Skip to content
CE-505 · Quantity Surveying & Costing (Lab)/Quick Revision Short Notes

Quantity Surveying & Costing (Lab) (CE-505) - Unit 4 Short Notes

4.1 Advanced Measurement & Pricing for Complex Elements

4.1.1 Measurement of Complex Building Components

  • Curtain Walling & Façades: Measured in m² of overall wall area. Includes glazing, framing, fixings, and weatherproofing. Separate items for special glass (e.g., double/triple, low-E, laminated) and bespoke panels.

  • Specialized Roofing:

    • Green Roofs: Measured in m² of planted area. Layers include waterproofing, root barrier, drainage, filter fabric, growing medium, and plants.

    • Tensile Fabric: Measured in m² of fabric area. Includes membrane, cables, masts, foundations, and hardware.

  • MEP Services (Mechanical, Electrical, Plumbing):

    • Ductwork: Measured in m² of surface area (for fabrication) or m of length (for installation). Classified by size, material (GI, aluminum), and insulation.

    • Piping: Measured in m of length. Includes pipes, fittings, valves, supports, insulation, and testing.

    • Wiring: Measured in m of length for circuits. Includes conduits, cables, boxes, and devices (switches, sockets).

    • Equipment: Measured as "item" (e.g., AHU, pump, panel). Includes supply, installation, testing, and commissioning.

  • Internal Fit-out & Partitions: Measured in m² for partitions (by type: stud, glass, solid). Includes all components: framing, panels, doors, finishes, and skirting.

4.1.2 Advanced Pricing Strategies

  • Bespoke/Custom Elements: Priced via detailed unit rate analysis. Requires breakdown of:

    • Labour: Hours × rate (skilled/unskilled).

    • Plant: Hire cost + operator.

    • Materials: Net cost + wastage + delivery.

    • Overheads & Profit: Applied as % of direct costs.

  • Provisional Sums & Prime Cost Items:

    • Provisional Sum: Estimated cost for defined scope of work not fully detailed at tender stage. Tenderers add % for overheads/profit.

    • Prime Cost (PC) Sum: Estimated cost for supply only of specific items (e.g., sanitary ware, kitchen units). Tenderer adds for fixing, wastage, and profit.

  • Dayworks Rates: Used for unforeseen work where measurement is impractical. Rate = (Labour cost + Plant cost + Materials cost) × (1 + Overheads % + Profit %).

    [!TIP] Exam Focus: Be prepared to calculate a dayworks rate from given labour, plant, and material costs, and to distinguish when provisional sums vs. dayworks are appropriate.


4.2 Cost Planning, Control, and Value Management

4.2.1 Elemental Cost Planning & Cost Models

  • Elemental Cost Plan: Breaks total project cost into standard functional elements (e.g., substructure, superstructure, finishes, services). Format often follows BCIS (Building Cost Information Service) elemental classification.

  • Cost Modeling: Creating a mathematical relationship between cost and key project variables (e.g., cost/m², cost/bedroom). Used for early-stage budgeting and benchmarking against similar buildings.

  • Benchmarking: Comparing project cost data ( elemental rates, cost/m²) against industry averages (from BCIS, RICS, or internal databases) to assess reasonableness.

4.2.2 Cost Control & Variance Analysis

  • Monitoring: Regular comparison of actual cost (from invoices, valuations) against budgeted cost (cost plan/estimate).

  • Forecasting Final Account:

    • Estimate at Completion (EAC) = Actual Cost to Date + Estimated Cost to Complete.

    • S-Curve Analysis: Graph plotting cumulative cost (or value) against time. Shows project spend profile and helps identify deviations from planned cash flow.

  • Variance Analysis (CRITICAL FORMULAS):

    • Cost Variance (CV): CV = Earned Value (EV) - Actual Cost (AC)

      • CV > 0: Under budget (favourable)

      • CV < 0: Over budget (unfavourable)

    • Schedule Variance (SV): SV = Earned Value (EV) - Planned Value (PV)

      • SV > 0: Ahead of schedule

      • SV < 0: Behind schedule

    • Earned Value (EV): Budgeted cost for work actually performed.

    • Planned Value (PV): Budgeted cost for work planned to be completed by a date.

    • Actual Cost (AC): Actual cost incurred for work performed.

4.2.3 Value Management (VM) vs. Value Engineering (VE)

Aspect Value Management (VM) Value Engineering (VE)
Timing Pre-construction / Design Phase Any phase, often design or post-contract
Primary Goal Maximize value (function / cost) for client Improve value by eliminating unnecessary cost
Focus Client's value system, objectives, needs Function of a component/system
Methodology Job Plan, stakeholder workshops, FAST diagrams Function Analysis, creative/ evaluation phases
Outcome Optimized project brief, cost planning Cost-saving proposals, design alternatives

[!TIP] Exam Focus: Know the difference between VM (strategic, client-focused) and VE (tactical, function-focused). Be able to interpret CV and SV from a given scenario.


