 2: Structural Cost = Cubical Content × Rate = 5250 × 1000 = Rs. 52,50,000.

  • Step 3: Add percentages for services (on structural cost):

    • Water Supply & Sanitary = 8% of 52,50,000 = 4,20,000

    • Electrification = 6% = 3,15,000

    • Fluctuation = 5% = 2,62,500

  • Step 4: Total (a) = Structural + Services = 52,50,000 + 4,20,000 + 3,15,000 + 2,62,500 = 62,47,500.

  • Step 5: Add Contractor's Profit (10%) & Petty Supervision/Contingencies (3%):

    • Profit = 10% of 62,47,500 = 6,24,750

    • Petty/Supervision = 3% of 62,47,500 = 1,87,425

  • Step 6: Total Estimated Cost = 62,47,500 + 6,24,750 + 1,87,425 = \boxed{Rs. 70,59,675}.


8.0 PRACTICAL APPLICATIONS & SHORT NOTES

8.1 Earthwork Volume in Embankment (Numerical)

Given: Length L = 0.5 km = 500 m, Top Width B = 4 m, Depth d = 2 m, Side Slope m = 1.5:1. Volume (for uniform section): $$\displaystyle V = (B + m \cdot d) \times d \times L $$ $$\displaystyle V = (4 + 1.5 \times 2) \times 2 \times 500 $$ $$\displaystyle V = (4 + 3) \times 2 \times 500 = 7 \times 2 \times 500 = 7000 \ \mathbf{m^3} $$.

8.2 Cost Calculation from Quantities

Given: Wall 4m long, 3m high, 0.3m thick.

  • Brickwork Volume = 4 × 3 × 0.3 = 3.6 m³.

    • Cost @ Rs. 320/m³ = 3.6 × 320 = Rs. 1,152.
  • Plastering Area (both sides) = 2 × (4 × 3) = 24 m² (ignoring deductions for simplicity).

    • Cost @ Rs. 8.50/m² = 24 × 8.5 = Rs. 204.
  • Total Cost = 1152 + 204 = Rs. 1,356.

8.3 Short Notes on High-Frequency Topics

[!TIP] Exam Focus: These are 5m/4m questions. Define clearly, list components/purposes, and give a small example/calculation if relevant.

a) Overhead Charges

Definition: Indirect project expenses not attributable to a specific work item but necessary for project execution.

Components:

  • Site office rent, electricity, water.
  • Salaries of project manager, engineers, clerks.
  • Communication, travel, insurance.
  • Taxes, permits, security.
  • Typically added as 2-5% to total direct cost.

b) Sinking Fund

Definition: A fund accumulated periodically (annually) to replace a depreciating asset at the end of its useful life.

Importance: Ensures capital availability for renewal without straining current finances; used in valuation of old buildings.

Calculation: Annual Sinking Fund = $$\displaystyle \frac{C \times i}{(1+i)^n - 1} $$ where C = Replacement Cost, i = interest rate, n = life in years.

c) Dual Rate of Interest

Concept: In valuation (Rental Method), two rates are used:

  1. Interest Rate (i): Return on capital invested (e.g., 7%).
  1. Sinking Fund Rate (s): Rate at which fund accumulates to replace asset (e.g., 4%).

Application: Year's Purchase (Y.P.) = $$\displaystyle \frac{1}{i + \frac{1}{S}} $$ where $$\displaystyle \frac{1}{S} $$ is sinking fund factor. Used for valuing old properties with limited remaining life.

d) Bill of Quantities (BOQ) & Abstract Sheet

  • BOQ: Detailed list of all work items with quantities, units, and rates. Part of tender document. Allows contractors to price uniformly.
  • Abstract Sheet: Summary of BOQ showing item-wise cost and total estimated cost. Prepared after detailed estimate.

Difference: BOQ is detailed; Abstract is condensed summary.

e) Tender Notice

Definition: Public advertisement inviting bids from contractors for a project.

Contents: Name of work, estimated cost, time for completion, earnest money, date of submission, address for sale of tender documents, eligibility criteria, last date, place of opening.

Purpose: To obtain competitive bids, ensure transparency, select lowest qualified bidder.

f) Task Work

Definition: Standard output of work (quantity) that a worker should complete in a normal working day (8 hours).

Factors Affecting:

  • Type of work (masonry, plastering).
  • Skill and efficiency of worker.
  • Tools and equipment used.
  • Site conditions (space, height).
  • Material availability at work point.
  • Supervision and method of work.
Go to where you left off?

Quick Add to Notes

Save questions, your own notes and screenshots into notes filed by unit. It takes a free account.

Create free account

Have an account? Log in