4.3 Life Cycle Costing (LCC) & Whole Life Costing (WLC)

4.3.1 Concepts & Importance

  • Capital Cost (CC): Initial construction cost.

  • Operational Cost (OC): Recurring costs during building life: energy, water, maintenance, cleaning, repairs, management.

  • Life Cycle Cost (LCC): LCC = Capital Cost + ∑ (Present Value of all Future Operational Costs)

  • Whole Life Cost (WLC): Broader than LCC; may include land acquisition, disposal costs, and non-monetary factors (e.g., environmental impact).

  • Rationale: A higher capital cost option may have lower operational costs, leading to lower total LCC over the building's life.

4.3.2 LCC Analysis Procedure & Key Formulas

  1. Identify Alternatives: Different designs, materials, or systems.

  2. Estimate Costs: Capital cost and all relevant recurring/non-recurring operational costs for each alternative over the study period (e.g., 30 years).

  3. Discount Future Costs to Present Value (PV): Using a discount rate (reflects time value of money, risk, inflation).

    • Present Value (PV) of a future cost: PV = Future Cost / (1 + i)^n

      • i = discount rate per period

      • n = number of periods

  4. Sum all Present Values: LCC = CC + PV(OC1) + PV(OC2) + ...

  5. Compare LCCs: The alternative with the lowest LCC is the most economical over the study period.

  6. Annual Equivalent Cost (AEC): Converts LCC into an equal annual cost for easier comparison.

    AEC = LCC × [ i(1+i)^n / ((1+i)^n - 1) ]

    Where i = discount rate, n = study period in years.

[!TIP] Exam Focus: Be proficient in numerical problems. Given cash flows and a discount rate, calculate PV of each cost, sum to get LCC, and/or convert to AEC. Always state your study period and discount rate assumption.


4.4 Risk, Contingency, and Inflation in Costing

4.4.1 Risk Identification & Analysis

  • Sources: Design changes, ground conditions, labour/material shortages, weather, client changes, regulatory changes.

  • Qualitative Analysis: Risk matrix (Probability × Impact) to rank risks as High/Medium/Low.

  • Quantitative Analysis:

    • Expected Monetary Value (EMV): EMV = Probability of Risk Occurrence × Financial Impact if it Occurs

    • Contingency Calculation (Simplified): Sum of EMVs for all identified risks.

4.4.2 Contingency Allowances

  • Design Contingency (Estimating Contingency): Included in the base estimate (typically 5-10%) to cover incomplete design and pricing inaccuracies.

  • Project Contingency (Management Reserve): Separate sum for unforeseen risks not in the base estimate. Managed by the client/project manager.

  • Calculation Methods:

    1. Percentage of Cost: Simple, but arbitrary.

    2. Risk-Based (EMV Sum): More defensible. Sum of EMVs from risk register.

    3. Monte Carlo Simulation: Computer-based, runs thousands of project cost scenarios using probability distributions for individual cost items to predict a probability distribution of total project cost.

4.4.3 Handling Inflation & Fluctuations

  • Price Adjustment (Fluctuation) Clauses: Adjust the contract sum based on changes in published indices (e.g., Retail Price Index - RPI, Consumer Price Index - CPI, or specific material/labour indices).

  • Formula (Common Format): Adjustment = (Current Index - Base Index) / Base Index × (Proportion of Contract Sum)

    • Proportion is the % of the contract sum deemed to be subject to fluctuation (e.g., 20% for labour, 30% for materials).
  • Purpose: Protects both client and contractor from unforeseen inflation during the contract period.

[!TIP] Exam Focus: Calculate EMV for given risks. Distinguish between design and project contingency. Apply a simple price adjustment formula to a contract sum.


4.5 Sustainability, Green Building, and Cost Implications

4.5.1 Costing for Sustainable Design

  • Initial Cost Premium: Extra capital cost for sustainable features (e.g., high-performance glazing, solar panels, rainwater harvesting, sustainable materials).

  • Long-Term Payback: Lower operational costs (energy, water, maintenance) over the building's life. Justified via LCC analysis.

  • Certification Costs (LEED, BREEAM, GRIHA): Include fees for assessors, documentation, and potential premium for certified materials/products.

  • Measurement & Pricing: Must identify and price specific sustainable items separately (e.g., recycled content insulation, low-VOC paints, photovoltaic systems).

4.5.2 Life Cycle Assessment (LCA) & Cost

  • LCA: Quantifies environmental impacts (carbon footprint, energy use, water use) over a product's or building's life.

  • Linking to Cost: The goal is to find the optimal point where environmental benefit (reduced LCA impact) is achieved at an acceptable cost increase or results in operational cost savings.

  • Cost-Benefit Evaluation: Compare options using a matrix of Capital Cost vs. Operational Cost Savings vs. Environmental Impact Reduction.

[!TIP] Exam Focus: You may be asked to evaluate a sustainable option. Use LCC to show if the operational savings justify the capital premium. Mention non-monetary benefits (e.g., ESG, occupant health).


4.6 Final Account Preparation & Dispute Resolution

4.6.1 The Final Account Process

  1. Compilation: Quantity Surveyor (for contractor) or Contract Administrator gathers all agreed variations, provisional sum finalizations, prime cost item adjustments, and retention money details.

  2. Reconciliation: Compare final measured/valued work against the contract sum and all variation orders.

  3. Settlement: Negotiate and agree the final sum with the client/engineer. Prepare the Final Account Statement showing:

    • Original Contract Sum

    • +/- Agreed Variations

    • +/- Adjustments to Provisional/PC Sums

    • +/- Retention Money Released

    • Final Certified Sum

  4. Documentation: All supporting documents (variation registers, measurement sheets, agreements) are filed.

4.6.2 Claims and Disputes

  • Types of Claims:

    • Extension of Time (EOT): Claim for additional time due to delays (client risk events).

    • Loss and Expense: Claim for financial loss (not just time) due to client-caused delays or disruptions.

  • Substantiation: Claim must be supported by:

    • Cause: Link to a client risk event (e.g., variation, late instruction).

    • Effect: Proof of delay (programme analysis) or financial loss (cost records).

    • Quantum: Detailed calculation of costs (labour, plant, material, overheads) or extension period.

  • Dispute Resolution (Hierarchy):

    1. Negotiation: Direct discussion between parties.

    2. Adjudication: Fast, interim binding decision (common in UK/Commonwealth contracts).

    3. Arbitration: Private, final and binding (like court but private).

    4. Litigation: Public court process, final and binding.

[!TIP] Exam Focus: Scenario-based questions. Given a delay event, identify if it's a client risk, and outline the steps to substantiate an EOT and/or loss & expense claim. Know the difference between EOT (time) and loss & expense (money).


4.7 Digital Tools & Software Applications in Costing (Lab Core)

4.7.1 Cost Database Management

  • Sources: BCIS (UK), Spons (UK), RSMeans (USA), RICS data, or in-house historical data.

  • Management: Updating for location factors (e.g., city vs. rural), time adjustments (inflation indices), and project-specific adjustments (size, complexity).

  • Application: Provides benchmark elemental rates (e.g., £/m² for superstructure) for early cost planning and checking tender prices.

4.7.2 Building Information Modeling (BIM) for Costing (5D BIM)

  • 5D BIM: Integration of 3D Model + Cost Data (4D is time/scheduling).

  • Process:

    1. Model Authoring: Design in BIM software (e.g., Autodesk Revit).

    2. Model Validation: Check for clashes (using Navisworks) – clashes can cause cost implications (rework).

    3. Quantity Take-Off (QTO): Use BIM software or dedicated tools (CostX, Innovaya, Vico Office) to automatically extract quantities (e.g., length of wall, area of floor) from the model.

    4. Cost Linking: Link extracted quantities to a cost database/unit rates to generate an estimate.

  • Advantages: Faster, more accurate QTO; instant update of cost when model changes; better visualization of cost distribution.

4.7.3 Specialized Cost Estimation Software

  • Functions:

    • Item Library/Database: Pre-built assemblies and unit rates.

    • Take-off Tools: On-screen measurement from PDFs/Drawings (e.g., Bluebeam Revu), or direct from BIM models.

    • Assembly Building: Group items into logical assemblies (e.g., "external wall - brick/block/insulation/plaster").

    • Reporting: Generate detailed estimates, summaries, and comparison reports.

  • Common Software: WinEst (Sierra), CostX (Exactal/Trimble), Bluebeam (for take-off), Vico Office (BIM 5D).

  • Lab Focus: Creating a complete estimate from given drawings using software: setting up a project, taking off quantities, applying rates, and producing a final report with elemental summaries.

[!TIP] LAB EXAM FOCUS: Be able to perform a basic quantity take-off in software like CostX or Bluebeam from a simple drawing. Understand the workflow: Open drawing -> calibrate -> measure (length, area, count) -> assign item from cost book -> generate report. Know the key advantage of BIM-based costing: model change automatically updates quantities and cost.

Go to where you left off?

Quick Add to Notes

Save questions, your own notes and screenshots into notes filed by unit. It takes a free account.

Create free account

Have an account? Log in